Reactive Supply and Voltage Control Compensation

Under Schedule 2 of the PJM Tariff, generation owners may submit for filing at FERC pursuant to Section 205 of the Federal Power Act and Part 35 of the Commission’s regulations a rate schedule for Reactive Supply and Voltage Control from Generation Sources Service for VAR capability. The Rate Schedule specifies the generator’s revenue requirement for Reactive Supply and Voltage Control from Generation Sources Service from the generating facility.

Proposed Timeline

Issue initiated: 6.9.2021
Work begins: 11.5.2021
Target Completion: 7.31.2023
Actual Completion: 8.9.2023

Issue Details

Stakeholder Body Reactive Power Compensation Task Force
Facilitator Croop, Danielle
Subject Matter Expert Boyle, Glen
Problem Statement/
Issue Charge First Read
3.10.2021
Issue Catalyst Dominion & IMM
Issue Status Closed
Manual Changes No
  • Stakeholder Process Step

  • Completed Approved
  • Completed Education
  • Completed Interest
  • Completed Design
  • Completed Options
  • Completed Packages
  • Completed Consensus
  • Completed Review
  • Completed Completed