Planning

Most Recently Approved RTEP Updates
As of 6:50 a.m. EPT

Competitive Planning Process
  • The PJM competitive planning process affords non-incumbent transmission developers an opportunity to participate in the regional planning and expansion of the PJM bulk electric system.
  • 2023 RTEP Window 1
     open7.24.2023 closed9.22.2023
Planning News from Inside Lines
  • FERC Filing Marks PJM’s Second Collaboration With New Jersey on Offshore Wind Transmission Study
    PJM and the New Jersey Board of Public Utilities have agreed to the terms on the next phase of a historic collaboration that deploys PJM’s competitive planning process to help New Jersey further advance its ambitious offshore wind goals. This next phase of the State Agreement Approach Study Agreement (referred to as “SAA 2.0”), signed […]
  • Transition Cycle 1 of New Interconnection Process Begins Jan. 22
    Transition Cycle 1 of PJM’s reformed interconnection process officially starts Jan. 22 when PJM will begin performing System Impact Studies on 308 projects representing 46,000 MW of new, mostly renewable, generation. Projects that were classified as Transition Cycle 1 (TC1) from the recent Transition Sorting Retool analysis will be analyzed using a cluster-based study approach. […]
Queued Generation Fuel Mix
As of 5:37 a.m. EPT
Total:
177,607 MW
Renewables:
91,061 MW
Generation Interconnection Requests by Fuel Type
As of 5:37 a.m. EPT
Queues Timeline
As of 1.22.2024 7:49 a.m. EPT
Criteria & Guidelines