Planning

Most Recently Approved RTEP Updates
transmission-under-construction

122 New Projects

5 Project Scope/Cost Change

0 Project Cancellations

Learn How PJM Plans the Future
As of 1:56 p.m. EPT

Competitive Planning Process
  • The PJM competitive planning process affords non-incumbent transmission developers an opportunity to participate in the regional planning and expansion of the PJM bulk electric system.
  • 2025 RTEP Window 1
     open6.18.2025 closed8.18.2025
Planning News from Inside Lines
  • Stakeholder Process on Backstop Procurement and Connect and Manage Moves Forward
    PJM and stakeholders on June 30 concluded an expedited series of sessions to help the PJM Board of Managers devise a proposal to reliably accommodate data center growth by facilitating bilateral transactions while allocating costs for new generation procured by PJM in an upcoming backstop procurement. PJM’s Critical Issue Fast Path process produced parallel sets […]
  • New Interconnection Process Delivers
    PJM highlights the latest milestones of its reformed interconnection process in an updated fact sheet (PDF). More than 800 projects reflecting 220 GW of capacity are being studied in the first Cycle of the new process. There is no longer a backlog of new service requests, as all generation projects seeking to connect with the […]
Generation Interconnection Requests by Fuel Type
(Active projects only)
As of 11:56 a.m. EPT

Projects Under Construction by MW
As of 11:56 a.m. EPT
Total:
52,184 MW
Cycle Timeline
As of 6.5.2026 10:58 a.m. EPT