Primary Frequency Response Requirement

Primary Frequency Response (PFR) is an essential reliability product and is needed to ensure system reliability and stability in both real-time operations and also during system restoration events.  PFR is the first line of defense for preventing system disturbances and is critical to the system restoration process. This stakeholder group will evaluate the need for a generator Primary Frequency Response (PFR) requirement in PJM to clarify and strengthen PJM requirements, consistent with the NERC Industry Advisory and industry practice.

Proposed Timeline

Issue initiated: 5.25.2017
Work begins: 7.25.2017
Target Completion: 6.18.2020
Actual Completion: 12.5.2018

Issue Details

Stakeholder Body Primary Frequency Response Senior Task Force
Facilitator Boyle, Glen
Subject Matter Expert Schweizer, David P.
Problem Statement/
Issue Charge First Read
4.27.2017
Issue Catalyst PJM
Issue Status Closed
Manual Changes Yes
Agreement Changes Open Access Transmission Tariff, Operating Agreement
  • Stakeholder Process Step

  • Completed Approved
  • Completed Education
  • Completed Interest
  • Completed Design
  • Completed Options
  • Completed Packages
  • Completed Consensus
  • Completed Review
  • Completed Completed