Markets & Operations

APSouth Interface Change

On September 30, 2007, the new Greenland Gap 500KV Substation is scheduled to be energized and tapped off of the existing Mt.Storm - Meadow Brook 500kV line. As a result, the Mt.Storm-Meadow Brook 500KV line will be replaced in the PJM Model by the Mt.Storm-Greenland Gap-Meadow Brook 500KV line. This line change requires a corresponding change to the APSouth Interface Definition. The existing and future APSouth definitions are as follows:

Existing APSouth Interface Definition: Mt.Storm-Doubs & Mt.Storm-Meadow Brook 500KV lines

New APSouth Interface Definition: Mt.Storm-Doubs & Greenland Gap-Meadow Brook 500KV lines