RTEP Phasor Measurement Unit (PMU) Placement

PJM has identified the reliability and resilience benefits of PMU data observability across the PJM footprint. To achieve and maintain these benefits, a minimum coverage of Synchrophasor devices are needed. • A PMU placement provision is needed in the RTEP planning process to ‘opportunistically’ install Synchrophasor devices at minimal cost. Targeted (retrofit) PMU placement projects may be needed to ensure near-term PMU coverage needed by key Synchrophasor applications. • PJM sees an opportunity to incorporate PMU Placement as a prospective requirement in the RTEP planning process to establish a growth-cycle of new and replacement PMU devices. Adding such a requirement for an identified category of RTEP projects will be a low-cost, high-benefit implementation. • Such a requirement would require a long-lead notice for newly approved projects to include PMU devices in project costs and design documents.

Proposed Timeline

Issue initiated: 7.7.2020
Work begins: TBD
Target Completion: 10.1.2020
Actual Completion: 10.1.2020

Issue Details

Stakeholder Body Planning Committee
Subject Matter Expert Murphy, Shaun
Problem Statement/
Issue Charge First Read
5.12.2020
Issue Catalyst PJM
Issue Status Closed
Manual Changes No
  • Stakeholder Process Step

  • Completed Approved
  • Completed Education
  • Completed Interest
  • Completed Design
  • Completed Options
  • Completed Packages
  • Completed Consensus
  • Completed Review
  • Completed Completed