Application of Designated Entity Agreement

Currently, certain ambiguities exist in the Amended and Restated Operating Agreement of PJM Interconnection, L.L.C. (OA) language at Schedule 6, section 1.5.8 regarding PJM’s use of its pro forma Designated Entity Agreement (DEA). Clarifying changes are required to address the apparent ambiguity.

Proposed Timeline

Issue initiated: 5.10.2022
Work begins: 4.12.2022
Target Completion: 5.10.2022
Actual Completion: 7.27.2022

Issue Details

Stakeholder Body Planning Committee
Facilitator Souder, David W.
Subject Matter Expert Caven, Augustine
PC Approval Date 5.10.2022
Problem Statement/
Issue Charge First Read
4.12.2022
Issue Catalyst PJM Planning Division, Infrastructure Coordination Department  
Issue Status Canceled
Manual Changes No
Agreement Changes Operating Agreement
  • Stakeholder Process Step

  • Completed Approved
  • Completed Education
  • Completed Interest
  • Completed Design
  • Completed Options
  • Completed Packages
  • Completed Consensus
  • Completed Review
  • Completed Completed