Suspension of Day Ahead Market

The existing PJM Open Access Transmission Tariff (the Tariff) and Operating Agreement do not contain specific language regarding the possible suspension of the execution and approval of the Day Ahead Market due to an extraordinary event or circumstance.

Proposed Timeline

Issue initiated: 3.6.2013
Work begins: TBD
Target Completion: TBD
Actual Completion: TBD

Issue Details

Stakeholder Body Market Implementation Committee
Subject Matter Expert Fernandez, Raymond J. III
Problem Statement/
Issue Charge First Read
3.6.2013
Issue Catalyst Internal Investigation at PJM
Issue Status Closed
Manual Changes No
Agreement Changes Open Access Transmission Tariff
  • Stakeholder Process Step

  • Completed Approved
  • Completed Education
  • Completed Interest
  • Completed Design
  • Completed Options
  • Completed Packages
  • Completed Consensus
  • Completed Review
  • Completed Completed