Manual 03A: EMS Model Updates and QA, Revision 24

PJM is retiring the PJM Compliance Bulletin that describes the process PJM members are to use to notify PJM of any change in the status of PJM Member Bulk Electric System (BES) elements as a result of the application of the NERC-approved BES definition; this process is currently covered in Manual 3A. PJM will need to revise Manual 3A to remove the PJM Compliance Bulletin obsolete reference and align NERC-approved BES equipment related definitions.

Proposed Timeline

Issue initiated: 2.8.2024
Work begins: 1.11.2024
Target Completion: 2.8.2024
Actual Completion: 2.8.2024

Issue Details

Stakeholder Body Operating Committee
Facilitator Patel, Anita
Subject Matter Expert Carrasco, Eliseo
MRC Approval Date 2.22.2024
Problem Statement/
Issue Charge First Read
1.11.2024
Issue Catalyst PJM
Issue Status Closed
Manual Changes Yes
  • Stakeholder Process Step

  • Completed Approved
  • Completed Education
  • Completed Interest
  • Completed Design
  • Completed Options
  • Completed Packages
  • Completed Consensus
  • Completed Review
  • Completed Completed