Committees & Groups

Issue Details

FTR Surplus

Under the existing ARR/FTR tariff provisions, FTR holders are currently paid FTR Auction Revenue Surplus Funds. The problem statement sponsors believe this may be inconsistent with the recent FERC precedent, as these funds were unavailable to firm transmission customers through the ARR/FTR process due to PJM modeling assumptions.

Proposed Timeline

Issue initiated: 6.7.2017
Work begins: 6.23.2017
Target Completion: TBD
Actual Completion: TBD

Issue Details

Stakeholder Body Market Implementation Committee
Facilitator Hendrzak, Chantal Aimee N.
Subject Matter Expert Perera, Asanga
Problem Statement/
Issue Charge First Read
4.12.2017
Issue Catalyst Direct Energy, Exelon, AMP, Calpine, SMECO, PJM ICC, ODEC
Issue Status Closed
Manual Changes No
Agreement Changes Open Access Transmission Tariff, Operating Agreement
  • Stakeholder Process Step

  • Completed Approved
  • Completed Education
  • Completed Interest
  • Completed Design
  • Completed Options
  • Completed Packages
  • Completed Consensus
  • Completed Review
  • Completed Completed
7.2.2018 -Filing-
ER18-1845-001  PDF
8.3.2018 -Order-
ER18-1245-000  PDF