Enhancements to Deactivation Rules

Given the anticipated volume of generation resource retirements expected in the coming years, this issue will evaluate the general deactivation process and the provisions of Part V of the Tariff, including a focus on compensation, the deactivation notification timeline and transparency.

Proposed Timeline

Issue initiated: 9.20.2023
Work begins: 10.12.2023
Target Completion: 10.17.2024
Actual Completion: TBD

Issue Details

Stakeholder Body Deactivation Enhancements Senior Task Force
Facilitator Hendrzak, Chantal Aimee N.
Subject Matter Expert Zhang, Michael
Problem Statement/
Issue Charge First Read
7.26.2023
Issue Catalyst PJM and IMM
Issue Status Solution Alternatives Proposed
Manual Changes No
Agreement Changes Open Access Transmission Tariff
  • Stakeholder Process Step

  • Completed Approved
  • Completed Education
  • Completed Interest
  • Completed Design
  • Completed Options
  • In Progress Packages
  • Not Started Consensus
  • Not Started Review