This work effort is designed to consider whether the development of Tariff, Operating Agreement (“OA”), and Manual language is needed to address both the CMPs referenced in the August 12, 2019 notice and future CIP-014 listed and other security impacted facilities.

Proposed Timeline

Issue initiated: 12.12.2019
Work begins: 1.7.2020
Target Completion: 8.25.2021
Actual Completion: TBD

Issue Details

Stakeholder Body Planning Committee
Facilitator Stotesbury, Christina J.
Subject Matter Expert Herman, Michael
PC Approval Date 7.13.2021
Problem Statement/
Issue Charge First Read
9.12.2019
Issue Catalyst Brought by the Office of the People’s Counsel for the District of Columbia in response to the August 12, 2019 notice by the PJM Transmission Owners (“TOs”) of their intent to file a new Attachment M-4 to the PJM Tariff (“Tariff”) for the planning of CIP-014 Mitigation Projects (“CMPs”).
Issue Status On-Hold
Manual Changes Yes
Agreement Changes Open Access Transmission Tariff, Operating Agreement
  • Stakeholder Process Step

  • On Hold Approved
  • Not Started Education
  • Not Started Interest
  • Not Started Design
  • Not Started Options
  • Not Started Packages
  • Not Started Consensus
  • Not Started Review
  • Not Started Completed
11.19.2021 -Filing-
Docket No. ER22-451-000  PDF
1.10.2022 -Order-
Docket No. ER22-451-000  PDF