Planning

Most Recently Approved RTEP Updates
As of 12:00 p.m. EPT

Competitive Planning Process
  • The PJM competitive planning process affords non-incumbent transmission developers an opportunity to participate in the regional planning and expansion of the PJM bulk electric system.
  • 2025 RTEP Window 1
     open6.18.2025 closed8.18.2025
Planning News from Inside Lines
  • FERC Approves Streamlined Process To Replace Retiring Facilities
    The Federal Energy Regulatory Commission has accepted PJM’s proposal to create a process separate from the traditional interconnection process for transferring Capacity Interconnection Rights from a retiring facility to an equivalent replacement resource at the same site. The plan is among several that PJM and stakeholders have initiated to get generation connected to the grid […]
  • PJM Issues Notice Regarding Behind the Meter Emergency Procedure for Large Loads With Backup Generation
    On Jan. 29 PJM sent a letter to members, state regulators, and owners and operators of backup generation for data centers and other large load customers in response to the U.S. Department of Energy’s Jan. 26 order, under section 202(c) of the Federal Power Act, directing certain customer-owned backup generation facilities to operate under emergency […]
Generation Interconnection Requests by Fuel Type
As of 8:38 a.m. EPT

Projects Under Construction by MW
As of 8:38 a.m. EPT
Total:
51,557 MW
Cycle Timeline
As of 12.3.2025 3:01 p.m. EPT
Criteria & Guidelines