Planning

Most Recently Approved RTEP Updates
As of 12:00 p.m. EPT

Competitive Planning Process
  • The PJM competitive planning process affords non-incumbent transmission developers an opportunity to participate in the regional planning and expansion of the PJM bulk electric system.
  • 2025 RTEP Window 1
     openTBD closedTBD
Planning News from Inside Lines
  • PJM Generation Interconnection Reforms Continue To Produce Results
    By Aftab Khan, Executive Vice President – Operations, Planning & Security Solar output reached an all-time high in the PJM region in April, and with the continued addition of new generation resources through PJM’s streamlined process, we can expect to continue setting new solar records on a regular basis. The nearly 12,000 MW of solar […]
  • PJM Statement on the U.S. Department of Energy 202(c) Order of May 30
    (Valley Forge, PA – May 31, 2025) – PJM issued the following statement today: For over two years, PJM has repeatedly documented and voiced its concerns over the growing risk of a supply and demand imbalance driven by the confluence of generator retirements and demand growth. Such an imbalance could have serious ramifications for reliability […]
Queued Generation Fuel Mix
As of 3:00 p.m. EPT
Total:
111,800 MW
Renewables:
49,996 MW
Generation Interconnection Requests by Fuel Type
As of 3:00 p.m. EPT
Cycle Timeline
As of 5.7.2025 4:03 p.m. EPT
Criteria & Guidelines