AG1-547 Transition Sort Retool Results -- Reprioritized to Transition Cycle #1

v1.00 released 2023-12-14 10:56

Mount Airy-Chatham 69 kV

32.54 MW Capacity / 50.0 MW Energy

Introduction

In accordance with Tariff Part VII, Subpart B, section 304, PJM performed load flow analysis (Transition Sort Retool) on all AE1 through AG1 projects that have met eligibility requirements according to Tariff, Part VII, Subpart B, section 303. The purpose of this study is to determine whether a project would be classified as eligible for the Expedited Process (Fast Lane) or if it would be reprioritized to be studied as part of Transition Cycle #1 (TC1) using the criteria from the Expedited Process Eligibility section of Tariff Part VII, section 304. This is not a System Impact Study report.

Below are the results of the study, details of how the study was performed, criterion used in the evaluation of the Expedited Process vs. TC1 determination, and next steps in the interconnection process for your project.

Transition Cycle #1:

The AG1-547 project has not met the Expedited Process Eligibility requirements in Tariff Part VII, Subpart B, section 304 and will therefore be reprioritized to Transition Cycle #1. Please see "Transition Cycle #1 Rules" below.

Transition Sort Retool Study Process and Criteria:

In order to determine Expedited Process vs. Transition Cycle #1 classification, projects which met the Transition Eligibility requirements from Tariff Part VII, Subpart B, section 303 were studied on the base case model that was used for the original System Impact Study analysis. Both a summer peak and light load load flow analysis were performed. Projects that have cost allocation eligibility or are identified as the first to cause a system violation which requires the need for a Network Upgrade with a total estimated cost greater than $5 million will be reprioritized to Transition Cycle #1. All other projects will be eligible for the expedited procedures set forth in Tariff Part VII, Subpart B, section 304 (B).

Expedited Process Eligibility: OATT Tariff Part VII, section 304:

A project is not eligible for the expedited process if it has cost allocation eligibility or is identified as the first to cause, as determined according to Tariff, Part VI, section 217.3, for a Network Upgrade which has a total estimated cost of greater than $5,000,000. Such cost estimate will be based on Transmission Provider's most recently available data.

Not considered in the Transition Sorting: The cost of the Interconnection Facilities is not considered when determining a project's eligibility for the expedited process. Affected Systems upgrade costs are also not considered in the evaluation.

Transition Sort Retool Results Provided:

This report includes a list of:

  1. the overloaded flowgates (overloaded facilities + contingency pair) that the project contributes towards
  2. other interconnection projects that may also contribute to the overloaded facility, and
  3. the total estimated cost for any required Network Upgrades.

Important Notes:

Note for Uprate Projects: Per Tariff Part VII, Subpart B, section 304 (B), if a project is an uprate (project relies on the Interconnection Facilities of a prior project) whose base project does not qualify for the expedited process, the uprate also will not qualify for the expedited process, regardless of analysis results.

Notes regarding Results displayed:

  1. Some flowgate overloads that a New Service Request contributes to, but does not contribute enough to meet cost allocation eligibility (per Manual 14A, Attachment B.3), may be reported in this Transition Sort report. These types of flowgates do not affect the classification of the New Service Request as either Expedited Process or Transition Cycle #1 because cost allocation eligibility has not been met.
  2. For projects that were determined to not meet Expedited Process eligibility and are being reprioritized to Transition Cycle #1, not all reinforcements in excess of $5,000,000 may be shown in this report. This report may only display a subset of those reinforcements determined to be in excess of $5,000,000 which would classify the project as not meeting Expedited Process Eligibility. This is not a formal System Impact Study.

Next Steps for your project:

Transition Cycle #1 Rules:

Refer to Tariff Part VII, Subpart B, section 304 (C) for the Transition Cycle #1 Project Rules.

Transition Cycle #1 will start no later than one year from the Transition Start Date (July 10, 2023). Transition Cycle #1 will run simultaneously with the expedited process, however Transition Cycle #1, Phase III will not begin until all expedited process projects have been completed.

Projects that are reprioritized to Transition Cycle #1 will not need to re-apply to the Interconnection Cycle Process. Therefore, there is no Application Review Phase for Transition Cycle #1. The cycle process for Transition Cycle #1 includes three Study Phases and three Decision Points:

  1. Phase I System Impact Study and Decision Point I; and
  2. Phase II System Impact Study and Decision Point II; and
  3. Phase III System Impact Study and Decision Point III

Refer to Tariff Part VII, Subpart D, section 307 for the Transition Cycle #1 study process.

General

The Interconnection Customer (IC), has proposed a Solar; Storage generating facility located in the Dominion zone — Pittsylvania County, Virginia. The installed facilities will have a total capability of 50.0 MW with 32.54 MW of this output being recognized by PJM as Capacity.

Project Information
Queue Number AG1-547
Project Name Mount Airy-Chatham 69 kV
Developer Name Curie Solar, LLC
State Virginia
County Pittsylvania
Transmission Owner Dominion
MFO 50.0 MW
MWE 50.0 MW
MWC 32.54 MW
Fuel Type Solar; Storage
Basecase Study Year 2024

Point of Interconnection

AG1-547 "Mount Airy-Chatham 69 kV" will interconnect with the Dominion transmission system. The primary POI will be a newly constructed 69 kV three breaker ring bus located on the line between the Mount Airy substation and Chatham substation.

 

Summer Peak Analysis

The Queue Project was evaluated as a 50.0 MW (Capacity 32.54 MW) injection in the Dominion area. Project was evaluated for compliance with applicable reliability planning criteria (PJM, NERC, NERC Regional Reliability Councils, and Transmission Owners). Potential Summer peak period network impacts are listed below:

Important to Note:

Note for Uprate Projects: Per Tariff Part VII, Subpart B, section 304 (B), if a project is an uprate (project relies on the Interconnection Facilities of a prior project) whose base project does not qualify for the expedited process, the uprate also will not qualify for the expedited process, regardless of analysis results.

Notes regarding Results displayed:

  1. Some flowgate overloads that a New Service Request contributes to, but does not contribute enough to meet cost allocation eligibility (per Manual 14A, Attachment B.3), may be reported in this Transition Sort report. These types of flowgates do not affect the classification of the New Service Request as either Expedited Process or Transition Cycle #1 because cost allocation eligibility has not been met.
  2. For projects that were determined to not meet Expedited Process eligibility and are being reprioritized to Transition Cycle #1, not all reinforcements in excess of $5,000,000 may be shown in this report. This report may only display a subset of those reinforcements determined to be in excess of $5,000,000 which would classify the project as not meeting Expedited Process Eligibility. This is not a formal System Impact Study.
Summer Peak Analysis
Area Facility Description Contingency Name Contingency Type DC|AC Initial Loading Final Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Details
DVP 2STONE MIL-2ALTVSTA 69.0 kV Ckt 1 line
314730 to 314670 ckt 1
DVP_P1-2: LN 173-A
CONTINGENCY 'DVP_P1-2: LN 173-A'
 OPEN BRANCH FROM BUS 314680 TO BUS 941820 CKT 1   /*2CHATHAM      69.0 - AE2-187 TAP   69.0
 OPEN BUS 314680                                   /*2CHATHAM      69.0
END
Single AC 116.48 % 148.55 % 101.52 B 150.81 32.54
DVP 2STONE MIL-2ALTVSTA 69.0 kV Ckt 1 line
314730 to 314670 ckt 1
DVP_P1-2: LN 35-C
CONTINGENCY 'DVP_P1-2: LN 35-C'
 OPEN BRANCH FROM BUS 314729 TO BUS 941800 CKT 1   /*2GLADYS       69.0 - AE2-185 TAP   69.0
END
Single AC 115.63 % 147.22 % 101.52 B 149.46 32.54
AEP/DVP 4ALTVSTA-05OTTER 138.0 kV Ckt 1 line
314667 to 242741 ckt 1
Base Case Single AC 138.22 % 144.63 % 167.0 A 241.53 11.07
DVP 2STONE MIL-2ALTVSTA 69.0 kV Ckt 1 line
314730 to 314670 ckt 1
Base Case Single AC 110.1 % 142.21 % 101.52 A 144.37 32.54
DVP 3SEDGE HILL-6SEDGE HILL 115.0/230.0 kV Ckt 1 transformer
314696 to 314697 ckt 1
DVP_P1-3: 6SEDGE HILL-TX#2
CONTINGENCY 'DVP_P1-3: 6SEDGE HILL-TX#2'
 OPEN BRANCH FROM BUS 314696 TO BUS 314697 CKT 2   /*3SEDGE HILL  115.0 - 6SEDGE HILL  230.0
END
Single AC 126.22 % 128.05 % 242.52 B 310.54 4.43
DVP 2STONE MIL-2ALTVSTA 69.0 kV Ckt 1 line
314730 to 314670 ckt 1
PJM_PLANT AC1-145
CONTINGENCY 'PJM_PLANT AC1-145'
 REMOVE MACHINE 1 FROM BUS 926645   /*AC1-145 C      0.6
 REMOVE MACHINE 1 FROM BUS 926646   /*AC1-145 E      0.6
END
Single AC 92.89 % 124.49 % 101.52 B 126.39 32.54
DVP 2STONE MIL-2ALTVSTA 69.0 kV Ckt 1 line
314730 to 314670 ckt 1
DVP_P1-1: G-1 AC1-145_C
CONTINGENCY 'DVP_P1-1: G-1 AC1-145_C'
 REMOVE MACHINE 1 FROM BUS 926645   /*AC1-145 C      0.6
END
Single AC 92.89 % 124.49 % 101.52 B 126.39 32.54
DVP AE1-108 TAP-4BREMO 138.0 kV Ckt 1 line
938820 to 314746 ckt 1
DVP_P1-2: LN 566
CONTINGENCY 'DVP_P1-2: LN 566'
 OPEN BRANCH FROM BUS 242519 TO BUS 314912 CKT 1   /*05CLOVRD     500.0 - 8LEXNGTN     500.0
END
Single AC 120.91 % 121.94 % 156.98 B 191.42 1.64
DVP 3SEDGE HILL-6SEDGE HILL 115.0/230.0 kV Ckt 2 transformer
314696 to 314697 ckt 2
DVP_P1-3: 6SEDGE HILL-TX#1
CONTINGENCY 'DVP_P1-3: 6SEDGE HILL-TX#1'
 OPEN BRANCH FROM BUS 314696 TO BUS 314697 CKT 1   /*3SEDGE HILL  115.0 - 6SEDGE HILL  230.0
END
Single AC 119.21 % 120.93 % 256.06 B 309.66 4.41
DVP 2ALTVSTA-4ALTVSTA 69.0/138.0 kV Ckt 1 transformer
314670 to 314667 ckt 1
DVP_P1-2: LN 173-A
CONTINGENCY 'DVP_P1-2: LN 173-A'
 OPEN BRANCH FROM BUS 314680 TO BUS 941820 CKT 1   /*2CHATHAM      69.0 - AE2-187 TAP   69.0
 OPEN BUS 314680                                   /*2CHATHAM      69.0
END
Single AC 91.69 % 119.42 % 134.04 B 160.07 32.54
DVP 2ALTVSTA-4ALTVSTA 69.0/138.0 kV Ckt 1 transformer
314670 to 314667 ckt 1
Base Case Single AC 90.22 % 119.01 % 128.78 A 153.26 32.54
DVP 2ALTVSTA-4ALTVSTA 69.0/138.0 kV Ckt 1 transformer
314670 to 314667 ckt 1
DVP_P1-2: LN 35-C
CONTINGENCY 'DVP_P1-2: LN 35-C'
 OPEN BRANCH FROM BUS 314729 TO BUS 941800 CKT 1   /*2GLADYS       69.0 - AE2-185 TAP   69.0
END
Single AC 91.53 % 118.34 % 134.04 B 158.62 32.54
AEP/DVP 4ALTVSTA-05OTTER 138.0 kV Ckt 1 line
314667 to 242741 ckt 1
AEP_P2-1_242575 05CAMDLM 138 926520 AC1-123 TAP 138 1-A
CONTINGENCY 'AEP_P2-1_242575 05CAMDLM 138 926520 AC1-123 TAP 138 1-A'
 OPEN BRANCH FROM BUS 242575 TO BUS 926520 CKT 1   /*05CAMDLM     138.0 - AC1-123 TAP  138.0
END
Single AC 113.67 % 118.17 % 245.0 B 289.51 11.34
AEP/DVP 4ALTVSTA-05OTTER 138.0 kV Ckt 1 line
314667 to 242741 ckt 1
AEP_P1-2_#5471_169-A
CONTINGENCY 'AEP_P1-2_#5471_169-A'
 OPEN BRANCH FROM BUS 242575 TO BUS 242737 CKT 1   /*05CAMDLM     138.0 - 05OPOSSUMCK  138.0
 OPEN BRANCH FROM BUS 242575 TO BUS 242781 CKT 1   /*05CAMDLM     138.0 - 05RUSTBR     138.0
 OPEN BRANCH FROM BUS 242575 TO BUS 926520 CKT 1   /*05CAMDLM     138.0 - AC1-123 TAP  138.0
END
Single AC 112.58 % 117.08 % 245.0 B 286.84 11.34
DVP 2ALTVSTA-4ALTVSTA 69.0/138.0 kV Ckt 1 transformer
314670 to 314667 ckt 1
DVP_P1-1: G-1 AC1-145_E
CONTINGENCY 'DVP_P1-1: G-1 AC1-145_E'
 REMOVE MACHINE 1 FROM BUS 926646   /*AC1-145 E      0.6
END
Single AC 86.68 % 114.34 % 134.04 B 153.26 32.54
AEP/DVP 3SKIMMER-05SKIMMR 115.0/69.0 kV Ckt 1 transformer
314861 to 242886 ckt 1
DVP_P1-3: 3SKIMMER-3SKIMMER_CK2
CONTINGENCY 'DVP_P1-3: 3SKIMMER-3SKIMMER_CK2'
 OPEN BRANCH FROM BUS 242886 TO BUS 314861 CKT 2   /*05SKIMMR      69.0 - 3SKIMMER     115.0
END
Single AC 105.32 % 109.27 % 53.0 B 57.91 2.19
AEP/DVP 3SKIMMER-05SKIMMR 115.0/69.0 kV Ckt 2 transformer
314861 to 242886 ckt 2
DVP_P1-3: 3SKIMMER-3SKIMMER
CONTINGENCY 'DVP_P1-3: 3SKIMMER-3SKIMMER'
 OPEN BRANCH FROM BUS 242886 TO BUS 314861 CKT 1   /*05SKIMMR      69.0 - 3SKIMMER     115.0
END
Single AC 104.52 % 108.43 % 53.0 B 57.47 2.17
DVP 3SEDGE HILL-6SEDGE HILL 115.0/230.0 kV Ckt 2 transformer
314696 to 314697 ckt 2
DVP_P4-2: 3202
CONTINGENCY 'DVP_P4-2: 3202'
 OPEN BRANCH FROM BUS 313852 TO BUS 314716 CKT 1   /*3WELCOTAP    115.0 - 3REEDY C     115.0
 OPEN BRANCH FROM BUS 313852 TO BUS 314718 CKT 1   /*3WELCOTAP    115.0 - 3S BOSTN     115.0
 OPEN BRANCH FROM BUS 313852 TO BUS 314724 CKT 1   /*3WELCOTAP    115.0 - 3WELCO       115.0
 OPEN BRANCH FROM BUS 314696 TO BUS 314697 CKT 1   /*3SEDGE HILL  115.0 - 6SEDGE HILL  230.0
 OPEN BRANCH FROM BUS 314696 TO BUS 314717 CKT 1   /*3SEDGE HILL  115.0 - 3SINAI       115.0
 OPEN BRANCH FROM BUS 314717 TO BUS 314718 CKT 1   /*3SINAI       115.0 - 3S BOSTN     115.0
 OPEN BUS 313852                                   /*3WELCOTAP    115.0
 OPEN BUS 314717                                   /*3SINAI       115.0
 OPEN BUS 314718                                   /*3S BOSTN     115.0
 OPEN BUS 314724                                   /*3WELCO       115.0
END
Breaker AC 184.87 % 186.93 % 279.1 C 521.72 6.78
AEP/DVP 05LEESVI-4ALTVSTA 138.0 kV Ckt 1 line
242701 to 314667 ckt 1
AEP_P4_#13922_05OPOSSUMCK 138_D
CONTINGENCY 'AEP_P4_#13922_05OPOSSUMCK 138_D'
 OPEN BRANCH FROM BUS 242575 TO BUS 242737 CKT 1   /*05CAMDLM     138.0 - 05OPOSSUMCK  138.0
 OPEN BRANCH FROM BUS 242575 TO BUS 242781 CKT 1   /*05CAMDLM     138.0 - 05RUSTBR     138.0
 OPEN BRANCH FROM BUS 242575 TO BUS 926520 CKT 1   /*05CAMDLM     138.0 - AC1-123 TAP  138.0
 OPEN BRANCH FROM BUS 242737 TO BUS 242785 CKT 1   /*05OPOSSUMCK  138.0 - 05S.LYNC     138.0
END
Breaker AC 122.8 % 124.38 % 284.0 B 353.24 4.49
AEP 05OTTER-05JOHNMT 138.0 kV Ckt 1 line
242741 to 242687 ckt 1
Base Case Single AC 136.6 % 143.0 % 167.0 A 238.82 11.07
AEP 05JOHNMT-05NEWLDN 138.0 kV Ckt 1 line
242687 to 242734 ckt 1
Base Case Single AC 134.03 % 140.44 % 167.0 A 234.53 11.07
AEP 05OTTER-05JOHNMT 138.0 kV Ckt 1 line
242741 to 242687 ckt 1
AEP_P2-1_242575 05CAMDLM 138 926520 AC1-123 TAP 138 1-A
CONTINGENCY 'AEP_P2-1_242575 05CAMDLM 138 926520 AC1-123 TAP 138 1-A'
 OPEN BRANCH FROM BUS 242575 TO BUS 926520 CKT 1   /*05CAMDLM     138.0 - AC1-123 TAP  138.0
END
Single AC 112.55 % 117.05 % 245.0 B 286.78 11.34
AEP 05OTTER-05JOHNMT 138.0 kV Ckt 1 line
242741 to 242687 ckt 1
AEP_P1-2_#5471_169-A
CONTINGENCY 'AEP_P1-2_#5471_169-A'
 OPEN BRANCH FROM BUS 242575 TO BUS 242737 CKT 1   /*05CAMDLM     138.0 - 05OPOSSUMCK  138.0
 OPEN BRANCH FROM BUS 242575 TO BUS 242781 CKT 1   /*05CAMDLM     138.0 - 05RUSTBR     138.0
 OPEN BRANCH FROM BUS 242575 TO BUS 926520 CKT 1   /*05CAMDLM     138.0 - AC1-123 TAP  138.0
END
Single AC 111.46 % 115.97 % 245.0 B 284.12 11.34
AEP 05JOHNMT-05NEWLDN 138.0 kV Ckt 1 line
242687 to 242734 ckt 1
AEP_P2-1_242575 05CAMDLM 138 926520 AC1-123 TAP 138 1-A
CONTINGENCY 'AEP_P2-1_242575 05CAMDLM 138 926520 AC1-123 TAP 138 1-A'
 OPEN BRANCH FROM BUS 242575 TO BUS 926520 CKT 1   /*05CAMDLM     138.0 - AC1-123 TAP  138.0
END
Single AC 110.78 % 115.29 % 245.0 B 282.45 11.34
AEP 05JOHNMT-05NEWLDN 138.0 kV Ckt 1 line
242687 to 242734 ckt 1
AEP_P1-2_#5471_169-A
CONTINGENCY 'AEP_P1-2_#5471_169-A'
 OPEN BRANCH FROM BUS 242575 TO BUS 242737 CKT 1   /*05CAMDLM     138.0 - 05OPOSSUMCK  138.0
 OPEN BRANCH FROM BUS 242575 TO BUS 242781 CKT 1   /*05CAMDLM     138.0 - 05RUSTBR     138.0
 OPEN BRANCH FROM BUS 242575 TO BUS 926520 CKT 1   /*05CAMDLM     138.0 - AC1-123 TAP  138.0
END
Single AC 109.69 % 114.2 % 245.0 B 279.79 11.34
AEP 05BANSTR-05EDAN 2 138.0 kV Ckt 1 line
242549 to 242632 ckt 1
AEP_P2-1_242720 05MONETA 138 242775 05ROCKCAS SS 138 1
CONTINGENCY 'AEP_P2-1_242720 05MONETA 138 242775 05ROCKCAS SS 138 1'
 OPEN BRANCH FROM BUS 242720 TO BUS 242775 CKT 1   /*05MONETA     138.0 - 05ROCKCAS SS 138.0
END
Single AC 100.44 % 102.24 % 296.0 B 302.64 5.51
AEP 05BANSTR-05EDAN 2 138.0 kV Ckt 1 line
242549 to 242632 ckt 1
AEP_P2-1_242720 05MONETA 138 243892 05MEADS8 138 1
CONTINGENCY 'AEP_P2-1_242720 05MONETA 138 243892 05MEADS8 138 1'
 OPEN BRANCH FROM BUS 242720 TO BUS 243892 CKT 1   /*05MONETA     138.0 - 05MEADS8     138.0
END
Single AC 98.91 % 100.71 % 296.0 B 298.11 5.51
AEP 05BANSTR-05EDAN 2 138.0 kV Ckt 1 line
242549 to 242632 ckt 1
AEP_P2-1_242607 05CLOVRD 138 243892 05MEADS8 138 1
CONTINGENCY 'AEP_P2-1_242607 05CLOVRD 138 243892 05MEADS8 138 1'
 OPEN BRANCH FROM BUS 242607 TO BUS 243892 CKT 1   /*05CLOVRD     138.0 - 05MEADS8     138.0
END
Single AC 98.52 % 100.32 % 296.0 B 296.96 5.51
AEP 05SMITHMTN-05LEESVI 138.0 kV Ckt 1 line
242802 to 242701 ckt 1
AEP_P4_#13922_05OPOSSUMCK 138_D
CONTINGENCY 'AEP_P4_#13922_05OPOSSUMCK 138_D'
 OPEN BRANCH FROM BUS 242575 TO BUS 242737 CKT 1   /*05CAMDLM     138.0 - 05OPOSSUMCK  138.0
 OPEN BRANCH FROM BUS 242575 TO BUS 242781 CKT 1   /*05CAMDLM     138.0 - 05RUSTBR     138.0
 OPEN BRANCH FROM BUS 242575 TO BUS 926520 CKT 1   /*05CAMDLM     138.0 - AC1-123 TAP  138.0
 OPEN BRANCH FROM BUS 242737 TO BUS 242785 CKT 1   /*05OPOSSUMCK  138.0 - 05S.LYNC     138.0
END
Breaker AC 119.33 % 121.07 % 255.0 B 308.73 4.49
AEP 05ROCKCAS SS-05MONETA 138.0 kV Ckt 1 line
242775 to 242720 ckt 1
AEP_P4_#10164_05EDAN 2 138_M
CONTINGENCY 'AEP_P4_#10164_05EDAN 2 138_M'
 OPEN BRANCH FROM BUS 242531 TO BUS 242632 CKT 4    /*05EDANV2     230.0 - 05EDAN 2     138.0
 OPEN BRANCH FROM BUS 242531 TO BUS 304094 CKT 1    /*05EDANV2     230.0 - 6YANCY TAP   230.0
 OPEN BRANCH FROM BUS 242549 TO BUS 242632 CKT 1    /*05BANSTR     138.0 - 05EDAN 2     138.0
 OPEN BRANCH FROM BUS 242549 TO BUS 314668 CKT Z1   /*05BANSTR     138.0 - 4BANISTR     138.0
 OPEN BRANCH FROM BUS 242549 TO BUS 940080 CKT 1    /*05BANSTR     138.0 - AE1-250 TAP  138.0
 OPEN BRANCH FROM BUS 242629 TO BUS 242632 CKT 1    /*05E.MONU     138.0 - 05EDAN 2     138.0
 OPEN BRANCH FROM BUS 242631 TO BUS 242632 CKT Z1   /*05EDAN 1     138.0 - 05EDAN 2     138.0
END
Breaker AC 102.08 % 104.16 % 409.0 B 426.02 8.72
AEP 05MONETA-05MEADS8 138.0 kV Ckt 1 line
242720 to 243892 ckt 1
AEP_P4_#10164_05EDAN 2 138_M
CONTINGENCY 'AEP_P4_#10164_05EDAN 2 138_M'
 OPEN BRANCH FROM BUS 242531 TO BUS 242632 CKT 4    /*05EDANV2     230.0 - 05EDAN 2     138.0
 OPEN BRANCH FROM BUS 242531 TO BUS 304094 CKT 1    /*05EDANV2     230.0 - 6YANCY TAP   230.0
 OPEN BRANCH FROM BUS 242549 TO BUS 242632 CKT 1    /*05BANSTR     138.0 - 05EDAN 2     138.0
 OPEN BRANCH FROM BUS 242549 TO BUS 314668 CKT Z1   /*05BANSTR     138.0 - 4BANISTR     138.0
 OPEN BRANCH FROM BUS 242549 TO BUS 940080 CKT 1    /*05BANSTR     138.0 - AE1-250 TAP  138.0
 OPEN BRANCH FROM BUS 242629 TO BUS 242632 CKT 1    /*05E.MONU     138.0 - 05EDAN 2     138.0
 OPEN BRANCH FROM BUS 242631 TO BUS 242632 CKT Z1   /*05EDAN 1     138.0 - 05EDAN 2     138.0
END
Breaker AC 98.26 % 100.34 % 409.0 B 410.4 8.72
AEP AC1-123 TAP-05CAMDLM 138.0 kV Ckt 1 line
926520 to 242575 ckt 1
AEP_P2-2_#10292_05NEWLDN 138_1
CONTINGENCY 'AEP_P2-2_#10292_05NEWLDN 138_1'
 OPEN BRANCH FROM BUS 242569 TO BUS 242734 CKT 1   /*05BRUSHT     138.0 - 05NEWLDN     138.0
 OPEN BRANCH FROM BUS 242641 TO BUS 242734 CKT 1   /*05FOREST     138.0 - 05NEWLDN     138.0
 OPEN BRANCH FROM BUS 242687 TO BUS 242734 CKT 1   /*05JOHNMT     138.0 - 05NEWLDN     138.0
END
Bus AC 108.55 % 110.51 % 255.0 B 281.8 5.19

Light Load Analysis

The Queue Project was evaluated as a 50.0 MW (Capacity 32.54 MW) injection in the Dominion area. Project was evaluated for compliance with applicable reliability planning criteria (PJM, NERC, NERC Regional Reliability Councils, and Transmission Owners). Potential light load period network impacts are listed below:

Important to Note:

Note for Uprate Projects: Per Tariff Part VII, Subpart B, section 304 (B), if a project is an uprate (project relies on the Interconnection Facilities of a prior project) whose base project does not qualify for the expedited process, the uprate also will not qualify for the expedited process, regardless of analysis results.

Notes regarding Results displayed:

  1. Some flowgate overloads that a New Service Request contributes to, but does not contribute enough to meet cost allocation eligibility (per Manual 14A, Attachment B.3), may be reported in this Transition Sort report. These types of flowgates do not affect the classification of the New Service Request as either Expedited Process or Transition Cycle #1 because cost allocation eligibility has not been met.
  2. For projects that were determined to not meet Expedited Process eligibility and are being reprioritized to Transition Cycle #1, not all reinforcements in excess of $5,000,000 may be shown in this report. This report may only display a subset of those reinforcements determined to be in excess of $5,000,000 which would classify the project as not meeting Expedited Process Eligibility. This is not a formal System Impact Study.

(No impacts were found for this analysis)

System Reinforcements

The table below lists all network upgrades which resolve the identified overloaded facilities in this report.

Important to Note:

Note for Uprate Projects: Per Tariff Part VII, Subpart B, section 304 (B), if a project is an uprate (project relies on the Interconnection Facilities of a prior project) whose base project does not qualify for the expedited process, the uprate also will not qualify for the expedited process, regardless of analysis results.

Notes regarding Results displayed:

  1. Some flowgate overloads that a New Service Request contributes to, but does not contribute enough to meet cost allocation eligibility (per Manual 14A, Attachment B.3), may be reported in this Transition Sort report. These types of flowgates do not affect the classification of the New Service Request as either Expedited Process or Transition Cycle #1 because cost allocation eligibility has not been met.
  2. For projects that were determined to not meet Expedited Process eligibility and are being reprioritized to Transition Cycle #1, not all reinforcements in excess of $5,000,000 may be shown in this report. This report may only display a subset of those reinforcements determined to be in excess of $5,000,000 which would classify the project as not meeting Expedited Process Eligibility. This is not a formal System Impact Study.
  3. Reinforcements previously identified by Transmission Owners for violations on lower voltage facilities are included in this report. Transmission Owner analysis will be updated as part of the Expedited Process and Transition Cycle 1 retools.
System Reinforcements
RTEP ID Title Total Cost
n6457.1 The sag study was completed under AE1-130 project and determined that no violations occur on this line when operating at Maximum Operating Temperature. No work required on the circuit at this time. $0
n8360 Reconductor/ Rebuild 17.2 miles between Candiers Mountain - Redeye 138kV which currently has ACSR ~ 556 ACSR ~ 26/7 overhead conductor $34,400,000
n6224 Current Station Rating: S/N: 167, S/E: 240 1) Rebuild/reconductor ACSR ~ 397.5 ~ 30/7 ~ LARK ~ Fe Clamps 9 d, Conductor Section 1, 6.5 miles $9,750,000
n6241 AEPA0019a and AEPA0019b $10,675,000
n6972.1 Replace Leesville & Smithmtn Riser Sub Cond 795 AAC 37 Str $100,000
n6972.2 Rebuild the 8.1 mile section ACSR ~556.5 ~26/7~DOVE on the Smith Mountain - Leesville 138 kV line. $12,150,000
n6972.3 Increase CT thermal limit at Leesville above 327 MVA $25,000
n6972.4 Increase Relay Compliance Trip Limit at Smith Mountain above 327 MVA $25,000
n6972.5 Increase Relay Compliance Trip Limit at Leesville above 327 MVA $25,000
n6594.2 An engineering study will need to be conducted to determine $50,000
n6594.1 Rebuild 8.4 miles section of the Leesville - Alta Vista 138 kV line $23,571,948
n6594.3 An engineering study will need to be conducted. $25,000
n6594.4 Replace Leesville Wavetrap (1200A) $100,000
n6594.5 Replace 2 Leesville Bus 1.5" AL Tubular $200,000
n6594.6 Replace 6 leesville Sub cond 1272 AAC 61 Str. $600,000
n6594.7 Replace 2 Leesville switches (1200A) $350,000
n8382 A sag study will be required on the 5.87 miles of 2-bundle ACSR ~ 556.5 ~ 26/7 ~ DOVE~ Conductor to determine what mitigation $60,000
n8381 A sag study will be required on the 5.08 miles of 2-bundle ACSR ~ 556.5 ~ 26/7 ~ DOVE~ Conductor to determine what mitigation $60,000
n5613 Rebuild 0.9 miles of the Otter - Alta Vista 138 kV line $2,740,849
n5613.1 Replace 795 AAC station conductors at Altavista $100,000
n6242 Relay Change Outs (Secondary) at Altavista Substation $120,000
n6518 Increase relay thermal limit above 80 MVA $25,000
n6609 Rebuild 1.64 miles of 69 kV Line 35 from Stone Mill to Altavista with 768 ACSS. $2,132,000
n7687 Add additional 230/115 kV transformer at Sedge Hill substation. $6,000,000
n7029 Add additional 138/69 kV transformer at Altavista substation $6,000,000

Attachments

Conclusion

The Transition Sort load flow retool results indicate that AG1-547 is not eligible for the Expedited Process per PJM Tariff Part VII, Subpart B, section 304 (A) will be reprioritized to Transition Cycle #1. See next steps for your project in the "Introduction" section above.