Export to CSV

AG1-523 Transition Sort Retool Results -- Reprioritized to Transition Cycle #1

v1.00 released 2023-12-14 10:42

Sullivan-Rockport 765 kV

180.0 MW Capacity / 300.0 MW Energy

Introduction

In accordance with Tariff Part VII, Subpart B, section 304, PJM performed load flow analysis (Transition Sort Retool) on all AE1 through AG1 projects that have met eligibility requirements according to Tariff, Part VII, Subpart B, section 303. The purpose of this study is to determine whether a project would be classified as eligible for the Expedited Process (Fast Lane) or if it would be reprioritized to be studied as part of Transition Cycle #1 (TC1) using the criteria from the Expedited Process Eligibility section of Tariff Part VII, section 304. This is not a System Impact Study report.

Below are the results of the study, details of how the study was performed, criterion used in the evaluation of the Expedited Process vs. TC1 determination, and next steps in the interconnection process for your project.

Transition Cycle #1:

The AG1-523 project has not met the Expedited Process Eligibility requirements in Tariff Part VII, Subpart B, section 304 and will therefore be reprioritized to Transition Cycle #1. Please see "Transition Cycle #1 Rules" below.

Transition Sort Retool Study Process and Criteria:

In order to determine Expedited Process vs. Transition Cycle #1 classification, projects which met the Transition Eligibility requirements from Tariff Part VII, Subpart B, section 303 were studied on the base case model that was used for the original System Impact Study analysis. Both a summer peak and light load load flow analysis were performed. Projects that have cost allocation eligibility or are identified as the first to cause a system violation which requires the need for a Network Upgrade with a total estimated cost greater than $5 million will be reprioritized to Transition Cycle #1. All other projects will be eligible for the expedited procedures set forth in Tariff Part VII, Subpart B, section 304 (B).

Expedited Process Eligibility: OATT Tariff Part VII, section 304:

A project is not eligible for the expedited process if it has cost allocation eligibility or is identified as the first to cause, as determined according to Tariff, Part VI, section 217.3, for a Network Upgrade which has a total estimated cost of greater than $5,000,000. Such cost estimate will be based on Transmission Provider's most recently available data.

Not considered in the Transition Sorting: The cost of the Interconnection Facilities is not considered when determining a project's eligibility for the expedited process. Affected Systems upgrade costs are also not considered in the evaluation.

Transition Sort Retool Results Provided:

This report includes a list of:

  1. the overloaded flowgates (overloaded facilities + contingency pair) that the project contributes towards
  2. other interconnection projects that may also contribute to the overloaded facility, and
  3. the total estimated cost for any required Network Upgrades.

Important Notes:

Note for Uprate Projects: Per Tariff Part VII, Subpart B, section 304 (B), if a project is an uprate (project relies on the Interconnection Facilities of a prior project) whose base project does not qualify for the expedited process, the uprate also will not qualify for the expedited process, regardless of analysis results.

Notes regarding Results displayed:

  1. Some flowgate overloads that a New Service Request contributes to, but does not contribute enough to meet cost allocation eligibility (per Manual 14A, Attachment B.3), may be reported in this Transition Sort report. These types of flowgates do not affect the classification of the New Service Request as either Expedited Process or Transition Cycle #1 because cost allocation eligibility has not been met.
  2. For projects that were determined to not meet Expedited Process eligibility and are being reprioritized to Transition Cycle #1, not all reinforcements in excess of $5,000,000 may be shown in this report. This report may only display a subset of those reinforcements determined to be in excess of $5,000,000 which would classify the project as not meeting Expedited Process Eligibility. This is not a formal System Impact Study.

Next Steps for your project:

Transition Cycle #1 Rules:

Refer to Tariff Part VII, Subpart B, section 304 (C) for the Transition Cycle #1 Project Rules.

Transition Cycle #1 will start no later than one year from the Transition Start Date (July 10, 2023). Transition Cycle #1 will run simultaneously with the expedited process, however Transition Cycle #1, Phase III will not begin until all expedited process projects have been completed.

Projects that are reprioritized to Transition Cycle #1 will not need to re-apply to the Interconnection Cycle Process. Therefore, there is no Application Review Phase for Transition Cycle #1. The cycle process for Transition Cycle #1 includes three Study Phases and three Decision Points:

  1. Phase I System Impact Study and Decision Point I; and
  2. Phase II System Impact Study and Decision Point II; and
  3. Phase III System Impact Study and Decision Point III

Refer to Tariff Part VII, Subpart D, section 307 for the Transition Cycle #1 study process.

General

The Interconnection Customer (IC) has proposed an uprate to a planned/existing Solar generating facility located in the AEP zone — Sullivan County, Indiana. This project is an increase to the Interconnection Customer's AG1-522 project, which will share the same point of interconnection. The AG1-523 queue position is a 300.0 MW uprate (180.0 MW Capacity uprate) to the previous project. The total installed facilities will have a capability of 600.0 MW with 360.0 MW of this output being recognized by PJM as Capacity. The proposed in-service date for this project is Thursday, June 01, 2023. This study does not imply a TO commitment to this in-service date.

Project Information

Queue Number

AG1-523

Project Name

Sullivan-Rockport 765 kV

Developer Name

PJM Solar Devco I, LLC

State

Indiana

County

Sullivan

Transmission Owner

AEP

MFO

600.0 MW

MWE

300.0 MW

MWC

180.0 MW

Fuel Type

Solar

Basecase Study Year

2024

 

Point of Interconnection

AG1-523 will interconnect on the AEP transmission system tapping the Sullivan to Rockport 765 kV line.

Summer Peak Analysis

The Queue Project was evaluated as a 300.0 MW (Capacity 180.0 MW) injection in the AEP area. Project was evaluated for compliance with applicable reliability planning criteria (PJM, NERC, NERC Regional Reliability Councils, and Transmission Owners). Potential Summer peak period network impacts are listed below:

Important to Note:

Note for Uprate Projects: Per Tariff Part VII, Subpart B, section 304 (B), if a project is an uprate (project relies on the Interconnection Facilities of a prior project) whose base project does not qualify for the expedited process, the uprate also will not qualify for the expedited process, regardless of analysis results.

Notes regarding Results displayed:

  1. Some flowgate overloads that a New Service Request contributes to, but does not contribute enough to meet cost allocation eligibility (per Manual 14A, Attachment B.3), may be reported in this Transition Sort report. These types of flowgates do not affect the classification of the New Service Request as either Expedited Process or Transition Cycle #1 because cost allocation eligibility has not been met.
  2. For projects that were determined to not meet Expedited Process eligibility and are being reprioritized to Transition Cycle #1, not all reinforcements in excess of $5,000,000 may be shown in this report. This report may only display a subset of those reinforcements determined to be in excess of $5,000,000 which would classify the project as not meeting Expedited Process Eligibility. This is not a formal System Impact Study.
Summer Peak Analysis
Area Facility Description Contingency Name Contingency Type DC|AC Initial Loading Final Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Details
AEP/ARE_2 05SULLIVAN-J1180 TAP 345.0 kV Ckt 1 line
247712 to 956820 ckt 1
AEP_P1-2_#363_1682
CONTINGENCY 'AEP_P1-2_#363_1682'
 OPEN BRANCH FROM BUS 243208 TO BUS 243209 CKT 1   /*05JEFRSO     765.0 - 05ROCKPT     765.0
END
Single DC 138.08 % 142.57 % 1466.0 B 2090.09 65.85
AEP 05SULLIVAN-05EUGENE 345.0 kV Ckt 1 line
247712 to 243221 ckt 1
AEP_P1-2_#363_1682
CONTINGENCY 'AEP_P1-2_#363_1682'
 OPEN BRANCH FROM BUS 243208 TO BUS 243209 CKT 1   /*05JEFRSO     765.0 - 05ROCKPT     765.0
END
Single DC 117.72 % 120.67 % 1335.0 B 1610.93 39.34
AEP/ARE_2 05SULLIVAN-J1180 TAP 345.0 kV Ckt 1 line
247712 to 956820 ckt 1
AEP_P1-2_#10136
CONTINGENCY 'AEP_P1-2_#10136'
 OPEN BRANCH FROM BUS 243208 TO BUS 243209 CKT 1   /*05JEFRSO     765.0 - 05ROCKPT     765.0
 OPEN BRANCH FROM BUS 243209 TO BUS 243443 CKT 2   /*05ROCKPT     765.0 - 05RKG2        26.0
 REMOVE UNIT 2H FROM BUS 243443                    /*05RKG2        26.0
 REMOVE UNIT 2L FROM BUS 243443                    /*05RKG2        26.0
END
Single AC 109.02 % 113.74 % 1466.0 B 1667.4 66.29
AEP/IPL 05SULLIVAN-16PETE 345.0 kV Ckt 1 line
247712 to 254529 ckt 1
AEP_P1-2_#363_1682
CONTINGENCY 'AEP_P1-2_#363_1682'
 OPEN BRANCH FROM BUS 243208 TO BUS 243209 CKT 1   /*05JEFRSO     765.0 - 05ROCKPT     765.0
END
Single DC 112.89 % 116.16 % 1409.0 B 1636.65 46.03
AEP 05ROCKPT-05JEFRSO 765.0 kV Ckt 1 line
243209 to 243208 ckt 1
AEP_P1-2_#8905_1697
CONTINGENCY 'AEP_P1-2_#8905_1697'
 OPEN BRANCH FROM BUS 243217 TO BUS 247712 CKT 1   /*05DEQUIN     345.0 - 05SULLIVAN   345.0
END
Single AC 103.48 % 105.86 % 3970.0 B 4202.56 83.83
AEP 05ROCKPT-05JEFRSO 765.0 kV Ckt 1 line
243209 to 243208 ckt 1
AEP_P1-2_#672_1713-B
CONTINGENCY 'AEP_P1-2_#672_1713-B'
 OPEN BRANCH FROM BUS 963840 TO BUS 963740 CKT 1   /*AG1-237 TAP  345.0 - AG1-226 TAP  345.0
END
Single AC 101.69 % 104.0 % 3970.0 B 4128.6 80.43
AEP/OVEC 05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line
242865 to 248000 ckt Z1
AEP_P1-2_#709_546
CONTINGENCY 'AEP_P1-2_#709_546'
 OPEN BRANCH FROM BUS 242924 TO BUS 243208 CKT 1   /*05HANG R     765.0 - 05JEFRSO     765.0
END
Single AC 98.84 % 100.89 % 2255.0 B 2275.09 42.34
AEP/OVEC 05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line
242865 to 248000 ckt Z1
AEP_P4_#1760_05JEFRSO 765_A
CONTINGENCY 'AEP_P4_#1760_05JEFRSO 765_A'
 OPEN BRANCH FROM BUS 242924 TO BUS 243208 CKT 1   /*05HANG R     765.0 - 05JEFRSO     765.0
 OPEN BRANCH FROM BUS 243207 TO BUS 243208 CKT 1   /*05GRNTWN     765.0 - 05JEFRSO     765.0
END
Breaker AC 161.07 % 164.96 % 2255.0 B 3719.78 102.33
AEP/OVEC 05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line
242865 to 248000 ckt Z1
AEP_P4_#6189_05HANG R 765_D1
CONTINGENCY 'AEP_P4_#6189_05HANG R 765_D1'
 OPEN BRANCH FROM BUS 242921 TO BUS 242924 CKT 1   /*05CORNU      765.0 - 05HANG R     765.0
 OPEN BRANCH FROM BUS 242921 TO BUS 242934 CKT 1   /*05CORNU      765.0 - 05CORNU      345.0
 OPEN BRANCH FROM BUS 242924 TO BUS 243208 CKT 1   /*05HANG R     765.0 - 05JEFRSO     765.0
 REMOVE UNIT 1A FROM BUS 247245                    /*05HRKG1A      18.0
 REMOVE UNIT 1B FROM BUS 247246                    /*05HRKG1B      18.0
 REMOVE UNIT 1S FROM BUS 247247                    /*05HRKG1S      18.0
 REMOVE UNIT 2A FROM BUS 247248                    /*05HRKG2A      18.0
 REMOVE UNIT 2B FROM BUS 247249                    /*05HRKG2B      18.0
 REMOVE UNIT 2S FROM BUS 247250                    /*05HRKG2S      18.0
END
Breaker AC 132.09 % 135.75 % 2255.0 B 3061.23 70.48
AEP 05ROCKPT-05JEFRSO 765.0 kV Ckt 1 line
243209 to 243208 ckt 1
AEP_P4_#8906_05SULLIVAN 345_C
CONTINGENCY 'AEP_P4_#8906_05SULLIVAN 345_C'
 OPEN BRANCH FROM BUS 243217 TO BUS 247712 CKT 1   /*05DEQUIN     345.0 - 05SULLIVAN   345.0
 OPEN BRANCH FROM BUS 243221 TO BUS 247712 CKT 1   /*05EUGENE     345.0 - 05SULLIVAN   345.0
END
Breaker AC 127.09 % 131.98 % 3970.0 B 5239.45 152.79
AEP 05ROCKPT-05JEFRSO 765.0 kV Ckt 1 line
243209 to 243208 ckt 1
AEP_P4_#8910_05DEQUIN 345_C
CONTINGENCY 'AEP_P4_#8910_05DEQUIN 345_C'
 OPEN BRANCH FROM BUS 243217 TO BUS 243878 CKT 2   /*05DEQUIN     345.0 - 05MEADOW     345.0
 OPEN BRANCH FROM BUS 243217 TO BUS 247712 CKT 1   /*05DEQUIN     345.0 - 05SULLIVAN   345.0
END
Breaker AC 120.01 % 124.31 % 3970.0 B 4935.15 139.97
AEP 05JEFRSO-05JEFRSO 765.0/345.0 kV Ckt 2 transformer
243208 to 242865 ckt 2
AEP_P4_#1760_05JEFRSO 765_A
CONTINGENCY 'AEP_P4_#1760_05JEFRSO 765_A'
 OPEN BRANCH FROM BUS 242924 TO BUS 243208 CKT 1   /*05HANG R     765.0 - 05JEFRSO     765.0
 OPEN BRANCH FROM BUS 243207 TO BUS 243208 CKT 1   /*05GRNTWN     765.0 - 05JEFRSO     765.0
END
Breaker AC 117.42 % 119.74 % 3039.0 B 3638.96 102.33
AEP/DEI 05EUGENE-08CAYSUB 345.0 kV Ckt 1 line
243221 to 249504 ckt 1
AEP_P4_#4697_05DEQUIN 345_B
CONTINGENCY 'AEP_P4_#4697_05DEQUIN 345_B'
 OPEN BRANCH FROM BUS 243217 TO BUS 243878 CKT 1   /*05DEQUIN     345.0 - 05MEADOW     345.0
 OPEN BRANCH FROM BUS 243217 TO BUS 963840 CKT 1   /*05DEQUIN     345.0 - AG1-237 TAP  345.0
END
Breaker AC 118.98 % 120.07 % 1374.0 B 1649.78 25.15
AEP AG1-522 TAP-05SULLIVAN 765.0 kV Ckt 1 line
966530 to 243210 ckt 1
AEP_P4_#9336_05ROCKPT 765_C
CONTINGENCY 'AEP_P4_#9336_05ROCKPT 765_C'
 OPEN BRANCH FROM BUS 243208 TO BUS 243209 CKT 1    /*05JEFRSO     765.0 - 05ROCKPT     765.0
 OPEN BRANCH FROM BUS 243209 TO BUS 247133 CKT Z7   /*05ROCKPT     765.0 - 05ROCKP WRK1 765.0
 OPEN BRANCH FROM BUS 243239 TO BUS 243785 CKT 1    /*05ROCKP WRK1 138.0 - 05AKSTL      138.0
 OPEN BRANCH FROM BUS 243239 TO BUS 247133 CKT 7    /*05ROCKP WRK1 138.0 - 05ROCKP WRK1 765.0
END
Breaker DC 95.43 % 103.1 % 3859.0 B 3978.51 295.88
AEP AG1-522 TAP-05SULLIVAN 765.0 kV Ckt 1 line
966530 to 243210 ckt 1
AEP_P4_#3002_05ROCKPT 765_C2
CONTINGENCY 'AEP_P4_#3002_05ROCKPT 765_C2'
 OPEN BRANCH FROM BUS 243208 TO BUS 243209 CKT 1    /*05JEFRSO     765.0 - 05ROCKPT     765.0
 OPEN BRANCH FROM BUS 243209 TO BUS 247135 CKT Z8   /*05ROCKPT     765.0 - 05ROCKP WRK2 765.0
 OPEN BRANCH FROM BUS 243240 TO BUS 243785 CKT 1    /*05ROCKP WRK2 138.0 - 05AKSTL      138.0
 OPEN BRANCH FROM BUS 243240 TO BUS 247135 CKT 8    /*05ROCKP WRK2 138.0 - 05ROCKP WRK2 765.0
END
Breaker DC 95.43 % 103.1 % 3859.0 B 3978.51 295.88
AEP AG1-522 TAP-05SULLIVAN 765.0 kV Ckt 1 line
966530 to 243210 ckt 1
AEP_P4_#8648_05JEFRSO 765_B
CONTINGENCY 'AEP_P4_#8648_05JEFRSO 765_B'
 OPEN BRANCH FROM BUS 243208 TO BUS 243209 CKT 1   /*05JEFRSO     765.0 - 05ROCKPT     765.0
END
Breaker DC 95.43 % 103.1 % 3859.0 B 3978.51 295.88
OVEC 06CLIFTY-06DEARB1 345.0 kV Ckt 1 line
248000 to 248001 ckt 1
AEP_P4_#1760_05JEFRSO 765_A
CONTINGENCY 'AEP_P4_#1760_05JEFRSO 765_A'
 OPEN BRANCH FROM BUS 242924 TO BUS 243208 CKT 1   /*05HANG R     765.0 - 05JEFRSO     765.0
 OPEN BRANCH FROM BUS 243207 TO BUS 243208 CKT 1   /*05GRNTWN     765.0 - 05JEFRSO     765.0
END
Breaker AC 105.08 % 107.09 % 1099.0 B 1176.88 25.57
AEP 05ROCKPT-05JEFRSO 765.0 kV Ckt 1 line
243209 to 243208 ckt 1
AEP_P7-1_#11041
CONTINGENCY 'AEP_P7-1_#11041'
 OPEN BRANCH FROM BUS 243217 TO BUS 243878 CKT 1   /*05DEQUIN     345.0 - 05MEADOW     345.0
 OPEN BRANCH FROM BUS 243217 TO BUS 243878 CKT 2   /*05DEQUIN     345.0 - 05MEADOW     345.0
END
Tower AC 131.63 % 136.36 % 3970.0 B 5413.33 139.25
AEP 05ROCKPT-05JEFRSO 765.0 kV Ckt 1 line
243209 to 243208 ckt 1
AEP_P7-1_#11014-A
CONTINGENCY 'AEP_P7-1_#11014-A'
 OPEN BRANCH FROM BUS 243217 TO BUS 247712 CKT 1   /*05DEQUIN     345.0 - 05SULLIVAN   345.0
 OPEN BRANCH FROM BUS 243217 TO BUS 963840 CKT 1   /*05DEQUIN     345.0 - AG1-237 TAP  345.0
END
Tower AC 131.43 % 136.22 % 3970.0 B 5407.74 143.03
AEP/DEI 05EUGENE-08CAYSUB 345.0 kV Ckt 1 line
243221 to 249504 ckt 1
AEP_P7-1_#11014-A
CONTINGENCY 'AEP_P7-1_#11014-A'
 OPEN BRANCH FROM BUS 243217 TO BUS 247712 CKT 1   /*05DEQUIN     345.0 - 05SULLIVAN   345.0
 OPEN BRANCH FROM BUS 243217 TO BUS 963840 CKT 1   /*05DEQUIN     345.0 - AG1-237 TAP  345.0
END
Tower AC 131.03 % 132.31 % 1374.0 B 1817.88 28.98
AEP/DEI 05EUGENE-08CAYSUB 345.0 kV Ckt 1 line
243221 to 249504 ckt 1
AEP_P7-1_#11014-B
CONTINGENCY 'AEP_P7-1_#11014-B'
 OPEN BRANCH FROM BUS 243217 TO BUS 247712 CKT 1   /*05DEQUIN     345.0 - 05SULLIVAN   345.0
 OPEN BRANCH FROM BUS 963840 TO BUS 963740 CKT 1   /*AG1-237 TAP  345.0 - AG1-226 TAP  345.0
END
Tower AC 124.74 % 125.98 % 1374.0 B 1730.94 28.98

Light Load Analysis

At this time light load analysis not required for this project.

System Reinforcements

The table below lists all network upgrades which resolve the identified overloaded facilities in this report.

Important to Note:

Note for Uprate Projects: Per Tariff Part VII, Subpart B, section 304 (B), if a project is an uprate (project relies on the Interconnection Facilities of a prior project) whose base project does not qualify for the expedited process, the uprate also will not qualify for the expedited process, regardless of analysis results.

Notes regarding Results displayed:

  1. Some flowgate overloads that a New Service Request contributes to, but does not contribute enough to meet cost allocation eligibility (per Manual 14A, Attachment B.3), may be reported in this Transition Sort report. These types of flowgates do not affect the classification of the New Service Request as either Expedited Process or Transition Cycle #1 because cost allocation eligibility has not been met.
  2. For projects that were determined to not meet Expedited Process eligibility and are being reprioritized to Transition Cycle #1, not all reinforcements in excess of $5,000,000 may be shown in this report. This report may only display a subset of those reinforcements determined to be in excess of $5,000,000 which would classify the project as not meeting Expedited Process Eligibility. This is not a formal System Impact Study.
  3. Reinforcements previously identified by Transmission Owners for violations on lower voltage facilities are included in this report. Transmission Owner analysis will be updated as part of the Expedited Process and Transition Cycle 1 retools.
System Reinforcements
RTEP ID Title Total Cost
n7980.2 Rebuild 47.02 miles of 1414 ACSR/PE, conductor section 2 $94,000,000
n7980.1 Rebuild 3.83 miles of 2303.5 ACAR , conductor section 1 $7,660,000
(TBD) An engineering study will need to be conducted for the Relay Settings. $25,000
n7964 Replace 765/345 Transformer $6,000,000
n7943.2 Replace Jefferson 345kV Circuit Breaker (5000A) $1,200,000
n7943.3 An engineering study will need to be conducted to determine if the Jefferso [...] l be required if the settings cannot be adjusted. Estimated Cost: $600,000. $25,000
n6497.1 An engineering study will need to be conducted to determine if the Rockport [...] ll be required if the settings cannot be adjusted, Estimated Cost: $600,000 $50,144
n6497.2 Replace 6 Rockport Current Transformers 3000Amps $4,800,000
n6497.3 Replace 2 Rockport 3000A non-oil Breakers at Rockport $6,000,000
s2280 Replace Rockport CB’s B, B2, C and C2 with 765kV SFMT 4000A Cb’s $0
n6497.4 AEPI0002e: Replace 3 3000A Wavetraps at Rockport $150k; AEPI0002f Replace 3 3000A Wavetraps at Jefferson $150k $426,497
n6497.5 Replace 12 3000A switches at Rockport $6,000,000
b2878 Upgrade the Clifty Creek 345 kV risers $3,675,000
n4106 Replace Two (2) Switches at the Clifty Creek 345 kV Station $412,916
b3748 Replace four Clifty Creek 345 kV 3000A switches with 5000 A 345 kV switches $850,000
n4106.3 Extend One (1) Tower on the Jefferson - Clifty Creek (IKEC) 345 kV Circuit $409,714
n4106.4 Rebuild 0.75 miles of ACSR ~ 2156 ~ 64/19 ~ BLUEBIRD conductor to mitigate the overload. $2,500,000
n4106.5 Replace Clifty Bus 5"0 AL Tubular Sch 40 $100,000
n4106.6 Replace Jefferson Breaker (5000A) $1,200,000
n4106.7 An engineering study will need to be conducted to determine if the Jefferso [...] l be required if the settings cannot be adjusted. Estimated Cost: $600,000. $25,000
(TBD) An engineering study will need to be conducted to determine if the Clifty R [...] l be required if the settings cannot be adjusted. Estimated Cost: $600,000. $25,000
n6781 A Sag Study will be required on the ~0.5 miles section of 954 2x Rail Condu [...] t sag study) and $0.75 million (complete line reconductor/rebuild required) $25,000
s2280 Sullivan 765/345kV Station: Replace Sullivan CB A2 765kV CB and associated equipment. Replace Rockport CB’s B, B2, C and C2 with 765kV SFMT 4000A Cb’s $0
n7925.3 Replace two sullivan 3000A Wavetrap $400,000
n7925.2 Reconductor/rebuild 1 miles of ACAR ~ 1024.5 ~ 30/7 ~ RAIL1 conductor section 6 $2,000,000
n7925.1 Reconductor/rebuild 0.82 miles of ACAR ~ 1024.5 ~ 30/7 ~ RAIL1 conductor section 5 $1,640,000
b2943 PJM Baseline Upgrade b2943. Perform a LIDAR study on the Clifty Creek - Dea [...] rating. The baseline project had a projected in-service date of 12/01/2020. $127,896
n7979 Replace one 1600 A Wavetrap at Clifty Creek, $200k, 12-18 months. The new SE rating is 1281 MVA SE. $200,000

Attachments

Export to CSV Download all tables in report

Uprate Chain
Project Project Status MFO MWE MWC Disposition
AG1-522 Active 300.0 300.0 180.0 Transition Cycle 1
AG1-523 Active 600.0 300.0 180.0 Transition Cycle 1
AG1-524 Active 900.0 300.0 180.0 Transition Cycle 1
AG1-525 Active 1200.0 300.0 180.0 Transition Cycle 1

Conclusion

The Transition Sort load flow retool results indicate that AG1-523 is not eligible for the Expedited Process per PJM Tariff Part VII, Subpart B, section 304 (A) will be reprioritized to Transition Cycle #1. See next steps for your project in the "Introduction" section above.