AG1-471 Transition Sort Retool Results -- Reprioritized to Transition Cycle #1

v1.00 released 2023-12-14 10:55

Up Church-Wayne County 69 kV

36.0 MW Capacity / 60.0 MW Energy

Introduction

In accordance with Tariff Part VII, Subpart B, section 304, PJM performed load flow analysis (Transition Sort Retool) on all AE1 through AG1 projects that have met eligibility requirements according to Tariff, Part VII, Subpart B, section 303. The purpose of this study is to determine whether a project would be classified as eligible for the Expedited Process (Fast Lane) or if it would be reprioritized to be studied as part of Transition Cycle #1 (TC1) using the criteria from the Expedited Process Eligibility section of Tariff Part VII, section 304. This is not a System Impact Study report.

Below are the results of the study, details of how the study was performed, criterion used in the evaluation of the Expedited Process vs. TC1 determination, and next steps in the interconnection process for your project.

Transition Cycle #1:

The AG1-471 project has not met the Expedited Process Eligibility requirements in Tariff Part VII, Subpart B, section 304 and will therefore be reprioritized to Transition Cycle #1. Please see "Transition Cycle #1 Rules" below.

Transition Sort Retool Study Process and Criteria:

In order to determine Expedited Process vs. Transition Cycle #1 classification, projects which met the Transition Eligibility requirements from Tariff Part VII, Subpart B, section 303 were studied on the base case model that was used for the original System Impact Study analysis. Both a summer peak and light load load flow analysis were performed. Projects that have cost allocation eligibility or are identified as the first to cause a system violation which requires the need for a Network Upgrade with a total estimated cost greater than $5 million will be reprioritized to Transition Cycle #1. All other projects will be eligible for the expedited procedures set forth in Tariff Part VII, Subpart B, section 304 (B).

Expedited Process Eligibility: OATT Tariff Part VII, section 304:

A project is not eligible for the expedited process if it has cost allocation eligibility or is identified as the first to cause, as determined according to Tariff, Part VI, section 217.3, for a Network Upgrade which has a total estimated cost of greater than $5,000,000. Such cost estimate will be based on Transmission Provider's most recently available data.

Not considered in the Transition Sorting: The cost of the Interconnection Facilities is not considered when determining a project's eligibility for the expedited process. Affected Systems upgrade costs are also not considered in the evaluation.

Transition Sort Retool Results Provided:

This report includes a list of:

  1. the overloaded flowgates (overloaded facilities + contingency pair) that the project contributes towards
  2. other interconnection projects that may also contribute to the overloaded facility, and
  3. the total estimated cost for any required Network Upgrades.

Important Notes:

Note for Uprate Projects: Per Tariff Part VII, Subpart B, section 304 (B), if a project is an uprate (project relies on the Interconnection Facilities of a prior project) whose base project does not qualify for the expedited process, the uprate also will not qualify for the expedited process, regardless of analysis results.

Notes regarding Results displayed:

  1. Some flowgate overloads that a New Service Request contributes to, but does not contribute enough to meet cost allocation eligibility (per Manual 14A, Attachment B.3), may be reported in this Transition Sort report. These types of flowgates do not affect the classification of the New Service Request as either Expedited Process or Transition Cycle #1 because cost allocation eligibility has not been met.
  2. For projects that were determined to not meet Expedited Process eligibility and are being reprioritized to Transition Cycle #1, not all reinforcements in excess of $5,000,000 may be shown in this report. This report may only display a subset of those reinforcements determined to be in excess of $5,000,000 which would classify the project as not meeting Expedited Process Eligibility. This is not a formal System Impact Study.

Next Steps for your project:

Transition Cycle #1 Rules:

Refer to Tariff Part VII, Subpart B, section 304 (C) for the Transition Cycle #1 Project Rules.

Transition Cycle #1 will start no later than one year from the Transition Start Date (July 10, 2023). Transition Cycle #1 will run simultaneously with the expedited process, however Transition Cycle #1, Phase III will not begin until all expedited process projects have been completed.

Projects that are reprioritized to Transition Cycle #1 will not need to re-apply to the Interconnection Cycle Process. Therefore, there is no Application Review Phase for Transition Cycle #1. The cycle process for Transition Cycle #1 includes three Study Phases and three Decision Points:

  1. Phase I System Impact Study and Decision Point I; and
  2. Phase II System Impact Study and Decision Point II; and
  3. Phase III System Impact Study and Decision Point III

Refer to Tariff Part VII, Subpart D, section 307 for the Transition Cycle #1 study process.

General

The Interconnection Customer (IC), has proposed a Solar generating facility located in the EKPC zone — Wayne County, Kentucky. The installed facilities will have a total capability of 60.0 MW with 36.0 MW of this output being recognized by PJM as Capacity.

Project Information
Queue Number AG1-471
Project Name Up Church-Wayne County 69 kV
Developer Name Barrelhead Solar, LLC
State Kentucky
County Wayne
Transmission Owner EKPC
MFO 60.0 MW
MWE 60.0 MW
MWC 36.0 MW
Fuel Type Solar
Basecase Study Year 2024

Point of Interconnection

AG1-471 will interconnect on the EKPC transmission system tapping the Upchurch to Wayne County 69 kV line.

Summer Peak Analysis

The Queue Project was evaluated as a 60.0 MW (Capacity 36.0 MW) injection in the EKPC area. Project was evaluated for compliance with applicable reliability planning criteria (PJM, NERC, NERC Regional Reliability Councils, and Transmission Owners). Potential Summer peak period network impacts are listed below:

Important to Note:

Note for Uprate Projects: Per Tariff Part VII, Subpart B, section 304 (B), if a project is an uprate (project relies on the Interconnection Facilities of a prior project) whose base project does not qualify for the expedited process, the uprate also will not qualify for the expedited process, regardless of analysis results.

Notes regarding Results displayed:

  1. Some flowgate overloads that a New Service Request contributes to, but does not contribute enough to meet cost allocation eligibility (per Manual 14A, Attachment B.3), may be reported in this Transition Sort report. These types of flowgates do not affect the classification of the New Service Request as either Expedited Process or Transition Cycle #1 because cost allocation eligibility has not been met.
  2. For projects that were determined to not meet Expedited Process eligibility and are being reprioritized to Transition Cycle #1, not all reinforcements in excess of $5,000,000 may be shown in this report. This report may only display a subset of those reinforcements determined to be in excess of $5,000,000 which would classify the project as not meeting Expedited Process Eligibility. This is not a formal System Impact Study.
Summer Peak Analysis
Area Facility Description Contingency Name Contingency Type DC|AC Initial Loading Final Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Details
EKPC/LGEE 5COOPER2-5ELIHU 161.0 kV Ckt 1 line
342718 to 324141 ckt 1
EKPC_P2-1_5LAUREL CO 161.00 TO 5LAUREL DAM 161.00
CONTINGENCY 'EKPC_P2-1_5LAUREL CO 161.00 TO 5LAUREL DAM 161.00'
 OPEN BRANCH FROM BUS 342754 TO BUS 342757 CKT 1   /*5LAUREL CO   161.0 - 5LAUREL DAM  161.0
END
Single AC 109.63 % 112.35 % 277.0 B 311.21 7.32
EKPC 5LAUREL DAM-5LAUREL CO 161.0 kV Ckt 1 line
342757 to 342754 ckt 1
EXT_B-69-25
CONTINGENCY 'EXT_B-69-25'
 OPEN BRANCH FROM BUS 324130 TO BUS 324141 CKT 1   /*5ALCALDE     161.0 - 5ELIHU       161.0
 OPEN BRANCH FROM BUS 324141 TO BUS 324514 CKT 1   /*5ELIHU       161.0 - 2ELIHU        69.0
 OPEN BRANCH FROM BUS 324141 TO BUS 324514 CKT 2   /*5ELIHU       161.0 - 2ELIHU        69.0
 OPEN BRANCH FROM BUS 324141 TO BUS 342718 CKT 1   /*5ELIHU       161.0 - 5COOPER2     161.0
END
Single AC 106.47 % 108.48 % 200.0 B 216.96 3.88
EKPC 5LAUREL DAM-5LAUREL CO 161.0 kV Ckt 1 line
342757 to 342754 ckt 1
EXT_324130 5ALCALDE 161 324141 5ELIHU 161 1
CONTINGENCY 'EXT_324130 5ALCALDE 161 324141 5ELIHU 161 1'
 OPEN BRANCH FROM BUS 324130 TO BUS 324141 CKT 1   /*5ALCALDE     161.0 - 5ELIHU       161.0
END
Single AC 102.94 % 104.95 % 200.0 B 209.9 3.88
EKPC/LGEE 5COOPER2-5ELIHU 161.0 kV Ckt 1 line
342718 to 324141 ckt 1
EKPC_P4-5_LAURL S50-1024
CONTINGENCY 'EKPC_P4-5_LAURL S50-1024'
 OPEN BRANCH FROM BUS 324688 TO BUS 342781 CKT 1   /*2PITTSBRG KU  69.0 - 5PITTSBURG   161.0
 OPEN BRANCH FROM BUS 342781 TO BUS 342820 CKT 1   /*5PITTSBURG   161.0 - 5TYNER       161.0
 OPEN BUS 342754                                   /*5LAUREL CO   161.0
END
Breaker AC 130.24 % 134.71 % 277.0 B 373.15 12.17
EKPC/LGEE 2SOMERSET KU-2FERGUSON SO 69.0 kV Ckt 1 line
342287 to 324531 ckt 1
EKPC_P2-3_COOP S42-1064
CONTINGENCY 'EKPC_P2-3_COOP S42-1064'
 OPEN BRANCH FROM BUS 341392 TO BUS 342727 CKT 1   /*2DENNY        69.0 - 5DENNY       161.0
 OPEN BUS 342718                                   /*5COOPER2     161.0
 OPEN BUS 342903                                   /*1COOPER2 G    20.0
END
Breaker AC 116.31 % 124.25 % 105.0 B 130.46 8.35
EKPC/LGEE 2SOMERSET KU-2FERGUSON SO 69.0 kV Ckt 1 line
342287 to 324531 ckt 1
EKPC_P2-3_COOP S42-210G
CONTINGENCY 'EKPC_P2-3_COOP S42-210G'
 OPEN BUS 342718   /*5COOPER2     161.0
 OPEN BUS 342903   /*1COOPER2 G    20.0
END
Breaker AC 116.3 % 124.24 % 105.0 B 130.45 8.35
EKPC/LGEE 2SOMERSET KU-2FERGUSON SO 69.0 kV Ckt 1 line
342287 to 324531 ckt 1
EKPC_P2-2_COOPER 2 161
CONTINGENCY 'EKPC_P2-2_COOPER 2 161'
 OPEN BUS 342718   /*5COOPER2     161.0
END
Bus AC 116.37 % 124.31 % 105.0 B 130.53 8.35
EKPC/LGEE 2SOMERSET KU-2FERGUSON SO 69.0 kV Ckt 1 line
342287 to 324531 ckt 1
EKPC_P7-1_COOP 161 DBL 2
CONTINGENCY 'EKPC_P7-1_COOP 161 DBL 2'
 OPEN BRANCH FROM BUS 324141 TO BUS 342718 CKT 1   /*5ELIHU       161.0 - 5COOPER2     161.0
 OPEN BRANCH FROM BUS 342718 TO BUS 342757 CKT 1   /*5COOPER2     161.0 - 5LAUREL DAM  161.0
END
Tower AC 161.54 % 169.81 % 105.0 B 178.3 8.61
EKPC 2SOMERSET-2SOMERSET KU 69.0 kV Ckt 1 line
342286 to 342287 ckt 1
EKPC_P7-1_COOP 161 DBL 2
CONTINGENCY 'EKPC_P7-1_COOP 161 DBL 2'
 OPEN BRANCH FROM BUS 324141 TO BUS 342718 CKT 1   /*5ELIHU       161.0 - 5COOPER2     161.0
 OPEN BRANCH FROM BUS 342718 TO BUS 342757 CKT 1   /*5COOPER2     161.0 - 5LAUREL DAM  161.0
END
Tower AC 139.37 % 145.94 % 115.0 B 167.84 7.56
EKPC/LGEE 5COOPER2-5ELIHU 161.0 kV Ckt 1 line
342718 to 324141 ckt 1
EKPC_P7-1_LAURL 161 DBL
CONTINGENCY 'EKPC_P7-1_LAURL 161 DBL'
 OPEN BRANCH FROM BUS 342754 TO BUS 342757 CKT 1   /*5LAUREL CO   161.0 - 5LAUREL DAM  161.0
 OPEN BRANCH FROM BUS 342754 TO BUS 342781 CKT 1   /*5LAUREL CO   161.0 - 5PITTSBURG   161.0
 OPEN BRANCH FROM BUS 342781 TO BUS 342820 CKT 1   /*5PITTSBURG   161.0 - 5TYNER       161.0
END
Tower AC 130.32 % 134.79 % 277.0 B 373.37 12.17

Light Load Analysis

At this time light load analysis not required for this project.

System Reinforcements

The table below lists all network upgrades which resolve the identified overloaded facilities in this report.

Important to Note:

Note for Uprate Projects: Per Tariff Part VII, Subpart B, section 304 (B), if a project is an uprate (project relies on the Interconnection Facilities of a prior project) whose base project does not qualify for the expedited process, the uprate also will not qualify for the expedited process, regardless of analysis results.

Notes regarding Results displayed:

  1. Some flowgate overloads that a New Service Request contributes to, but does not contribute enough to meet cost allocation eligibility (per Manual 14A, Attachment B.3), may be reported in this Transition Sort report. These types of flowgates do not affect the classification of the New Service Request as either Expedited Process or Transition Cycle #1 because cost allocation eligibility has not been met.
  2. For projects that were determined to not meet Expedited Process eligibility and are being reprioritized to Transition Cycle #1, not all reinforcements in excess of $5,000,000 may be shown in this report. This report may only display a subset of those reinforcements determined to be in excess of $5,000,000 which would classify the project as not meeting Expedited Process Eligibility. This is not a formal System Impact Study.
  3. Reinforcements previously identified by Transmission Owners for violations on lower voltage facilities are included in this report. Transmission Owner analysis will be updated as part of the Expedited Process and Transition Cycle 1 retools.
System Reinforcements
RTEP ID Title Total Cost
n7773.3 Replace the 1200A circuit breaker S7-654 at Somerset substation with a 2000A circuit breaker $130,000
n7773.2 Replace the 795 MCM ACSR jumpers at the Somerset substation using bundled 500 MCM copper or equivalent $30,000
n7773.1 Replace the 1200A current transformer at Somerset with a 2000A current transformer. $35,000
n6232.1 Replace the 1200A interconnection metering CTs with 2000A equipment. $70,000
n6232 Replace the 500 MCM copper jumpers at the Somerset substation using 750 MCM copper or equivalent $250,000
n8368.1 Increase the maximum operating temperature of the 795 MCM ACSR conductor in the Cooper-Elihu 161 kV line section to 275 degrees F (6.7 miles) $680,000
n8368.2 Rebuild the Cooper-Elihu 161 kV line section using 954 MCM ACSS conductor (6.7 miles) $10,200,000
n8368.4 Upgrade the existing 795 MCM ACSR jumpers at the Cooper substation associated with the Cooper-Elihu 161 kV line using bundled 500 MCM CU or equivalent $30,000
(TBD) LGEE violation (non PJM area). EKPC continuous rating is 267 MVA. $0
n7771.2 Increase the maximum operating temperature of the Laurel County-Laurel Dam 161 kV line section 795 MCM conductor to 212 degrees F (~0.2 miles) $40,000
n7771.1 Increase the maximum operating temperature of the Laurel County-Laurel Dam 161 kV line section 795 MCM conductor to 167 degrees F (~0.2 miles) $35,000

Attachments

Conclusion

The Transition Sort load flow retool results indicate that AG1-471 is not eligible for the Expedited Process per PJM Tariff Part VII, Subpart B, section 304 (A) will be reprioritized to Transition Cycle #1. See next steps for your project in the "Introduction" section above.