AG1-437 Transition Sort Retool Results -- Reprioritized to Transition Cycle #1

v1.00 released 2023-12-14 10:49

Cashie-Earleys 230 kV

60.0 MW Capacity / 100.0 MW Energy

Introduction

In accordance with Tariff Part VII, Subpart B, section 304, PJM performed load flow analysis (Transition Sort Retool) on all AE1 through AG1 projects that have met eligibility requirements according to Tariff, Part VII, Subpart B, section 303. The purpose of this study is to determine whether a project would be classified as eligible for the Expedited Process (Fast Lane) or if it would be reprioritized to be studied as part of Transition Cycle #1 (TC1) using the criteria from the Expedited Process Eligibility section of Tariff Part VII, section 304. This is not a System Impact Study report.

Below are the results of the study, details of how the study was performed, criterion used in the evaluation of the Expedited Process vs. TC1 determination, and next steps in the interconnection process for your project.

Transition Cycle #1:

The AG1-437 project has not met the Expedited Process Eligibility requirements in Tariff Part VII, Subpart B, section 304 and will therefore be reprioritized to Transition Cycle #1. Please see "Transition Cycle #1 Rules" below.

Transition Sort Retool Study Process and Criteria:

In order to determine Expedited Process vs. Transition Cycle #1 classification, projects which met the Transition Eligibility requirements from Tariff Part VII, Subpart B, section 303 were studied on the base case model that was used for the original System Impact Study analysis. Both a summer peak and light load load flow analysis were performed. Projects that have cost allocation eligibility or are identified as the first to cause a system violation which requires the need for a Network Upgrade with a total estimated cost greater than $5 million will be reprioritized to Transition Cycle #1. All other projects will be eligible for the expedited procedures set forth in Tariff Part VII, Subpart B, section 304 (B).

Expedited Process Eligibility: OATT Tariff Part VII, section 304:

A project is not eligible for the expedited process if it has cost allocation eligibility or is identified as the first to cause, as determined according to Tariff, Part VI, section 217.3, for a Network Upgrade which has a total estimated cost of greater than $5,000,000. Such cost estimate will be based on Transmission Provider's most recently available data.

Not considered in the Transition Sorting: The cost of the Interconnection Facilities is not considered when determining a project's eligibility for the expedited process. Affected Systems upgrade costs are also not considered in the evaluation.

Transition Sort Retool Results Provided:

This report includes a list of:

  1. the overloaded flowgates (overloaded facilities + contingency pair) that the project contributes towards
  2. other interconnection projects that may also contribute to the overloaded facility, and
  3. the total estimated cost for any required Network Upgrades.

Important Notes:

Note for Uprate Projects: Per Tariff Part VII, Subpart B, section 304 (B), if a project is an uprate (project relies on the Interconnection Facilities of a prior project) whose base project does not qualify for the expedited process, the uprate also will not qualify for the expedited process, regardless of analysis results.

Notes regarding Results displayed:

  1. Some flowgate overloads that a New Service Request contributes to, but does not contribute enough to meet cost allocation eligibility (per Manual 14A, Attachment B.3), may be reported in this Transition Sort report. These types of flowgates do not affect the classification of the New Service Request as either Expedited Process or Transition Cycle #1 because cost allocation eligibility has not been met.
  2. For projects that were determined to not meet Expedited Process eligibility and are being reprioritized to Transition Cycle #1, not all reinforcements in excess of $5,000,000 may be shown in this report. This report may only display a subset of those reinforcements determined to be in excess of $5,000,000 which would classify the project as not meeting Expedited Process Eligibility. This is not a formal System Impact Study.

Next Steps for your project:

Transition Cycle #1 Rules:

Refer to Tariff Part VII, Subpart B, section 304 (C) for the Transition Cycle #1 Project Rules.

Transition Cycle #1 will start no later than one year from the Transition Start Date (July 10, 2023). Transition Cycle #1 will run simultaneously with the expedited process, however Transition Cycle #1, Phase III will not begin until all expedited process projects have been completed.

Projects that are reprioritized to Transition Cycle #1 will not need to re-apply to the Interconnection Cycle Process. Therefore, there is no Application Review Phase for Transition Cycle #1. The cycle process for Transition Cycle #1 includes three Study Phases and three Decision Points:

  1. Phase I System Impact Study and Decision Point I; and
  2. Phase II System Impact Study and Decision Point II; and
  3. Phase III System Impact Study and Decision Point III

Refer to Tariff Part VII, Subpart D, section 307 for the Transition Cycle #1 study process.

General

The Interconnection Customer (IC), has proposed a Solar generating facility located in the Dominion zone — Bertie County, North Carolina. The installed facilities will have a total capability of 100.0 MW with 60.0 MW of this output being recognized by PJM as Capacity.

Project Information
Queue Number AG1-437
Project Name Cashie-Earleys 230 kV
Developer Name RWE Solar Development, LLC
State North Carolina
County Bertie
Transmission Owner Dominion
MFO 100.0 MW
MWE 100.0 MW
MWC 60.0 MW
Fuel Type Solar
Basecase Study Year 2024

Point of Interconnection

AG1-437 will interconnect with the Dominion transmission system tapping the Earleys to Cashie 230 kV line.

 

Summer Peak Analysis

The Queue Project was evaluated as a 100.0 MW (Capacity 60.0 MW) injection in the Dominion area. Project was evaluated for compliance with applicable reliability planning criteria (PJM, NERC, NERC Regional Reliability Councils, and Transmission Owners). Potential Summer peak period network impacts are listed below:

Important to Note:

Note for Uprate Projects: Per Tariff Part VII, Subpart B, section 304 (B), if a project is an uprate (project relies on the Interconnection Facilities of a prior project) whose base project does not qualify for the expedited process, the uprate also will not qualify for the expedited process, regardless of analysis results.

Notes regarding Results displayed:

  1. Some flowgate overloads that a New Service Request contributes to, but does not contribute enough to meet cost allocation eligibility (per Manual 14A, Attachment B.3), may be reported in this Transition Sort report. These types of flowgates do not affect the classification of the New Service Request as either Expedited Process or Transition Cycle #1 because cost allocation eligibility has not been met.
  2. For projects that were determined to not meet Expedited Process eligibility and are being reprioritized to Transition Cycle #1, not all reinforcements in excess of $5,000,000 may be shown in this report. This report may only display a subset of those reinforcements determined to be in excess of $5,000,000 which would classify the project as not meeting Expedited Process Eligibility. This is not a formal System Impact Study.
Summer Peak Analysis
Area Facility Description Contingency Name Contingency Type DC|AC Initial Loading Final Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Details
DVP 6DRY BREAD-6CLUBHSE 230.0 kV Ckt 1 line
313725 to 314563 ckt 1
DVP_P1-2: LN 246
CONTINGENCY 'DVP_P1-2: LN 246'
 OPEN BRANCH FROM BUS 314537 TO BUS 314575 CKT 1                /*6SUFFOLK     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314569 TO BUS 314575 CKT 1                /*6EARLEYS     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314575 TO BUS 314590 CKT 1                /*6NUCO TP     230.0 - 6NUCOR       230.0
 OPEN BUS 314575                                                /*6NUCO TP     230.0
 OPEN BUS 314590                                                /*6NUCOR       230.0
 SET POSTCONTRATING 876 BRANCH FROM BUS 314537 TO BUS 314648 CKT 1 /*6SUFFOLK     230.0 - 6SUNBURY     230.0
 SET PRECONTRATING 813 BRANCH FROM BUS 314537 TO BUS 314648 CKT 1 /*6SUFFOLK     230.0 - 6SUNBURY     230.0
END
Single AC 163.44 % 166.04 % 375.06 B 622.74 9.58
DVP 6DRY BREAD-6CLUBHSE 230.0 kV Ckt 1 line
313725 to 314563 ckt 1
314575 6NUCO TP 230 314537 6SUFFOLK 230 1
CONTINGENCY '314575 6NUCO TP      230  314537 6SUFFOLK   230  1'  /* Auto-generated
  /* 314575 6NUCO TP      230  314537 6SUFFOLK   230  1
END
Single AC 160.84 % 163.42 % 375.06 B 612.93 9.58
DVP 6EARLEYS-6NUCO TP 230.0 kV Ckt 1 line
314569 to 314575 ckt 1
DVP_P1-2: LN 2092
CONTINGENCY 'DVP_P1-2: LN 2092'
 OPEN BRANCH FROM BUS 313714 TO BUS 314662 CKT 1   /*6PERQUIMANS  230.0 - 6S HERTFORD  230.0
 OPEN BRANCH FROM BUS 314651 TO BUS 314662 CKT 1   /*6WINFALL     230.0 - 6S HERTFORD  230.0
 OPEN BUS 314662                                   /*6S HERTFORD  230.0
END
Single AC 146.07 % 150.03 % 571.52 B 857.43 22.13
DVP 6EARLEYS-6NUCO TP 230.0 kV Ckt 1 line
314569 to 314575 ckt 1
DVP_P1-2: LN 2131
CONTINGENCY 'DVP_P1-2: LN 2131'
 OPEN BRANCH FROM BUS 313714 TO BUS 313885 CKT 1   /*6PERQUIMANS  230.0 - 6WALBMRL     230.0
 OPEN BRANCH FROM BUS 313885 TO BUS 314637 CKT 1   /*6WALBMRL     230.0 - 6EDENTON     230.0
 OPEN BRANCH FROM BUS 314203 TO BUS 314637 CKT 1   /*6MACKEYS     230.0 - 6EDENTON     230.0
 OPEN BUS 313885                                   /*6WALBMRL     230.0
 OPEN BUS 314637                                   /*6EDENTON     230.0
END
Single AC 144.13 % 148.08 % 571.52 B 846.32 22.13
DVP 6LAKEVEW-6DRY BREAD 230.0 kV Ckt 1 line
314583 to 313725 ckt 1
DVP_P1-2: LN 246
CONTINGENCY 'DVP_P1-2: LN 246'
 OPEN BRANCH FROM BUS 314537 TO BUS 314575 CKT 1                /*6SUFFOLK     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314569 TO BUS 314575 CKT 1                /*6EARLEYS     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314575 TO BUS 314590 CKT 1                /*6NUCO TP     230.0 - 6NUCOR       230.0
 OPEN BUS 314575                                                /*6NUCO TP     230.0
 OPEN BUS 314590                                                /*6NUCOR       230.0
 SET POSTCONTRATING 876 BRANCH FROM BUS 314537 TO BUS 314648 CKT 1 /*6SUFFOLK     230.0 - 6SUNBURY     230.0
 SET PRECONTRATING 813 BRANCH FROM BUS 314537 TO BUS 314648 CKT 1 /*6SUFFOLK     230.0 - 6SUNBURY     230.0
END
Single AC 146.19 % 148.78 % 375.06 B 558.01 9.6
DVP 6LAKEVEW-6DRY BREAD 230.0 kV Ckt 1 line
314583 to 313725 ckt 1
314575 6NUCO TP 230 314537 6SUFFOLK 230 1
CONTINGENCY '314575 6NUCO TP      230  314537 6SUFFOLK   230  1'  /* Auto-generated
  /* 314575 6NUCO TP      230  314537 6SUFFOLK   230  1
END
Single AC 143.58 % 146.16 % 375.06 B 548.2 9.6
DVP 6NUCO TP-6SUFFOLK 230.0 kV Ckt 1 line
314575 to 314537 ckt 1
DVP_P1-2: LN 2092
CONTINGENCY 'DVP_P1-2: LN 2092'
 OPEN BRANCH FROM BUS 313714 TO BUS 314662 CKT 1   /*6PERQUIMANS  230.0 - 6S HERTFORD  230.0
 OPEN BRANCH FROM BUS 314651 TO BUS 314662 CKT 1   /*6WINFALL     230.0 - 6S HERTFORD  230.0
 OPEN BUS 314662                                   /*6S HERTFORD  230.0
END
Single AC 137.4 % 141.34 % 571.52 B 807.76 22.13
DVP 6NUCO TP-6SUFFOLK 230.0 kV Ckt 1 line
314575 to 314537 ckt 1
DVP_P1-2: LN 2131
CONTINGENCY 'DVP_P1-2: LN 2131'
 OPEN BRANCH FROM BUS 313714 TO BUS 313885 CKT 1   /*6PERQUIMANS  230.0 - 6WALBMRL     230.0
 OPEN BRANCH FROM BUS 313885 TO BUS 314637 CKT 1   /*6WALBMRL     230.0 - 6EDENTON     230.0
 OPEN BRANCH FROM BUS 314203 TO BUS 314637 CKT 1   /*6MACKEYS     230.0 - 6EDENTON     230.0
 OPEN BUS 313885                                   /*6WALBMRL     230.0
 OPEN BUS 314637                                   /*6EDENTON     230.0
END
Single AC 135.47 % 139.41 % 571.52 B 796.76 22.13
DVP 6DRY BREAD-6CLUBHSE 230.0 kV Ckt 1 line
313725 to 314563 ckt 1
Base Case Single AC 133.15 % 134.9 % 375.06 A 505.96 6.57
DVP 6SAPONY-6CARSON 230.0 kV Ckt 1 line
314435 to 314282 ckt 1
DVP_P1-2: LN 246
CONTINGENCY 'DVP_P1-2: LN 246'
 OPEN BRANCH FROM BUS 314537 TO BUS 314575 CKT 1                /*6SUFFOLK     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314569 TO BUS 314575 CKT 1                /*6EARLEYS     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314575 TO BUS 314590 CKT 1                /*6NUCO TP     230.0 - 6NUCOR       230.0
 OPEN BUS 314575                                                /*6NUCO TP     230.0
 OPEN BUS 314590                                                /*6NUCOR       230.0
 SET POSTCONTRATING 876 BRANCH FROM BUS 314537 TO BUS 314648 CKT 1 /*6SUFFOLK     230.0 - 6SUNBURY     230.0
 SET PRECONTRATING 813 BRANCH FROM BUS 314537 TO BUS 314648 CKT 1 /*6SUFFOLK     230.0 - 6SUNBURY     230.0
END
Single AC 132.18 % 133.63 % 678.68 B 906.92 10.0
DVP AE2-033 TAP-6SAPONY 230.0 kV Ckt 1 line
940480 to 314435 ckt 1
DVP_P1-2: LN 246
CONTINGENCY 'DVP_P1-2: LN 246'
 OPEN BRANCH FROM BUS 314537 TO BUS 314575 CKT 1                /*6SUFFOLK     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314569 TO BUS 314575 CKT 1                /*6EARLEYS     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314575 TO BUS 314590 CKT 1                /*6NUCO TP     230.0 - 6NUCOR       230.0
 OPEN BUS 314575                                                /*6NUCO TP     230.0
 OPEN BUS 314590                                                /*6NUCOR       230.0
 SET POSTCONTRATING 876 BRANCH FROM BUS 314537 TO BUS 314648 CKT 1 /*6SUFFOLK     230.0 - 6SUNBURY     230.0
 SET PRECONTRATING 813 BRANCH FROM BUS 314537 TO BUS 314648 CKT 1 /*6SUFFOLK     230.0 - 6SUNBURY     230.0
END
Single AC 133.64 % 134.92 % 678.68 B 915.65 10.0
DVP 6SAPONY-6CARSON 230.0 kV Ckt 1 line
314435 to 314282 ckt 1
314575 6NUCO TP 230 314537 6SUFFOLK 230 1
CONTINGENCY '314575 6NUCO TP      230  314537 6SUFFOLK   230  1'  /* Auto-generated
  /* 314575 6NUCO TP      230  314537 6SUFFOLK   230  1
END
Single AC 130.64 % 132.09 % 678.68 B 896.46 10.0
DVP AE2-033 TAP-6SAPONY 230.0 kV Ckt 1 line
940480 to 314435 ckt 1
314575 6NUCO TP 230 314537 6SUFFOLK 230 1
CONTINGENCY '314575 6NUCO TP      230  314537 6SUFFOLK   230  1'  /* Auto-generated
  /* 314575 6NUCO TP      230  314537 6SUFFOLK   230  1
END
Single AC 132.1 % 133.37 % 678.68 B 905.14 10.0
DVP 6CLUBHSE-AE2-033 TAP 230.0 kV Ckt 1 line
314563 to 940480 ckt 1
DVP_P1-2: LN 246
CONTINGENCY 'DVP_P1-2: LN 246'
 OPEN BRANCH FROM BUS 314537 TO BUS 314575 CKT 1                /*6SUFFOLK     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314569 TO BUS 314575 CKT 1                /*6EARLEYS     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314575 TO BUS 314590 CKT 1                /*6NUCO TP     230.0 - 6NUCOR       230.0
 OPEN BUS 314575                                                /*6NUCO TP     230.0
 OPEN BUS 314590                                                /*6NUCOR       230.0
 SET POSTCONTRATING 876 BRANCH FROM BUS 314537 TO BUS 314648 CKT 1 /*6SUFFOLK     230.0 - 6SUNBURY     230.0
 SET PRECONTRATING 813 BRANCH FROM BUS 314537 TO BUS 314648 CKT 1 /*6SUFFOLK     230.0 - 6SUNBURY     230.0
END
Single AC 123.8 % 125.33 % 678.68 B 850.58 10.0
DVP 6CLUBHSE-AE2-033 TAP 230.0 kV Ckt 1 line
314563 to 940480 ckt 1
314575 6NUCO TP 230 314537 6SUFFOLK 230 1
CONTINGENCY '314575 6NUCO TP      230  314537 6SUFFOLK   230  1'  /* Auto-generated
  /* 314575 6NUCO TP      230  314537 6SUFFOLK   230  1
END
Single AC 122.24 % 123.77 % 678.68 B 840.03 10.0
DVP 6LAKEVEW-6DRY BREAD 230.0 kV Ckt 1 line
314583 to 313725 ckt 1
Base Case Single AC 115.97 % 117.73 % 375.06 A 441.55 6.59
DVP AD1-057 TAP-6HATHAWAY 230.0 kV Ckt 1 line
934330 to 313845 ckt 1
314435 6SAPONY 230 940480 AE2-033 TAP 230 1
CONTINGENCY '314435 6SAPONY       230  940480 AE2-033 TAP   230  1'  /* Auto-generated
  /* 314435 6SAPONY       230  940480 AE2-033 TAP   230  1
END
Single AC 121.0 % 122.0 % 441.8 B 539.01 4.43
DVP AD1-057 TAP-6HATHAWAY 230.0 kV Ckt 1 line
934330 to 313845 ckt 1
DVP_P1-2: LN 238-A
CONTINGENCY 'DVP_P1-2: LN 238-A'
 OPEN BRANCH FROM BUS 314282 TO BUS 314435 CKT 1   /*6CARSON      230.0 - 6SAPONY      230.0
 OPEN BRANCH FROM BUS 314435 TO BUS 940480 CKT 1   /*6SAPONY      230.0 - AE2-033 TAP  230.0
 OPEN BUS 314435                                   /*6SAPONY      230.0
 OPEN BUS 923852                                   /*AB2-025 E    230.0
END
Single AC 120.97 % 121.98 % 441.8 B 538.92 4.43
DVP 6HORNRTN-AD1-057 TAP 230.0 kV Ckt 1 line
314579 to 934330 ckt 1
314435 6SAPONY 230 940480 AE2-033 TAP 230 1
CONTINGENCY '314435 6SAPONY       230  940480 AE2-033 TAP   230  1'  /* Auto-generated
  /* 314435 6SAPONY       230  940480 AE2-033 TAP   230  1
END
Single AC 112.87 % 113.87 % 441.8 B 503.06 4.43
DVP 6HORNRTN-AD1-057 TAP 230.0 kV Ckt 1 line
314579 to 934330 ckt 1
DVP_P1-2: LN 238-A
CONTINGENCY 'DVP_P1-2: LN 238-A'
 OPEN BRANCH FROM BUS 314282 TO BUS 314435 CKT 1   /*6CARSON      230.0 - 6SAPONY      230.0
 OPEN BRANCH FROM BUS 314435 TO BUS 940480 CKT 1   /*6SAPONY      230.0 - AE2-033 TAP  230.0
 OPEN BUS 314435                                   /*6SAPONY      230.0
 OPEN BUS 923852                                   /*AB2-025 E    230.0
END
Single AC 112.84 % 113.84 % 441.8 B 502.96 4.43
DVP 6EARLEYS-6NUCO TP 230.0 kV Ckt 1 line
314569 to 314575 ckt 1
Base Case Single AC 99.47 % 102.11 % 571.52 A 583.56 14.85
DVP 6S HERTFORD-6WINFALL 230.0 kV Ckt 1 line
314662 to 314651 ckt 1
DVP_P1-2: LN 246
CONTINGENCY 'DVP_P1-2: LN 246'
 OPEN BRANCH FROM BUS 314537 TO BUS 314575 CKT 1                /*6SUFFOLK     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314569 TO BUS 314575 CKT 1                /*6EARLEYS     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314575 TO BUS 314590 CKT 1                /*6NUCO TP     230.0 - 6NUCOR       230.0
 OPEN BUS 314575                                                /*6NUCO TP     230.0
 OPEN BUS 314590                                                /*6NUCOR       230.0
 SET POSTCONTRATING 876 BRANCH FROM BUS 314537 TO BUS 314648 CKT 1 /*6SUFFOLK     230.0 - 6SUNBURY     230.0
 SET PRECONTRATING 813 BRANCH FROM BUS 314537 TO BUS 314648 CKT 1 /*6SUFFOLK     230.0 - 6SUNBURY     230.0
END
Single AC 99.19 % 102.17 % 733.2 B 749.14 20.88
DVP 6PERQUIMANS-6S HERTFORD 230.0 kV Ckt 1 line
313714 to 314662 ckt 1
DVP_P1-2: LN 246
CONTINGENCY 'DVP_P1-2: LN 246'
 OPEN BRANCH FROM BUS 314537 TO BUS 314575 CKT 1                /*6SUFFOLK     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314569 TO BUS 314575 CKT 1                /*6EARLEYS     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314575 TO BUS 314590 CKT 1                /*6NUCO TP     230.0 - 6NUCOR       230.0
 OPEN BUS 314575                                                /*6NUCO TP     230.0
 OPEN BUS 314590                                                /*6NUCOR       230.0
 SET POSTCONTRATING 876 BRANCH FROM BUS 314537 TO BUS 314648 CKT 1 /*6SUFFOLK     230.0 - 6SUNBURY     230.0
 SET PRECONTRATING 813 BRANCH FROM BUS 314537 TO BUS 314648 CKT 1 /*6SUFFOLK     230.0 - 6SUNBURY     230.0
END
Single AC 98.46 % 101.45 % 733.2 B 743.82 20.88
DVP 6S HERTFORD-6WINFALL 230.0 kV Ckt 1 line
314662 to 314651 ckt 1
314575 6NUCO TP 230 314537 6SUFFOLK 230 1
CONTINGENCY '314575 6NUCO TP      230  314537 6SUFFOLK   230  1'  /* Auto-generated
  /* 314575 6NUCO TP      230  314537 6SUFFOLK   230  1
END
Single AC 97.53 % 100.51 % 733.2 B 736.94 20.88
DVP 6ELIZ CT-6SHAWBRO 230.0 kV Ckt 1 line
314638 to 314647 ckt 1
DVP_P4-2: 246T247
CONTINGENCY 'DVP_P4-2: 246T247'
 OPEN BRANCH FROM BUS 313713 TO BUS 314648 CKT 1   /*6SWAMP       230.0 - 6SUNBURY     230.0
 OPEN BRANCH FROM BUS 314537 TO BUS 314575 CKT 1   /*6SUFFOLK     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314537 TO BUS 314648 CKT 1   /*6SUFFOLK     230.0 - 6SUNBURY     230.0
 OPEN BRANCH FROM BUS 314569 TO BUS 314575 CKT 1   /*6EARLEYS     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314575 TO BUS 314590 CKT 1   /*6NUCO TP     230.0 - 6NUCOR       230.0
 OPEN BUS 314575                                   /*6NUCO TP     230.0
 OPEN BUS 314590                                   /*6NUCOR       230.0
 OPEN BUS 314648                                   /*6SUNBURY     230.0
END
Breaker AC 166.53 % 171.59 % 699.0 C 1199.41 29.55
CPLE/DVP 6EVERETS-6GREENVILE T 230.0 kV Ckt 1 line
314574 to 304451 ckt 1
DVP_P4-2: 246T247
CONTINGENCY 'DVP_P4-2: 246T247'
 OPEN BRANCH FROM BUS 313713 TO BUS 314648 CKT 1   /*6SWAMP       230.0 - 6SUNBURY     230.0
 OPEN BRANCH FROM BUS 314537 TO BUS 314575 CKT 1   /*6SUFFOLK     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314537 TO BUS 314648 CKT 1   /*6SUFFOLK     230.0 - 6SUNBURY     230.0
 OPEN BRANCH FROM BUS 314569 TO BUS 314575 CKT 1   /*6EARLEYS     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314575 TO BUS 314590 CKT 1   /*6NUCO TP     230.0 - 6NUCOR       230.0
 OPEN BUS 314575                                   /*6NUCO TP     230.0
 OPEN BUS 314590                                   /*6NUCOR       230.0
 OPEN BUS 314648                                   /*6SUNBURY     230.0
END
Breaker AC 137.67 % 141.77 % 478.0 B 677.66 20.37
DVP AG1-437 TAP-6EARLEYS 230.0 kV Ckt 1 line
965690 to 314569 ckt 1
DVP_P4-2: 2020T2144
CONTINGENCY 'DVP_P4-2: 2020T2144'
 OPEN BRANCH FROM BUS 313713 TO BUS 314651 CKT 1   /*6SWAMP       230.0 - 6WINFALL     230.0
 OPEN BRANCH FROM BUS 313851 TO BUS 314638 CKT 1   /*6ECITYDP2    230.0 - 6ELIZ CT     230.0
 OPEN BRANCH FROM BUS 313851 TO BUS 314639 CKT 1   /*6ECITYDP2    230.0 - 6TANGLEW     230.0
 OPEN BRANCH FROM BUS 314639 TO BUS 314651 CKT 1   /*6TANGLEW     230.0 - 6WINFALL     230.0
 OPEN BUS 313851                                   /*6ECITYDP2    230.0
 OPEN BUS 314639                                   /*6TANGLEW     230.0
 OPEN BUS 917122                                   /*Z2-027 E     230.0
END
Breaker AC 123.59 % 135.71 % 699.0 C 948.6 84.47
CPLE/DVP 6EVERETS-6GREENVILE T 230.0 kV Ckt 1 line
314574 to 304451 ckt 1
DVP_P4-2: 2058T2167
CONTINGENCY 'DVP_P4-2: 2058T2167'
 OPEN BRANCH FROM BUS 304222 TO BUS 313845 CKT 1   /*6ROCKYMT230T 230.0 - 6HATHAWAY    230.0
 OPEN BRANCH FROM BUS 313844 TO BUS 313845 CKT 2   /*3HATHAWAY    115.0 - 6HATHAWAY    230.0
 OPEN BRANCH FROM BUS 313845 TO BUS 314564 CKT 1   /*6HATHAWAY    230.0 - 6EDGECOM     230.0
END
Breaker AC 107.59 % 111.3 % 478.0 B 532.03 18.38
DVP 6POE-6HARROWG 230.0 kV Ckt 1 line
314331 to 314299 ckt 1
DVP_P4-2: 24972-4
CONTINGENCY 'DVP_P4-2: 24972-4'
 OPEN BRANCH FROM BUS 314282 TO BUS 314285 CKT 1   /*6CARSON      230.0 - 6CHRL249     230.0
 OPEN BRANCH FROM BUS 314282 TO BUS 314902 CKT 1   /*6CARSON      230.0 - 8CARSON      500.0
 OPEN BRANCH FROM BUS 314285 TO BUS 314316 CKT 1   /*6CHRL249     230.0 - 6LOCKS       230.0
 OPEN BRANCH FROM BUS 314314 TO BUS 314316 CKT 2   /*3LOCKS       115.0 - 6LOCKS       230.0
 OPEN BUS 314285                                   /*6CHRL249     230.0
 OPEN BUS 314455                                   /*6CARSO_1     230.0
END
Breaker AC 133.97 % 134.97 % 541.0 C 730.17 8.21
DVP 6HARROWG-6TYLER1 230.0 kV Ckt 1 line
314299 to 314263 ckt 1
DVP_P4-2: 24972-4
CONTINGENCY 'DVP_P4-2: 24972-4'
 OPEN BRANCH FROM BUS 314282 TO BUS 314285 CKT 1   /*6CARSON      230.0 - 6CHRL249     230.0
 OPEN BRANCH FROM BUS 314282 TO BUS 314902 CKT 1   /*6CARSON      230.0 - 8CARSON      500.0
 OPEN BRANCH FROM BUS 314285 TO BUS 314316 CKT 1   /*6CHRL249     230.0 - 6LOCKS       230.0
 OPEN BRANCH FROM BUS 314314 TO BUS 314316 CKT 2   /*3LOCKS       115.0 - 6LOCKS       230.0
 OPEN BUS 314285                                   /*6CHRL249     230.0
 OPEN BUS 314455                                   /*6CARSO_1     230.0
END
Breaker AC 133.89 % 134.88 % 541.0 C 729.72 8.21
DVP 6ELIZ CT-6SHAWBRO 230.0 kV Ckt 1 line
314638 to 314647 ckt 1
DVP_P4-2: 24742
CONTINGENCY 'DVP_P4-2: 24742'
 OPEN BRANCH FROM BUS 313713 TO BUS 314648 CKT 1   /*6SWAMP       230.0 - 6SUNBURY     230.0
 OPEN BRANCH FROM BUS 314536 TO BUS 314537 CKT 1   /*3SUFFOLK     115.0 - 6SUFFOLK     230.0
 OPEN BRANCH FROM BUS 314537 TO BUS 314648 CKT 1   /*6SUFFOLK     230.0 - 6SUNBURY     230.0
 OPEN BRANCH FROM BUS 314537 TO BUS 314928 CKT 1   /*6SUFFOLK     230.0 - 8SUFFOLK     500.0
 OPEN BUS 314648                                   /*6SUNBURY     230.0
 REMOVE SWSHUNT FROM BUS 314537                    /*6SUFFOLK     230.0
END
Breaker AC 133.71 % 137.21 % 699.0 C 959.11 23.14
DVP 6S HERTFORD-6WINFALL 230.0 kV Ckt 1 line
314662 to 314651 ckt 1
DVP_P4-2: 24642
CONTINGENCY 'DVP_P4-2: 24642'
 OPEN BRANCH FROM BUS 314536 TO BUS 314537 CKT 3   /*3SUFFOLK     115.0 - 6SUFFOLK     230.0
 OPEN BRANCH FROM BUS 314537 TO BUS 314575 CKT 1   /*6SUFFOLK     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314537 TO BUS 314928 CKT 2   /*6SUFFOLK     230.0 - 8SUFFOLK     500.0
 OPEN BRANCH FROM BUS 314569 TO BUS 314575 CKT 1   /*6EARLEYS     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314575 TO BUS 314590 CKT 1   /*6NUCO TP     230.0 - 6NUCOR       230.0
 OPEN BUS 314575                                   /*6NUCO TP     230.0
 OPEN BUS 314590                                   /*6NUCOR       230.0
END
Breaker AC 120.3 % 124.55 % 897.0 C 1117.21 34.64
DVP 6PERQUIMANS-6S HERTFORD 230.0 kV Ckt 1 line
313714 to 314662 ckt 1
DVP_P4-2: 24642
CONTINGENCY 'DVP_P4-2: 24642'
 OPEN BRANCH FROM BUS 314536 TO BUS 314537 CKT 3   /*3SUFFOLK     115.0 - 6SUFFOLK     230.0
 OPEN BRANCH FROM BUS 314537 TO BUS 314575 CKT 1   /*6SUFFOLK     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314537 TO BUS 314928 CKT 2   /*6SUFFOLK     230.0 - 8SUFFOLK     500.0
 OPEN BRANCH FROM BUS 314569 TO BUS 314575 CKT 1   /*6EARLEYS     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314575 TO BUS 314590 CKT 1   /*6NUCO TP     230.0 - 6NUCOR       230.0
 OPEN BUS 314575                                   /*6NUCO TP     230.0
 OPEN BUS 314590                                   /*6NUCOR       230.0
END
Breaker AC 119.68 % 123.93 % 897.0 C 1111.66 34.64
DVP 6EDENTON-6WALBMRL 230.0 kV Ckt 1 line
314637 to 313885 ckt 1
DVP_P4-2: 24642
CONTINGENCY 'DVP_P4-2: 24642'
 OPEN BRANCH FROM BUS 314536 TO BUS 314537 CKT 3   /*3SUFFOLK     115.0 - 6SUFFOLK     230.0
 OPEN BRANCH FROM BUS 314537 TO BUS 314575 CKT 1   /*6SUFFOLK     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314537 TO BUS 314928 CKT 2   /*6SUFFOLK     230.0 - 8SUFFOLK     500.0
 OPEN BRANCH FROM BUS 314569 TO BUS 314575 CKT 1   /*6EARLEYS     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314575 TO BUS 314590 CKT 1   /*6NUCO TP     230.0 - 6NUCOR       230.0
 OPEN BUS 314575                                   /*6NUCO TP     230.0
 OPEN BUS 314590                                   /*6NUCOR       230.0
END
Breaker AC 104.49 % 108.52 % 897.0 C 973.43 34.65
DVP 6WALBMRL-6PERQUIMANS 230.0 kV Ckt 1 line
313885 to 313714 ckt 1
DVP_P4-2: 24642
CONTINGENCY 'DVP_P4-2: 24642'
 OPEN BRANCH FROM BUS 314536 TO BUS 314537 CKT 3   /*3SUFFOLK     115.0 - 6SUFFOLK     230.0
 OPEN BRANCH FROM BUS 314537 TO BUS 314575 CKT 1   /*6SUFFOLK     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314537 TO BUS 314928 CKT 2   /*6SUFFOLK     230.0 - 8SUFFOLK     500.0
 OPEN BRANCH FROM BUS 314569 TO BUS 314575 CKT 1   /*6EARLEYS     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314575 TO BUS 314590 CKT 1   /*6NUCO TP     230.0 - 6NUCOR       230.0
 OPEN BUS 314575                                   /*6NUCO TP     230.0
 OPEN BUS 314590                                   /*6NUCOR       230.0
END
Breaker AC 104.48 % 108.52 % 897.0 C 973.38 34.65
DVP 6MACKEYS-6EDENTON 230.0 kV Ckt 1 line
314203 to 314637 ckt 1
DVP_P4-2: 24642
CONTINGENCY 'DVP_P4-2: 24642'
 OPEN BRANCH FROM BUS 314536 TO BUS 314537 CKT 3   /*3SUFFOLK     115.0 - 6SUFFOLK     230.0
 OPEN BRANCH FROM BUS 314537 TO BUS 314575 CKT 1   /*6SUFFOLK     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314537 TO BUS 314928 CKT 2   /*6SUFFOLK     230.0 - 8SUFFOLK     500.0
 OPEN BRANCH FROM BUS 314569 TO BUS 314575 CKT 1   /*6EARLEYS     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314575 TO BUS 314590 CKT 1   /*6NUCO TP     230.0 - 6NUCOR       230.0
 OPEN BUS 314575                                   /*6NUCO TP     230.0
 OPEN BUS 314590                                   /*6NUCOR       230.0
END
Breaker AC 104.39 % 108.42 % 897.0 C 972.54 34.65
DVP 6WINFALL-6TANGLEW 230.0 kV Ckt 1 line
314651 to 314639 ckt 1
DVP_P4-2: 246T247
CONTINGENCY 'DVP_P4-2: 246T247'
 OPEN BRANCH FROM BUS 313713 TO BUS 314648 CKT 1   /*6SWAMP       230.0 - 6SUNBURY     230.0
 OPEN BRANCH FROM BUS 314537 TO BUS 314575 CKT 1   /*6SUFFOLK     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314537 TO BUS 314648 CKT 1   /*6SUFFOLK     230.0 - 6SUNBURY     230.0
 OPEN BRANCH FROM BUS 314569 TO BUS 314575 CKT 1   /*6EARLEYS     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314575 TO BUS 314590 CKT 1   /*6NUCO TP     230.0 - 6NUCOR       230.0
 OPEN BUS 314575                                   /*6NUCO TP     230.0
 OPEN BUS 314590                                   /*6NUCOR       230.0
 OPEN BUS 314648                                   /*6SUNBURY     230.0
END
Breaker AC 107.69 % 110.63 % 1204.0 C 1331.95 29.56
DVP 6TANGLEW-6ECITYDP2 230.0 kV Ckt 1 line
314639 to 313851 ckt 1
DVP_P4-2: 246T247
CONTINGENCY 'DVP_P4-2: 246T247'
 OPEN BRANCH FROM BUS 313713 TO BUS 314648 CKT 1   /*6SWAMP       230.0 - 6SUNBURY     230.0
 OPEN BRANCH FROM BUS 314537 TO BUS 314575 CKT 1   /*6SUFFOLK     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314537 TO BUS 314648 CKT 1   /*6SUFFOLK     230.0 - 6SUNBURY     230.0
 OPEN BRANCH FROM BUS 314569 TO BUS 314575 CKT 1   /*6EARLEYS     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314575 TO BUS 314590 CKT 1   /*6NUCO TP     230.0 - 6NUCOR       230.0
 OPEN BUS 314575                                   /*6NUCO TP     230.0
 OPEN BUS 314590                                   /*6NUCOR       230.0
 OPEN BUS 314648                                   /*6SUNBURY     230.0
END
Breaker AC 104.59 % 107.28 % 1204.0 C 1291.68 29.56
DVP 6ECITYDP2-6ELIZ CT 230.0 kV Ckt 1 line
313851 to 314638 ckt 1
DVP_P4-2: 246T247
CONTINGENCY 'DVP_P4-2: 246T247'
 OPEN BRANCH FROM BUS 313713 TO BUS 314648 CKT 1   /*6SWAMP       230.0 - 6SUNBURY     230.0
 OPEN BRANCH FROM BUS 314537 TO BUS 314575 CKT 1   /*6SUFFOLK     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314537 TO BUS 314648 CKT 1   /*6SUFFOLK     230.0 - 6SUNBURY     230.0
 OPEN BRANCH FROM BUS 314569 TO BUS 314575 CKT 1   /*6EARLEYS     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314575 TO BUS 314590 CKT 1   /*6NUCO TP     230.0 - 6NUCOR       230.0
 OPEN BUS 314575                                   /*6NUCO TP     230.0
 OPEN BUS 314590                                   /*6NUCOR       230.0
 OPEN BUS 314648                                   /*6SUNBURY     230.0
END
Breaker AC 104.57 % 107.27 % 1204.0 C 1291.48 29.56
DVP 6SUFFOLK-8SUFFOLK 230.0/500.0 kV Ckt 2 transformer
314537 to 314928 ckt 2
DVP_P4-2: H7T565
CONTINGENCY 'DVP_P4-2: H7T565'
 OPEN BRANCH FROM BUS 314537 TO BUS 314928 CKT 1   /*6SUFFOLK     230.0 - 8SUFFOLK     500.0
 OPEN BRANCH FROM BUS 314927 TO BUS 314928 CKT 1   /*8YADKIN      500.0 - 8SUFFOLK     500.0
END
Breaker AC 99.55 % 101.25 % 1004.3 C 1016.89 19.78
CPLE/DVP 3BTLEBRO-3ROCKYMT115T 115.0 kV Ckt 1 line
314554 to 304223 ckt 1
DVP_P7-1: LN 2058-2181
CONTINGENCY 'DVP_P7-1: LN 2058-2181'
 OPEN BRANCH FROM BUS 304222 TO BUS 313845 CKT 1   /*6ROCKYMT230T 230.0 - 6HATHAWAY    230.0
 OPEN BRANCH FROM BUS 304226 TO BUS 314591 CKT 1   /*6PA-RMOUNT#4 230.0 - 6NASH        230.0
 OPEN BRANCH FROM BUS 313844 TO BUS 313845 CKT 2   /*3HATHAWAY    115.0 - 6HATHAWAY    230.0
 OPEN BRANCH FROM BUS 313845 TO BUS 314591 CKT 1   /*6HATHAWAY    230.0 - 6NASH        230.0
 OPEN BUS 304226                                   /*6PA-RMOUNT#4 230.0
 OPEN BUS 314591                                   /*6NASH        230.0
END
Tower AC 259.42 % 262.71 % 164.0 B 430.84 6.43
CPLE/DVP 6EVERETS-6GREENVILE T 230.0 kV Ckt 1 line
314574 to 304451 ckt 1
DVP_P7-1: LN 2058-2181
CONTINGENCY 'DVP_P7-1: LN 2058-2181'
 OPEN BRANCH FROM BUS 304222 TO BUS 313845 CKT 1   /*6ROCKYMT230T 230.0 - 6HATHAWAY    230.0
 OPEN BRANCH FROM BUS 304226 TO BUS 314591 CKT 1   /*6PA-RMOUNT#4 230.0 - 6NASH        230.0
 OPEN BRANCH FROM BUS 313844 TO BUS 313845 CKT 2   /*3HATHAWAY    115.0 - 6HATHAWAY    230.0
 OPEN BRANCH FROM BUS 313845 TO BUS 314591 CKT 1   /*6HATHAWAY    230.0 - 6NASH        230.0
 OPEN BUS 304226                                   /*6PA-RMOUNT#4 230.0
 OPEN BUS 314591                                   /*6NASH        230.0
END
Tower AC 140.62 % 143.59 % 478.0 B 686.35 17.58
AEP 05EDAN 1-05DANVL2 138.0 kV Ckt 1 line
242631 to 242620 ckt 1
AEP_P4_#11112_05J.FERR 765_A1
CONTINGENCY 'AEP_P4_#11112_05J.FERR 765_A1'
 OPEN BRANCH FROM BUS 242511 TO BUS 242514 CKT 1    /*05BROADF     765.0 - 05J.FERR     765.0
 OPEN BRANCH FROM BUS 242514 TO BUS 242520 CKT 1    /*05J.FERR     765.0 - 05J.FERR     500.0
 OPEN BRANCH FROM BUS 242520 TO BUS 306719 CKT 1    /*05J.FERR     500.0 - 8ANTIOCH     500.0
 OPEN BRANCH FROM BUS 242566 TO BUS 242567 CKT ZB   /*05BROADF     138.0 - 05BROADX     138.0
END
Breaker AC 148.57 % 149.67 % 402.0 B 601.69 5.37

Light Load Analysis

At this time light load analysis not required for this project.

System Reinforcements

The table below lists all network upgrades which resolve the identified overloaded facilities in this report.

Important to Note:

Note for Uprate Projects: Per Tariff Part VII, Subpart B, section 304 (B), if a project is an uprate (project relies on the Interconnection Facilities of a prior project) whose base project does not qualify for the expedited process, the uprate also will not qualify for the expedited process, regardless of analysis results.

Notes regarding Results displayed:

  1. Some flowgate overloads that a New Service Request contributes to, but does not contribute enough to meet cost allocation eligibility (per Manual 14A, Attachment B.3), may be reported in this Transition Sort report. These types of flowgates do not affect the classification of the New Service Request as either Expedited Process or Transition Cycle #1 because cost allocation eligibility has not been met.
  2. For projects that were determined to not meet Expedited Process eligibility and are being reprioritized to Transition Cycle #1, not all reinforcements in excess of $5,000,000 may be shown in this report. This report may only display a subset of those reinforcements determined to be in excess of $5,000,000 which would classify the project as not meeting Expedited Process Eligibility. This is not a formal System Impact Study.
  3. Reinforcements previously identified by Transmission Owners for violations on lower voltage facilities are included in this report. Transmission Owner analysis will be updated as part of the Expedited Process and Transition Cycle 1 retools.
System Reinforcements
RTEP ID Title Total Cost
n6124 PJM Network Upgrade n6124. Increasing the Danville East Danville 138 kV ci [...] e line. $8,249,851
n7754.1 AEPA0021g : Replace 5 Sub cond 2000 AAC 91 Str at Danville2 138kV station $0
n7754.2 AEPA0021h : Replace 3 Sub cond 2000 AAC 91 Str at East Danville 138kV station $0
s2143.2 Replace 2000A non-oil breaker on the 05EDAN 1-05DANVL2 138 kV line $0
n7754.3 The Danville - East Danville 138 kV Circuit will require higher capacity conductor to obtain a rating higher than the 482 MVA achieved by the initial rebuild to 1272 ACSR by AD1-152 . $456,572
n6618.1 Hathaway 115 kV Bus Split. $20,749
(TBD) Reconductor 8.5 miles RockyMt-Battleborro with single 795 ACSS-TW per phase, upgrade disconnect switches and CT ratios. $31,000,000
s2825.1 Rebuild entire line#2167 Edgecombe NUG to Hathaway. $39,500,000
n6118 Upgrade the breaker leads at DVPs Battleboro terminal will bring the rating to 239/239/239 MVA (Limited by terminal equipment at Rocky Mount) $100,000
s2825.2 Rebuild line #55 Tarboro to Hart Mills. $3,500,000
n6221 Rebuild 11.79 miles of 230 kV Line 238 from Sapony to Carson with 2-795 150C ACSR. $17,685,000
n8303 Wreck and rebuild 230 kV Line 238 from Clubhouse to AE2-033 TAP. $22,620,000
b3121 PJM Baseline Upgrade b3121: Rebuild Clubhouse-Lakeview 230 kV Line #254. $0
n6138 Rebuild 13.7 miles of 230 kV Line 246 from Earleys to Nucor Tap with 2-636 ACSR. $20,550,000
n8288 Wreck and rebuild 18.67 miles of the line 2034 from Earleys to AG1-437. $49,075,000
n6879 Wreck and rebuild 5.6 miles of existing single circuit line 2020 between El [...] ts. Add a three breaker station at Pasquotank and Elizabeth City DP 230 kV. $27,000,000
n6314 Rebuild 10.28 miles of 230 kV Line 2021 from Elizabeth City to Shawboro with 2-636 ACSR. $15,420,000
n6144 Rebuild 20.5 miles of 230 kV Line #218 from Everetts to Greenville with 2-636 ACSR $39,923,299
(TBD) Rebuild aging double circuit 230kV towers of Everets to Greenvile Line $19,000,000
(TBD) Reconductor one side of Everets to Greenvile 230 kV Line. $350,000
n6179 Rebuild 12.3 miles of 230 kV Line 2003 from Poe to Harrowgate with 2-636 ACSR. $30,750,000
s2824 Rebuild 230 kV Line #2056 from Hornertown to Hathaway. $49,100,000
n6438 Rebuild 4.65 miles of 230 kV Line 2131 from Perquimans to South Hertford with 2-636 ACSR. $6,975,000
n6870 Wreck and rebuild 16.7 miles of existing single circuit line 2131 between M [...] R for all new and modified circuits. Add a breaker at each 230 kV terminal. $44,150,000
n6452 Rebuild 2.47 miles of 230 kV Line 238 from AE2-033 TAP to Sapony with 2-795 150C ACSR. $3,705,000
n6849 Rebuild 30.6 miles of 230 kV Line 246 from Nuco TP to Suffolk with 2-636 ACSR. $45,900,000
n7645 Add additional 500/230 kV transformer Suffolk Substation $22,000,000
n6440 Rebuild 9.97 miles of 230 kV Line 2020 from Winfall to Tanglewood DP with 2-795 150C ACSR. $14,955,000
n6178 Rebuild 4.5 miles of 230 kV Line 2003 from Harrowgate to Tyler with 2-636 ACSR. $11,250,000
n6439 Rebuild 3.3 miles of 230 kV Line 2131 from South Hertford to Winfall with 2-636 ACSR. $4,950,000

Attachments

Export to CSV Download all tables in report

Uprate Chain
Project Project Status MFO MWE MWC Disposition
AG1-437 Active 100.0 100.0 60.0 Transition Cycle 1
AG1-442 Active 135.0 35.0 35.0 Transition Cycle 1

Conclusion

The Transition Sort load flow retool results indicate that AG1-437 is not eligible for the Expedited Process per PJM Tariff Part VII, Subpart B, section 304 (A) will be reprioritized to Transition Cycle #1. See next steps for your project in the "Introduction" section above.