AG1-366 Transition Sort Retool Results -- Qualifies for Expedited Process

v1.00 released 2023-12-14 10:53

Allen 345 kV

20.0 MW Capacity / 50.0 MW Energy

Introduction

In accordance with Tariff Part VII, Subpart B, section 304, PJM performed load flow analysis (Transition Sort Retool) on all AE1 through AG1 projects that have met eligibility requirements according to Tariff, Part VII, Subpart B, section 303. The purpose of this study is to determine whether a project would be classified as eligible for the Expedited Process (Fast Lane) or if it would be reprioritized to be studied as part of Transition Cycle #1 (TC1) using the criteria from the Expedited Process Eligibility section of Tariff Part VII, section 304. This is not a System Impact Study report.

Below are the results of the study, how the study was performed, criterion used in the evaluation of the Expedited Process vs. TC1 determination, and next steps in the interconnection process for your project.

Eligible for Expedited Process:

The AG1-366 project has been determined to meet the initial screen to be eligible for the Expedited Process according to the Expedited Process Eligibility requirements in Tariff Part VII, Subpart B, section 304. Though your project initially screens as eligible for the Expedited Process, there are several conditions identified under Tariff Part VII, Subpart B, section 304 (B) that could shift your project from the Expedited Process into TC1. Please see "Expedited Process Rules" below.

Transition Sort Retool Study Process and Criteria:

In order to determine Expedited Process vs. Transition Cycle #1 classification, projects which met the Transition Eligibility requirements from Tariff Part VII, Subpart B, section 303 were studied on the base case model that was used for the original System Impact Study analysis. Both a summer peak and light load load flow analysis were performed. Projects that have cost allocation eligibility or are identified as the first to cause a system violation which requires the need for a Network Upgrade with a total estimated cost greater than $5 million will be reprioritized to Transition Cycle #1. All other projects will be eligible for the expedited procedures set forth in Tariff Part VII, Subpart B, section 304 (B).

Expedited Process Eligibility: OATT Tariff Part VII, section 304:

A project is not eligible for the expedited process if it has cost allocation eligibility or is identified as the first to cause, as determined according to Tariff, Part VI, section 217.3, for a Network Upgrade which has a total estimated cost of greater than $5,000,000. Such cost estimate will be based on Transmission Provider's most recently available data.

Not considered in the Transition Sorting: The cost of the Interconnection Facilities is not considered when determining a project's eligibility for the expedited process. Affected Systems upgrade costs are also not considered in the evaluation.

Transition Sort Retool Results Provided:

This report includes a list of:

  1. the overloaded flowgates (overloaded facilities + contingency pair) that the project contributes towards
  2. other interconnection projects that may also contribute to the overloaded facility, and
  3. the total estimated cost for any required Network Upgrades.

Important to Note: Some flowgate overloads that a New Service Request contributes to, but does not contribute enough to meet cost allocation eligibility (per Manual 14A, Attachment B.3), may be reported in this Transition Sort report. These types of flowgates do not affect the classification of the New Service Request as either Expedited Process or Transition Cycle #1 because cost allocation eligibility has not been met.

Next Steps for your project:

Refreshed Retool for Projects in Expedited Process:

After the initial sorting retool, PJM will conduct a refreshed analysis of the projects in the Expedited Process with the Transition Cycle #1 projects lifted from the study case model. After this refreshed analysis (including load flow, short circuit and stability analysis), retooled System Impact Study reports can be delivered to the Project Developers. Once the project's Facilities Study report is completed (and no conditions exist that would require the project to shift to TC1, see "Expedited Process Rules" below), the final GIA will be tendered along with the Facilities Study report.

Expedited Process Rules:

Though your project initially screens to be eligible for the Expedited Process, there are several conditions identified under Tariff Part VII, Subpart B, section 304 (B) that could shift your project into TC1 until the final GIA is tendered.

  • If stability analysis or a sag study is completed during the expedited process, and it is determined that a project has an estimated Network Upgrade cost greater than $5,000,000, the project will be removed from the expedited process and shifted to Transition Cycle #1.
  • If it is determined during the Facilities Study that the cost of a Network Upgrade is now estimated to be greater than $5,000,000, the project will be removed from the expedited process and shifted to Transition Cycle #1.
  • If a project is an uprate (project relies on the Interconnection Facilities of a prior project) whose base project does not qualify for the expedited process, the uprate also will not qualify for the expedited process, regardless of analysis results.
  • If the interconnected Transmission Owner identifies the need for a Network Upgrade due to a violation of their criteria that is in excess of $5M, the project will be removed from the expedited process and shifted to Transition Cycle #1.

General

The Interconnection Customer (IC) has proposed an uprate to a planned/existing Storage generating facility located in the AEP zone — Allen County, Indiana. This project is an increase to the Interconnection Customer's original project, which will share the same point of interconnection. The AG1-366 queue position is a 50.0 MW uprate (20.0 MW Capacity uprate) to the previous project. The total installed facilities will have a capability of 250.0 MW.

Project Information
Queue Number AG1-366
Project Name Allen 345 kV
Developer Name EDPR Northeast Allen Solar Park LLC
State Indiana
County Allen
Transmission Owner AEP
MFO 250.0 MW
MWE 50.0 MW
MWC 20.0 MW
Fuel Type Storage
Basecase Study Year 2024

Point of Interconnection

AG1-366 will interconnect on the AEP transmission system at the Allen 345 kV substation.

Summer Peak Analysis

The Queue Project was evaluated as a 50.0 MW (Capacity 20.0 MW) injection in the AEP area. Project was evaluated for compliance with applicable reliability planning criteria (PJM, NERC, NERC Regional Reliability Councils, and Transmission Owners). Potential Summer peak period network impacts are listed below:

Important to Note: Some flowgate overloads that a New Service Request contributes to, but does not contribute enough to meet cost allocation eligibility (per Manual 14A, Attachment B.3), may be reported in this Transition Sort report. These types of flowgates do not affect the classification of the New Service Request as either Expedited Process or Transition Cycle #1 because cost allocation eligibility has not been met.

Summer Peak Analysis
Area Facility Description Contingency Name Contingency Type DC|AC Initial Loading Final Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Details
AEP 05SORENS-05ROB PK 345.0 kV Ckt 1 line
243232 to 243231 ckt 1
AEP_P4_#9391_05SORENS 345_F
CONTINGENCY 'AEP_P4_#9391_05SORENS 345_F'
 OPEN BRANCH FROM BUS 243211 TO BUS 243232 CKT 1   /*05ALLEN      345.0 - 05SORENS     345.0
 OPEN BRANCH FROM BUS 243232 TO BUS 246999 CKT 3   /*05SORENS     345.0 - 05SORENS     765.0
END
Breaker AC 99.7 % 100.74 % 1203.0 B 1211.93 13.0

Light Load Analysis

The Queue Project was evaluated as a 50.0 MW (Capacity 20.0 MW) injection in the AEP area. Project was evaluated for compliance with applicable reliability planning criteria (PJM, NERC, NERC Regional Reliability Councils, and Transmission Owners). Potential light load period network impacts are listed below:

Important to Note: Some flowgate overloads that a New Service Request contributes to, but does not contribute enough to meet cost allocation eligibility (per Manual 14A, Attachment B.3), may be reported in this Transition Sort report. These types of flowgates do not affect the classification of the New Service Request as either Expedited Process or Transition Cycle #1 because cost allocation eligibility has not been met.

Light Load Analysis
Area Facility Description Contingency Name Contingency Type DC|AC Initial Loading Final Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Details
AEP 05ALLEN-05RPMONE 345.0 kV Ckt 1 line
243211 to 242933 ckt 1
AEP_P1-2_#7441_100545-A
CONTINGENCY 'AEP_P1-2_#7441_100545-A'
 OPEN BRANCH FROM BUS 242928 TO BUS 958430 CKT 1   /*05MARYSV     765.0 - AF2-137 TAP  765.0
END
Single DC 131.21 % 130.79 % 897.0 B 1173.19 10.03
AEP 05ALLEN-05RPMONE 345.0 kV Ckt 1 line
243211 to 242933 ckt 1
AEP_P1-2_#7441_100545-B
CONTINGENCY 'AEP_P1-2_#7441_100545-B'
 OPEN BRANCH FROM BUS 958430 TO BUS 246999 CKT 1   /*AF2-137 TAP  765.0 - 05SORENS     765.0
END
Single DC 131.04 % 130.37 % 897.0 B 1169.42 10.03
AEP 05ALLEN-05RPMONE 345.0 kV Ckt 1 line
243211 to 242933 ckt 1
AEP_P4_#7445_05MARYSV 765_B
CONTINGENCY 'AEP_P4_#7445_05MARYSV 765_B'
 OPEN BRANCH FROM BUS 242928 TO BUS 958430 CKT 1   /*05MARYSV     765.0 - AF2-137 TAP  765.0
 OPEN BRANCH FROM BUS 962760 TO BUS 242928 CKT 1   /*AG1-125 TAP  765.0 - 05MARYSV     765.0
END
Breaker AC 118.9 % 119.59 % 897.0 B 1072.72 9.93

System Reinforcements

The table below lists all network upgrades which resolve the identified overloaded facilities in this report.

Important to Note: Some flowgate overloads that a New Service Request contributes to, but does not contribute enough to meet cost allocation eligibility (per Manual 14A, Attachment B.3), may be reported in this Transition Sort report. These types of flowgates do not affect the classification of the New Service Request as either Expedited Process or Transition Cycle #1 because cost allocation eligibility has not been met.

Reinforcements previously identified by Transmission Owners for violations on lower voltage facilities are included in this report. Transmission Owner analysis will be updated as part of the Expedited Process and Transition Cycle 1 retools.

System Reinforcements
RTEP ID Title Total Cost
n7751 Replace 1600A Switches at Sorenson 345kV $100,000
n8196.2 In addition to N8196.1, replace an additional existing double circuit towers with steel double circuit single pole structures on the Allen - RPMone 345kV line. $458,600
n8196.1 AEP will replace two (2) existing double circuit towers with steel double circuit single pole structures on the Allen - RPMone 345kV line. $916,437
n6740 Sag Study - Allen and Rpmone 345 kV line (12.25 miles). Completed, Rate B should be 1057MVA. $49,000

Attachments

Export to CSV Download all tables in report

Uprate Chain
Project Project Status MFO MWE MWC Disposition
AF2-224 Active 100.0 100.0 42.0 Expedited Process
AG1-365 Active 200.0 100.0 60.0 Expedited Process
AG1-366 Active 250.0 50.0 20.0 Expedited Process

Conclusion

The Transition Sort load flow retool results indicate that AG1-366 is eligible for the Expedited Process per PJM Tariff Part VII, Subpart B, section 304 (A). See next steps for your project in the "Introduction" section above.