Export to CSV

AG1-178 Transition Sort Retool Results -- Reprioritized to Transition Cycle #1

v1.00 released 2023-12-14 10:50

Carson-Suffolk 500 kV

324.94 MW Capacity / 500.0 MW Energy

Introduction

In accordance with Tariff Part VII, Subpart B, section 304, PJM performed load flow analysis (Transition Sort Retool) on all AE1 through AG1 projects that have met eligibility requirements according to Tariff, Part VII, Subpart B, section 303. The purpose of this study is to determine whether a project would be classified as eligible for the Expedited Process (Fast Lane) or if it would be reprioritized to be studied as part of Transition Cycle #1 (TC1) using the criteria from the Expedited Process Eligibility section of Tariff Part VII, section 304. This is not a System Impact Study report.

Below are the results of the study, details of how the study was performed, criterion used in the evaluation of the Expedited Process vs. TC1 determination, and next steps in the interconnection process for your project.

Transition Cycle #1:

The AG1-178 project has not met the Expedited Process Eligibility requirements in Tariff Part VII, Subpart B, section 304 and will therefore be reprioritized to Transition Cycle #1. Please see "Transition Cycle #1 Rules" below.

Transition Sort Retool Study Process and Criteria:

In order to determine Expedited Process vs. Transition Cycle #1 classification, projects which met the Transition Eligibility requirements from Tariff Part VII, Subpart B, section 303 were studied on the base case model that was used for the original System Impact Study analysis. Both a summer peak and light load load flow analysis were performed. Projects that have cost allocation eligibility or are identified as the first to cause a system violation which requires the need for a Network Upgrade with a total estimated cost greater than $5 million will be reprioritized to Transition Cycle #1. All other projects will be eligible for the expedited procedures set forth in Tariff Part VII, Subpart B, section 304 (B).

Expedited Process Eligibility: OATT Tariff Part VII, section 304:

A project is not eligible for the expedited process if it has cost allocation eligibility or is identified as the first to cause, as determined according to Tariff, Part VI, section 217.3, for a Network Upgrade which has a total estimated cost of greater than $5,000,000. Such cost estimate will be based on Transmission Provider's most recently available data.

Not considered in the Transition Sorting: The cost of the Interconnection Facilities is not considered when determining a project's eligibility for the expedited process. Affected Systems upgrade costs are also not considered in the evaluation.

Transition Sort Retool Results Provided:

This report includes a list of:

  1. the overloaded flowgates (overloaded facilities + contingency pair) that the project contributes towards
  2. other interconnection projects that may also contribute to the overloaded facility, and
  3. the total estimated cost for any required Network Upgrades.

Important Notes:

Note for Uprate Projects: Per Tariff Part VII, Subpart B, section 304 (B), if a project is an uprate (project relies on the Interconnection Facilities of a prior project) whose base project does not qualify for the expedited process, the uprate also will not qualify for the expedited process, regardless of analysis results.

Notes regarding Results displayed:

  1. Some flowgate overloads that a New Service Request contributes to, but does not contribute enough to meet cost allocation eligibility (per Manual 14A, Attachment B.3), may be reported in this Transition Sort report. These types of flowgates do not affect the classification of the New Service Request as either Expedited Process or Transition Cycle #1 because cost allocation eligibility has not been met.
  2. For projects that were determined to not meet Expedited Process eligibility and are being reprioritized to Transition Cycle #1, not all reinforcements in excess of $5,000,000 may be shown in this report. This report may only display a subset of those reinforcements determined to be in excess of $5,000,000 which would classify the project as not meeting Expedited Process Eligibility. This is not a formal System Impact Study.

Next Steps for your project:

Transition Cycle #1 Rules:

Refer to Tariff Part VII, Subpart B, section 304 (C) for the Transition Cycle #1 Project Rules.

Transition Cycle #1 will start no later than one year from the Transition Start Date (July 10, 2023). Transition Cycle #1 will run simultaneously with the expedited process, however Transition Cycle #1, Phase III will not begin until all expedited process projects have been completed.

Projects that are reprioritized to Transition Cycle #1 will not need to re-apply to the Interconnection Cycle Process. Therefore, there is no Application Review Phase for Transition Cycle #1. The cycle process for Transition Cycle #1 includes three Study Phases and three Decision Points:

  1. Phase I System Impact Study and Decision Point I; and
  2. Phase II System Impact Study and Decision Point II; and
  3. Phase III System Impact Study and Decision Point III

Refer to Tariff Part VII, Subpart D, section 307 for the Transition Cycle #1 study process.

General

The Interconnection Customer (IC), has proposed a Solar generating facility located in the Dominion zone — Sussex County, Virginia. The installed facilities will have a total capability of 500.0 MW with 324.94 MW of this output being recognized by PJM as Capacity.

Project Information
Queue Number AG1-178
Project Name Carson-Suffolk 500 kV
Developer Name Cabin Point Solar, LLC
State Virginia
County Sussex
Transmission Owner Dominion
MFO 500.0 MW
MWE 500.0 MW
MWC 324.94 MW
Fuel Type Solar
Basecase Study Year 2024

Point of Interconnection

The POI for AG1-178 is a new tap on the Dominion Carson-Suffolk 500 kV Line.

Summer Peak Analysis

The Queue Project was evaluated as a 500.0 MW (Capacity 324.94 MW) injection in the Dominion area. Project was evaluated for compliance with applicable reliability planning criteria (PJM, NERC, NERC Regional Reliability Councils, and Transmission Owners). Potential Summer peak period network impacts are listed below:

Important to Note:

Note for Uprate Projects: Per Tariff Part VII, Subpart B, section 304 (B), if a project is an uprate (project relies on the Interconnection Facilities of a prior project) whose base project does not qualify for the expedited process, the uprate also will not qualify for the expedited process, regardless of analysis results.

Notes regarding Results displayed:

  1. Some flowgate overloads that a New Service Request contributes to, but does not contribute enough to meet cost allocation eligibility (per Manual 14A, Attachment B.3), may be reported in this Transition Sort report. These types of flowgates do not affect the classification of the New Service Request as either Expedited Process or Transition Cycle #1 because cost allocation eligibility has not been met.
  2. For projects that were determined to not meet Expedited Process eligibility and are being reprioritized to Transition Cycle #1, not all reinforcements in excess of $5,000,000 may be shown in this report. This report may only display a subset of those reinforcements determined to be in excess of $5,000,000 which would classify the project as not meeting Expedited Process Eligibility. This is not a formal System Impact Study.
Summer Peak Analysis
Area Facility Description Contingency Name Contingency Type DC|AC Initial Loading Final Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Details
DVP 8ELMONT-8LADYSMITH 500.0 kV Ckt 1 line
314908 to 314911 ckt 1
DVP_P1-2: LN 576
CONTINGENCY 'DVP_P1-2: LN 576'
 OPEN BRANCH FROM BUS 314914 TO BUS 314918 CKT 1                /*8MDLTHAN     500.0 - 8NO ANNA     500.0
 SET POSTCONTRATING 3118 BRANCH FROM BUS 314902 TO BUS 314914 CKT 1 /*8CARSON      500.0 - 8MDLTHAN     500.0
 SET PRECONTRATING 2858 BRANCH FROM BUS 314902 TO BUS 314914 CKT 1 /*8CARSON      500.0 - 8MDLTHAN     500.0
END
Single AC 157.74 % 160.47 % 2442.12 B 3918.75 95.92
DVP 6CARSON-6CHRL249 230.0 kV Ckt 1 line
314282 to 314285 ckt 1
DVP_P1-2: LN 563
CONTINGENCY 'DVP_P1-2: LN 563'
 OPEN BRANCH FROM BUS 314902 TO BUS 314914 CKT 1                /*8CARSON      500.0 - 8MDLTHAN     500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TAP  500.0
 SET PRECONTRATING 2650 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TAP  500.0
END
Single AC 144.97 % 149.03 % 559.3 B 833.55 24.4
DVP 6CHRL249-6LOCKS 230.0 kV Ckt 1 line
314285 to 314316 ckt 1
DVP_P1-2: LN 563
CONTINGENCY 'DVP_P1-2: LN 563'
 OPEN BRANCH FROM BUS 314902 TO BUS 314914 CKT 1                /*8CARSON      500.0 - 8MDLTHAN     500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TAP  500.0
 SET PRECONTRATING 2650 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TAP  500.0
END
Single AC 141.51 % 145.56 % 559.3 B 814.12 24.4
DVP 6CARSON-6CHRL249 230.0 kV Ckt 1 line
314282 to 314285 ckt 1
DVP_P1-2: LN 2002
CONTINGENCY 'DVP_P1-2: LN 2002'
 OPEN BRANCH FROM BUS 314282 TO BUS 314331 CKT 1   /*6CARSON      230.0 - 6POE         230.0
 OPEN BRANCH FROM BUS 314329 TO BUS 314331 CKT 1   /*3POE         115.0 - 6POE         230.0
END
Single AC 135.37 % 138.71 % 559.3 B 775.83 18.64
DVP 6CHRL249-6LOCKS 230.0 kV Ckt 1 line
314285 to 314316 ckt 1
DVP_P1-2: LN 2002
CONTINGENCY 'DVP_P1-2: LN 2002'
 OPEN BRANCH FROM BUS 314282 TO BUS 314331 CKT 1   /*6CARSON      230.0 - 6POE         230.0
 OPEN BRANCH FROM BUS 314329 TO BUS 314331 CKT 1   /*3POE         115.0 - 6POE         230.0
END
Single AC 131.95 % 135.3 % 559.3 B 756.76 18.64
DVP 8ELMONT-8LADYSMITH 500.0 kV Ckt 1 line
314908 to 314911 ckt 1
DVP_P1-2: LN 563
CONTINGENCY 'DVP_P1-2: LN 563'
 OPEN BRANCH FROM BUS 314902 TO BUS 314914 CKT 1                /*8CARSON      500.0 - 8MDLTHAN     500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TAP  500.0
 SET PRECONTRATING 2650 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TAP  500.0
END
Single AC 138.51 % 140.56 % 2442.12 B 3432.57 81.81
DVP 6CHESTF B-6BASIN 230.0 kV Ckt 1 line
314287 to 314276 ckt 1
DVP_P1-2: LN 563
CONTINGENCY 'DVP_P1-2: LN 563'
 OPEN BRANCH FROM BUS 314902 TO BUS 314914 CKT 1                /*8CARSON      500.0 - 8MDLTHAN     500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TAP  500.0
 SET PRECONTRATING 2650 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TAP  500.0
END
Single AC 138.35 % 140.18 % 663.64 B 930.27 21.18
DVP 6LOCKS-6HARR205 230.0 kV Ckt 1 line
314316 to 314301 ckt 1
DVP_P1-2: LN 563
CONTINGENCY 'DVP_P1-2: LN 563'
 OPEN BRANCH FROM BUS 314902 TO BUS 314914 CKT 1                /*8CARSON      500.0 - 8MDLTHAN     500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TAP  500.0
 SET PRECONTRATING 2650 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TAP  500.0
END
Single AC 124.14 % 128.54 % 441.8 B 567.88 19.5
DVP 8CARSON-6CARSON 500.0/230.0 kV Ckt 1 transformer
314902 to 314282 ckt 1
DVP_P1-2: LN 563
CONTINGENCY 'DVP_P1-2: LN 563'
 OPEN BRANCH FROM BUS 314902 TO BUS 314914 CKT 1                /*8CARSON      500.0 - 8MDLTHAN     500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TAP  500.0
 SET PRECONTRATING 2650 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TAP  500.0
END
Single AC 127.36 % 133.54 % 903.9 B 1207.05 53.14
DVP 6HARR205-6TYLER 230.0 kV Ckt 1 line
314301 to 314346 ckt 1
DVP_P1-2: LN 563
CONTINGENCY 'DVP_P1-2: LN 563'
 OPEN BRANCH FROM BUS 314902 TO BUS 314914 CKT 1                /*8CARSON      500.0 - 8MDLTHAN     500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TAP  500.0
 SET PRECONTRATING 2650 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TAP  500.0
END
Single AC 118.48 % 122.8 % 441.8 B 542.52 19.5
DVP 6POE-6HARROWG 230.0 kV Ckt 1 line
314331 to 314299 ckt 1
DVP_P1-2: LN 563
CONTINGENCY 'DVP_P1-2: LN 563'
 OPEN BRANCH FROM BUS 314902 TO BUS 314914 CKT 1                /*8CARSON      500.0 - 8MDLTHAN     500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TAP  500.0
 SET PRECONTRATING 2650 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TAP  500.0
END
Single AC 116.33 % 120.37 % 441.8 B 531.8 18.91
DVP 6HARROWG-6TYLER1 230.0 kV Ckt 1 line
314299 to 314263 ckt 1
DVP_P1-2: LN 563
CONTINGENCY 'DVP_P1-2: LN 563'
 OPEN BRANCH FROM BUS 314902 TO BUS 314914 CKT 1                /*8CARSON      500.0 - 8MDLTHAN     500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TAP  500.0
 SET PRECONTRATING 2650 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TAP  500.0
END
Single AC 116.29 % 120.33 % 441.8 B 531.62 18.91
DVP 8MDLTHAN-6MDLTHAN 500.0/230.0 kV Ckt 1 transformer
314914 to 314322 ckt 1
DVP_P1-2: LN 576
CONTINGENCY 'DVP_P1-2: LN 576'
 OPEN BRANCH FROM BUS 314914 TO BUS 314918 CKT 1                /*8MDLTHAN     500.0 - 8NO ANNA     500.0
 SET POSTCONTRATING 3118 BRANCH FROM BUS 314902 TO BUS 314914 CKT 1 /*8CARSON      500.0 - 8MDLTHAN     500.0
 SET PRECONTRATING 2858 BRANCH FROM BUS 314902 TO BUS 314914 CKT 1 /*8CARSON      500.0 - 8MDLTHAN     500.0
END
Single AC 114.92 % 118.97 % 1058.16 B 1258.87 45.19
DVP 8MDLTHAN-8NO ANNA 500.0 kV Ckt 1 line
314914 to 314918 ckt 1
DVP_P1-2: LN 574
CONTINGENCY 'DVP_P1-2: LN 574'
 OPEN BRANCH FROM BUS 314908 TO BUS 314911 CKT 1                /*8ELMONT      500.0 - 8LADYSMITH   500.0
 SET POSTCONTRATING 2598 BRANCH FROM BUS 314903 TO BUS 314908 CKT 1 /*8CHCKAHM     500.0 - 8ELMONT      500.0
 SET POSTCONTRATING 2831 BRANCH FROM BUS 314905 TO BUS 314911 CKT 1 /*8CHANCE      500.0 - 8LADYSMITH   500.0
 SET PRECONTRATING 2538 BRANCH FROM BUS 314903 TO BUS 314908 CKT 1 /*8CHCKAHM     500.0 - 8ELMONT      500.0
 SET PRECONTRATING 2552 BRANCH FROM BUS 314905 TO BUS 314911 CKT 1 /*8CHANCE      500.0 - 8LADYSMITH   500.0
END
Single AC 112.9 % 115.28 % 3220.44 B 3712.68 104.2
DVP 8SPOTSYL-8MORRSVL 500.0 kV Ckt 1 line
314934 to 314916 ckt 1
DVP_P1-2: LN 552
CONTINGENCY 'DVP_P1-2: LN 552'
 OPEN BRANCH FROM BUS 314135 TO BUS 314905 CKT 1                /*3CHANCE      115.0 - 8CHANCE      500.0
 OPEN BRANCH FROM BUS 314900 TO BUS 314905 CKT 1                /*8BRISTER     500.0 - 8CHANCE      500.0
 SET POSTCONTRATING 2078 BRANCH FROM BUS 314900 TO BUS 314919 CKT 1 /*8BRISTER     500.0 - 8OX          500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314900 TO BUS 314916 CKT 1 /*8BRISTER     500.0 - 8MORRSVL     500.0
 SET PRECONTRATING 1905 BRANCH FROM BUS 314900 TO BUS 314919 CKT 1 /*8BRISTER     500.0 - 8OX          500.0
 SET PRECONTRATING 2650 BRANCH FROM BUS 314900 TO BUS 314916 CKT 1 /*8BRISTER     500.0 - 8MORRSVL     500.0
END
Single AC 113.06 % 114.92 % 3220.44 B 3701.03 69.42
DVP 8SPOTSYL-8MORRSVL 500.0 kV Ckt 1 line
314934 to 314916 ckt 1
DVP_P1-2: LN 581
CONTINGENCY 'DVP_P1-2: LN 581'
 OPEN BRANCH FROM BUS 314135 TO BUS 314905 CKT 2   /*3CHANCE      115.0 - 8CHANCE      500.0
 OPEN BRANCH FROM BUS 314905 TO BUS 314911 CKT 1   /*8CHANCE      500.0 - 8LADYSMITH   500.0
END
Single AC 112.9 % 114.8 % 3220.44 B 3697.16 68.4
DVP 8NO ANNA-8SPOTSYL 500.0 kV Ckt 1 line
314918 to 314934 ckt 1
DVP_P1-2: LN 575-B
CONTINGENCY 'DVP_P1-2: LN 575-B'
 OPEN BRANCH FROM BUS 962840 TO BUS 314918 CKT 1   /*AG1-133 TAP  500.0 - 8NO ANNA     500.0
END
Single AC 113.92 % 115.29 % 3220.44 B 3712.75 68.16
DVP 6CARSON-6POE 230.0 kV Ckt 1 line
314282 to 314331 ckt 1
DVP_P1-2: LN 249
CONTINGENCY 'DVP_P1-2: LN 249'
 OPEN BRANCH FROM BUS 314282 TO BUS 314285 CKT 1   /*6CARSON      230.0 - 6CHRL249     230.0
 OPEN BRANCH FROM BUS 314285 TO BUS 314316 CKT 1   /*6CHRL249     230.0 - 6LOCKS       230.0
 OPEN BRANCH FROM BUS 314314 TO BUS 314316 CKT 2   /*3LOCKS       115.0 - 6LOCKS       230.0
 OPEN BUS 314285                                   /*6CHRL249     230.0
END
Single AC 103.78 % 106.37 % 678.68 B 721.92 17.29
DVP AG1-133 TAP-8LADYSMITH 500.0 kV Ckt 1 line
962840 to 314911 ckt 1
DVP_P1-2: LN 594
CONTINGENCY 'DVP_P1-2: LN 594'
 OPEN BRANCH FROM BUS 314916 TO BUS 314934 CKT 1                /*8MORRSVL     500.0 - 8SPOTSYL     500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314900 TO BUS 314916 CKT 1 /*8BRISTER     500.0 - 8MORRSVL     500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314918 TO BUS 314934 CKT 1 /*8NO ANNA     500.0 - 8SPOTSYL     500.0
 SET PRECONTRATING 2650 BRANCH FROM BUS 314900 TO BUS 314916 CKT 1 /*8BRISTER     500.0 - 8MORRSVL     500.0
 SET PRECONTRATING 2650 BRANCH FROM BUS 314918 TO BUS 314934 CKT 1 /*8NO ANNA     500.0 - 8SPOTSYL     500.0
END
Single AC 109.04 % 111.1 % 3218.56 B 3575.79 61.19
DVP 8NO ANNA-AG1-133 TAP 500.0 kV Ckt 1 line
314918 to 962840 ckt 1
DVP_P1-2: LN 573
CONTINGENCY 'DVP_P1-2: LN 573'
 OPEN BRANCH FROM BUS 314918 TO BUS 314934 CKT 1                /*8NO ANNA     500.0 - 8SPOTSYL     500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314916 TO BUS 314934 CKT 1 /*8MORRSVL     500.0 - 8SPOTSYL     500.0
 SET PRECONTRATING 2650 BRANCH FROM BUS 314916 TO BUS 314934 CKT 1 /*8MORRSVL     500.0 - 8SPOTSYL     500.0
END
Single AC 111.77 % 113.35 % 3218.56 B 3648.17 64.26
DVP 8CHCKAHM-8ELMONT 500.0 kV Ckt 1 line
314903 to 314908 ckt 1
DVP_P1-2: LN 563
CONTINGENCY 'DVP_P1-2: LN 563'
 OPEN BRANCH FROM BUS 314902 TO BUS 314914 CKT 1                /*8CARSON      500.0 - 8MDLTHAN     500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TAP  500.0
 SET PRECONTRATING 2650 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TAP  500.0
END
Single AC 102.28 % 106.0 % 2442.12 B 2588.67 90.06
DVP 8LADYSMITH-8POSSUM 500.0 kV Ckt 1 line
314911 to 314922 ckt 1
DVP_P1-2: LN 581
CONTINGENCY 'DVP_P1-2: LN 581'
 OPEN BRANCH FROM BUS 314135 TO BUS 314905 CKT 2   /*3CHANCE      115.0 - 8CHANCE      500.0
 OPEN BRANCH FROM BUS 314905 TO BUS 314911 CKT 1   /*8CHANCE      500.0 - 8LADYSMITH   500.0
END
Single AC 115.35 % 116.14 % 2442.12 B 2836.38 51.82
DVP 8NO ANNA-8SPOTSYL 500.0 kV Ckt 1 line
314918 to 314934 ckt 1
DVP_P1-2: LN 581
CONTINGENCY 'DVP_P1-2: LN 581'
 OPEN BRANCH FROM BUS 314135 TO BUS 314905 CKT 2   /*3CHANCE      115.0 - 8CHANCE      500.0
 OPEN BRANCH FROM BUS 314905 TO BUS 314911 CKT 1   /*8CHANCE      500.0 - 8LADYSMITH   500.0
END
Single AC 109.62 % 111.59 % 3220.44 B 3593.82 70.9
DVP 8NO ANNA-AG1-133 TAP 500.0 kV Ckt 1 line
314918 to 962840 ckt 1
DVP_P1-2: LN 594
CONTINGENCY 'DVP_P1-2: LN 594'
 OPEN BRANCH FROM BUS 314916 TO BUS 314934 CKT 1                /*8MORRSVL     500.0 - 8SPOTSYL     500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314900 TO BUS 314916 CKT 1 /*8BRISTER     500.0 - 8MORRSVL     500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314918 TO BUS 314934 CKT 1 /*8NO ANNA     500.0 - 8SPOTSYL     500.0
 SET PRECONTRATING 2650 BRANCH FROM BUS 314900 TO BUS 314916 CKT 1 /*8BRISTER     500.0 - 8MORRSVL     500.0
 SET PRECONTRATING 2650 BRANCH FROM BUS 314918 TO BUS 314934 CKT 1 /*8NO ANNA     500.0 - 8SPOTSYL     500.0
END
Single AC 107.14 % 109.23 % 3218.56 B 3515.67 61.19
DVP 8LADYSMITH-8POSSUM 500.0 kV Ckt 1 line
314911 to 314922 ckt 1
DVP_P1-2: LN 594
CONTINGENCY 'DVP_P1-2: LN 594'
 OPEN BRANCH FROM BUS 314916 TO BUS 314934 CKT 1                /*8MORRSVL     500.0 - 8SPOTSYL     500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314900 TO BUS 314916 CKT 1 /*8BRISTER     500.0 - 8MORRSVL     500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314918 TO BUS 314934 CKT 1 /*8NO ANNA     500.0 - 8SPOTSYL     500.0
 SET PRECONTRATING 2650 BRANCH FROM BUS 314900 TO BUS 314916 CKT 1 /*8BRISTER     500.0 - 8MORRSVL     500.0
 SET PRECONTRATING 2650 BRANCH FROM BUS 314918 TO BUS 314934 CKT 1 /*8NO ANNA     500.0 - 8SPOTSYL     500.0
END
Single AC 113.08 % 114.28 % 2442.12 B 2790.83 50.69
DVP 8SURRY-8CHCKAHM 500.0 kV Ckt 1 line
314924 to 314903 ckt 1
DVP_P1-2: LN 563
CONTINGENCY 'DVP_P1-2: LN 563'
 OPEN BRANCH FROM BUS 314902 TO BUS 314914 CKT 1                /*8CARSON      500.0 - 8MDLTHAN     500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TAP  500.0
 SET PRECONTRATING 2650 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TAP  500.0
END
Single AC 101.67 % 104.77 % 2442.12 B 2558.58 85.77
DVP 6WALR209-6LIGH209 230.0 kV Ckt 1 line
314415 to 314391 ckt 1
DVP_P1-2: LN 567
CONTINGENCY 'DVP_P1-2: LN 567'
 OPEN BRANCH FROM BUS 314903 TO BUS 314924 CKT 1                /*8CHCKAHM     500.0 - 8SURRY       500.0
 SET POSTCONTRATING 2598 BRANCH FROM BUS 314903 TO BUS 314908 CKT 1 /*8CHCKAHM     500.0 - 8ELMONT      500.0
 SET PRECONTRATING 2538 BRANCH FROM BUS 314903 TO BUS 314908 CKT 1 /*8CHCKAHM     500.0 - 8ELMONT      500.0
END
Single AC 102.7 % 106.26 % 441.8 B 469.44 18.41
DVP AG1-133 TAP-8LADYSMITH 500.0 kV Ckt 1 line
962840 to 314911 ckt 1
DVP_P1-2: LN 573
CONTINGENCY 'DVP_P1-2: LN 573'
 OPEN BRANCH FROM BUS 314918 TO BUS 314934 CKT 1                /*8NO ANNA     500.0 - 8SPOTSYL     500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314916 TO BUS 314934 CKT 1 /*8MORRSVL     500.0 - 8SPOTSYL     500.0
 SET PRECONTRATING 2650 BRANCH FROM BUS 314916 TO BUS 314934 CKT 1 /*8MORRSVL     500.0 - 8SPOTSYL     500.0
END
Single AC 111.3 % 111.95 % 3218.56 B 3603.21 64.26
DVP 8CHCKAHM-8ELMONT 500.0 kV Ckt 1 line
314903 to 314908 ckt 1
DVP_P1-2: LN 576
CONTINGENCY 'DVP_P1-2: LN 576'
 OPEN BRANCH FROM BUS 314914 TO BUS 314918 CKT 1                /*8MDLTHAN     500.0 - 8NO ANNA     500.0
 SET POSTCONTRATING 3118 BRANCH FROM BUS 314902 TO BUS 314914 CKT 1 /*8CARSON      500.0 - 8MDLTHAN     500.0
 SET PRECONTRATING 2858 BRANCH FROM BUS 314902 TO BUS 314914 CKT 1 /*8CARSON      500.0 - 8MDLTHAN     500.0
END
Single AC 101.43 % 103.82 % 2442.12 B 2535.36 86.02
DVP 8CARSON-8MDLTHAN 500.0 kV Ckt 1 line
314902 to 314914 ckt 1
DVP_P1-2: LN 567
CONTINGENCY 'DVP_P1-2: LN 567'
 OPEN BRANCH FROM BUS 314903 TO BUS 314924 CKT 1                /*8CHCKAHM     500.0 - 8SURRY       500.0
 SET POSTCONTRATING 2598 BRANCH FROM BUS 314903 TO BUS 314908 CKT 1 /*8CHCKAHM     500.0 - 8ELMONT      500.0
 SET PRECONTRATING 2538 BRANCH FROM BUS 314903 TO BUS 314908 CKT 1 /*8CHCKAHM     500.0 - 8ELMONT      500.0
END
Single AC 96.54 % 100.12 % 3220.44 B 3224.24 115.0
DVP 8CARSON-8MDLTHAN 500.0 kV Ckt 1 line
314902 to 314914 ckt 1
DVP_P1-2: LN 574
CONTINGENCY 'DVP_P1-2: LN 574'
 OPEN BRANCH FROM BUS 314908 TO BUS 314911 CKT 1                /*8ELMONT      500.0 - 8LADYSMITH   500.0
 SET POSTCONTRATING 2598 BRANCH FROM BUS 314903 TO BUS 314908 CKT 1 /*8CHCKAHM     500.0 - 8ELMONT      500.0
 SET POSTCONTRATING 2831 BRANCH FROM BUS 314905 TO BUS 314911 CKT 1 /*8CHANCE      500.0 - 8LADYSMITH   500.0
 SET PRECONTRATING 2538 BRANCH FROM BUS 314903 TO BUS 314908 CKT 1 /*8CHCKAHM     500.0 - 8ELMONT      500.0
 SET PRECONTRATING 2552 BRANCH FROM BUS 314905 TO BUS 314911 CKT 1 /*8CHANCE      500.0 - 8LADYSMITH   500.0
END
Single AC 99.37 % 102.36 % 3220.44 B 3296.35 110.08
DVP 8MDLTHAN-8NO ANNA 500.0 kV Ckt 1 line
314914 to 314918 ckt 1
DVP_P1-2: LN 557
CONTINGENCY 'DVP_P1-2: LN 557'
 OPEN BRANCH FROM BUS 314903 TO BUS 314908 CKT 1   /*8CHCKAHM     500.0 - 8ELMONT      500.0
END
Single AC 97.63 % 100.35 % 3220.44 B 3231.78 100.91
DVP 8CARSON-8MDLTHAN 500.0 kV Ckt 1 line
314902 to 314914 ckt 1
DVP_P1-2: LN 557
CONTINGENCY 'DVP_P1-2: LN 557'
 OPEN BRANCH FROM BUS 314903 TO BUS 314908 CKT 1   /*8CHCKAHM     500.0 - 8ELMONT      500.0
END
Single AC 97.05 % 100.35 % 3220.44 B 3231.74 114.33
DVP 6CARSON-6CHRL249 230.0 kV Ckt 1 line
314282 to 314285 ckt 1
DVP_P4-2: 562T563
CONTINGENCY 'DVP_P4-2: 562T563'
 OPEN BRANCH FROM BUS 314902 TO BUS 314914 CKT 1   /*8CARSON      500.0 - 8MDLTHAN     500.0
 OPEN BRANCH FROM BUS 314902 TO BUS 940640 CKT 1   /*8CARSON      500.0 - AE2-051 TAP  500.0
END
Breaker AC 164.16 % 167.94 % 684.0 C 1148.68 31.21
DVP 6CHRL249-6LOCKS 230.0 kV Ckt 1 line
314285 to 314316 ckt 1
DVP_P4-2: 562T563
CONTINGENCY 'DVP_P4-2: 562T563'
 OPEN BRANCH FROM BUS 314902 TO BUS 314914 CKT 1   /*8CARSON      500.0 - 8MDLTHAN     500.0
 OPEN BRANCH FROM BUS 314902 TO BUS 940640 CKT 1   /*8CARSON      500.0 - AE2-051 TAP  500.0
END
Breaker AC 161.34 % 165.12 % 684.0 C 1129.41 31.21
DVP 8CARSON-6CARSON 500.0/230.0 kV Ckt 1 transformer
314902 to 314282 ckt 1
DVP_P4-2: 562T563
CONTINGENCY 'DVP_P4-2: 562T563'
 OPEN BRANCH FROM BUS 314902 TO BUS 314914 CKT 1   /*8CARSON      500.0 - 8MDLTHAN     500.0
 OPEN BRANCH FROM BUS 314902 TO BUS 940640 CKT 1   /*8CARSON      500.0 - AE2-051 TAP  500.0
END
Breaker AC 154.57 % 160.76 % 1039.7 C 1671.44 68.22
DVP 6LOCKS-6HARR205 230.0 kV Ckt 1 line
314316 to 314301 ckt 1
DVP_P4-2: 562T563
CONTINGENCY 'DVP_P4-2: 562T563'
 OPEN BRANCH FROM BUS 314902 TO BUS 314914 CKT 1   /*8CARSON      500.0 - 8MDLTHAN     500.0
 OPEN BRANCH FROM BUS 314902 TO BUS 940640 CKT 1   /*8CARSON      500.0 - AE2-051 TAP  500.0
END
Breaker AC 145.42 % 149.08 % 541.0 C 806.54 24.66
DVP 6HARR205-6TYLER 230.0 kV Ckt 1 line
314301 to 314346 ckt 1
DVP_P4-2: 562T563
CONTINGENCY 'DVP_P4-2: 562T563'
 OPEN BRANCH FROM BUS 314902 TO BUS 314914 CKT 1   /*8CARSON      500.0 - 8MDLTHAN     500.0
 OPEN BRANCH FROM BUS 314902 TO BUS 940640 CKT 1   /*8CARSON      500.0 - AE2-051 TAP  500.0
END
Breaker AC 138.77 % 142.51 % 541.0 C 770.98 24.66
DVP 8ELMONT-8LADYSMITH 500.0 kV Ckt 1 line
314908 to 314911 ckt 1
DVP_P4-2: 57602
CONTINGENCY 'DVP_P4-2: 57602'
 OPEN BRANCH FROM BUS 314232 TO BUS 314918 CKT 1   /*6NO ANNA     230.0 - 8NO ANNA     500.0
 OPEN BRANCH FROM BUS 314914 TO BUS 314918 CKT 1   /*8MDLTHAN     500.0 - 8NO ANNA     500.0
END
Breaker AC 155.89 % 156.09 % 3351.0 C 5230.74 95.91
DVP 8ELMONT-8LADYSMITH 500.0 kV Ckt 1 line
314908 to 314911 ckt 1
DVP_P4-2: WT576
CONTINGENCY 'DVP_P4-2: WT576'
 OPEN BRANCH FROM BUS 314232 TO BUS 314918 CKT 2   /*6NO ANNA     230.0 - 8NO ANNA     500.0
 OPEN BRANCH FROM BUS 314914 TO BUS 314918 CKT 1   /*8MDLTHAN     500.0 - 8NO ANNA     500.0
END
Breaker AC 155.89 % 156.09 % 3351.0 C 5230.71 95.91
DVP 6POE-6HARROWG 230.0 kV Ckt 1 line
314331 to 314299 ckt 1
DVP_P4-2: 562T563
CONTINGENCY 'DVP_P4-2: 562T563'
 OPEN BRANCH FROM BUS 314902 TO BUS 314914 CKT 1   /*8CARSON      500.0 - 8MDLTHAN     500.0
 OPEN BRANCH FROM BUS 314902 TO BUS 940640 CKT 1   /*8CARSON      500.0 - AE2-051 TAP  500.0
END
Breaker AC 131.49 % 135.17 % 541.0 C 731.28 23.42
DVP 6HARROWG-6TYLER1 230.0 kV Ckt 1 line
314299 to 314263 ckt 1
DVP_P4-2: 562T563
CONTINGENCY 'DVP_P4-2: 562T563'
 OPEN BRANCH FROM BUS 314902 TO BUS 314914 CKT 1   /*8CARSON      500.0 - 8MDLTHAN     500.0
 OPEN BRANCH FROM BUS 314902 TO BUS 940640 CKT 1   /*8CARSON      500.0 - AE2-051 TAP  500.0
END
Breaker AC 131.48 % 135.16 % 541.0 C 731.22 23.42
DVP 8SURRY-8CHCKAHM 500.0 kV Ckt 1 line
314924 to 314903 ckt 1
DVP_P4-2: 56372
CONTINGENCY 'DVP_P4-2: 56372'
 OPEN BRANCH FROM BUS 314282 TO BUS 314902 CKT 1   /*6CARSON      230.0 - 8CARSON      500.0
 OPEN BRANCH FROM BUS 314902 TO BUS 314914 CKT 1   /*8CARSON      500.0 - 8MDLTHAN     500.0
END
Breaker AC 135.21 % 136.63 % 3144.0 C 4295.68 98.13
DVP 8CARSON-8MDLTHAN 500.0 kV Ckt 1 line
314902 to 314914 ckt 1
DVP_P4-2: 557T574
CONTINGENCY 'DVP_P4-2: 557T574'
 OPEN BRANCH FROM BUS 314214 TO BUS 314903 CKT 1   /*6CHCKAHM     230.0 - 8CHCKAHM     500.0
 OPEN BRANCH FROM BUS 314903 TO BUS 314908 CKT 1   /*8CHCKAHM     500.0 - 8ELMONT      500.0
 OPEN BRANCH FROM BUS 314908 TO BUS 314911 CKT 1   /*8ELMONT      500.0 - 8LADYSMITH   500.0
END
Breaker AC 133.67 % 135.29 % 3940.0 C 5330.31 122.97
DVP 8CARSON-8MDLTHAN 500.0 kV Ckt 1 line
314902 to 314914 ckt 1
DVP_P4-2: H2T557
CONTINGENCY 'DVP_P4-2: H2T557'
 OPEN BRANCH FROM BUS 314214 TO BUS 314903 CKT 1   /*6CHCKAHM     230.0 - 8CHCKAHM     500.0
 OPEN BRANCH FROM BUS 314218 TO BUS 314908 CKT 2   /*6ELMONT      230.0 - 8ELMONT      500.0
 OPEN BRANCH FROM BUS 314903 TO BUS 314908 CKT 1   /*8CHCKAHM     500.0 - 8ELMONT      500.0
END
Breaker AC 126.26 % 127.83 % 3940.0 C 5036.42 120.81
DVP 8CARSON-8MDLTHAN 500.0 kV Ckt 1 line
314902 to 314914 ckt 1
DVP_P4-2: 557T567
CONTINGENCY 'DVP_P4-2: 557T567'
 OPEN BRANCH FROM BUS 314214 TO BUS 314903 CKT 1   /*6CHCKAHM     230.0 - 8CHCKAHM     500.0
 OPEN BRANCH FROM BUS 314903 TO BUS 314908 CKT 1   /*8CHCKAHM     500.0 - 8ELMONT      500.0
 OPEN BRANCH FROM BUS 314903 TO BUS 314924 CKT 1   /*8CHCKAHM     500.0 - 8SURRY       500.0
END
Breaker AC 124.06 % 125.7 % 3940.0 C 4952.46 118.8
DVP 8CARSON-8MDLTHAN 500.0 kV Ckt 1 line
314902 to 314914 ckt 1
DVP_P4-5: L122
CONTINGENCY 'DVP_P4-5: L122'
 OPEN BRANCH FROM BUS 314214 TO BUS 314903 CKT 1   /*6CHCKAHM     230.0 - 8CHCKAHM     500.0
 OPEN BRANCH FROM BUS 314903 TO BUS 314908 CKT 1   /*8CHCKAHM     500.0 - 8ELMONT      500.0
END
Breaker AC 123.96 % 125.55 % 3940.0 C 4946.59 118.8
DVP 8SURRY-8CHCKAHM 500.0 kV Ckt 1 line
314924 to 314903 ckt 1
DVP_P4-2: 563T576
CONTINGENCY 'DVP_P4-2: 563T576'
 OPEN BRANCH FROM BUS 314902 TO BUS 314914 CKT 1   /*8CARSON      500.0 - 8MDLTHAN     500.0
 OPEN BRANCH FROM BUS 314914 TO BUS 314918 CKT 1   /*8MDLTHAN     500.0 - 8NO ANNA     500.0
END
Breaker AC 125.58 % 126.24 % 3144.0 C 3968.86 87.65
DVP 8MDLTHAN-8NO ANNA 500.0 kV Ckt 1 line
314914 to 314918 ckt 1
DVP_P4-2: 557T574
CONTINGENCY 'DVP_P4-2: 557T574'
 OPEN BRANCH FROM BUS 314214 TO BUS 314903 CKT 1   /*6CHCKAHM     230.0 - 8CHCKAHM     500.0
 OPEN BRANCH FROM BUS 314903 TO BUS 314908 CKT 1   /*8CHCKAHM     500.0 - 8ELMONT      500.0
 OPEN BRANCH FROM BUS 314908 TO BUS 314911 CKT 1   /*8ELMONT      500.0 - 8LADYSMITH   500.0
END
Breaker AC 125.23 % 125.97 % 3940.0 C 4963.22 111.72
DVP 8SPOTSYL-8MORRSVL 500.0 kV Ckt 1 line
314934 to 314916 ckt 1
DVP_P4-2: 568T575
CONTINGENCY 'DVP_P4-2: 568T575'
 OPEN BRANCH FROM BUS 314911 TO BUS 314922 CKT 1   /*8LADYSMITH   500.0 - 8POSSUM      500.0
 OPEN BRANCH FROM BUS 314911 TO BUS 962840 CKT 1   /*8LADYSMITH   500.0 - AG1-133 TAP  500.0
END
Breaker AC 122.29 % 122.9 % 3940.0 C 4842.42 69.19
DVP 6CARSON-6POE 230.0 kV Ckt 1 line
314282 to 314331 ckt 1
DVP_P4-2: 562T563
CONTINGENCY 'DVP_P4-2: 562T563'
 OPEN BRANCH FROM BUS 314902 TO BUS 314914 CKT 1   /*8CARSON      500.0 - 8MDLTHAN     500.0
 OPEN BRANCH FROM BUS 314902 TO BUS 940640 CKT 1   /*8CARSON      500.0 - AE2-051 TAP  500.0
END
Breaker AC 109.0 % 111.63 % 830.0 C 926.53 26.97
DVP 8SPOTSYL-8MORRSVL 500.0 kV Ckt 1 line
314934 to 314916 ckt 1
DVP_P4-2: H1T575
CONTINGENCY 'DVP_P4-2: H1T575'
 OPEN BRANCH FROM BUS 314196 TO BUS 314911 CKT 1   /*6LADYSMITH   230.0 - 8LADYSMITH   500.0
 OPEN BRANCH FROM BUS 314911 TO BUS 962840 CKT 1   /*8LADYSMITH   500.0 - AG1-133 TAP  500.0
END
Breaker AC 116.77 % 117.34 % 3940.0 C 4623.31 66.23
DVP 8NO ANNA-8SPOTSYL 500.0 kV Ckt 1 line
314918 to 314934 ckt 1
DVP_P4-2: 568T575
CONTINGENCY 'DVP_P4-2: 568T575'
 OPEN BRANCH FROM BUS 314911 TO BUS 314922 CKT 1   /*8LADYSMITH   500.0 - 8POSSUM      500.0
 OPEN BRANCH FROM BUS 314911 TO BUS 962840 CKT 1   /*8LADYSMITH   500.0 - AG1-133 TAP  500.0
END
Breaker AC 116.34 % 116.95 % 3940.0 C 4607.67 70.81
DVP 8CHCKAHM-8ELMONT 500.0 kV Ckt 1 line
314903 to 314908 ckt 1
DVP_P4-2: 56372
CONTINGENCY 'DVP_P4-2: 56372'
 OPEN BRANCH FROM BUS 314282 TO BUS 314902 CKT 1   /*6CARSON      230.0 - 8CARSON      500.0
 OPEN BRANCH FROM BUS 314902 TO BUS 314914 CKT 1   /*8CARSON      500.0 - 8MDLTHAN     500.0
END
Breaker AC 113.71 % 114.12 % 3637.0 C 4150.69 97.7
DVP AG1-133 TAP-8LADYSMITH 500.0 kV Ckt 1 line
962840 to 314911 ckt 1
DVP_P4-2: 515T573
CONTINGENCY 'DVP_P4-2: 515T573'
 OPEN BRANCH FROM BUS 314918 TO BUS 314934 CKT 1   /*8NO ANNA     500.0 - 8SPOTSYL     500.0
 OPEN BRANCH FROM BUS 314934 TO BUS 926730 CKT 1   /*8SPOTSYL     500.0 - AC1-158 MAIN 500.0
 OPEN BUS 926730                                   /*AC1-158 MAIN 500.0
 OPEN BUS 926731                                   /*AC1-158 COL1  34.5
 OPEN BUS 926732                                   /*AC1-158 COL2  34.5
 OPEN BUS 926733                                   /*AC1-158 COL3  34.5
 OPEN BUS 926734                                   /*AC1-158 COL4  34.5
 OPEN BUS 926735                                   /*AC1-158 TER1  13.8
 OPEN BUS 926736                                   /*AC1-158 TER2  13.8
 OPEN BUS 926737                                   /*AC1-158 C1     0.4
 OPEN BUS 926738                                   /*AC1-158 C2     0.4
 OPEN BUS 926739                                   /*AC1-158 E1     0.4
 OPEN BUS 926740                                   /*AC1-158 E2     0.4
END
Breaker AC 112.34 % 112.92 % 3938.0 C 4446.87 64.22
DVP AG1-133 TAP-8LADYSMITH 500.0 kV Ckt 1 line
962840 to 314911 ckt 1
DVP_P4-2: H1T573
CONTINGENCY 'DVP_P4-2: H1T573'
 OPEN BRANCH FROM BUS 314755 TO BUS 314934 CKT 1   /*3SPOTSYL     115.0 - 8SPOTSYL     500.0
 OPEN BRANCH FROM BUS 314918 TO BUS 314934 CKT 1   /*8NO ANNA     500.0 - 8SPOTSYL     500.0
END
Breaker AC 111.92 % 112.52 % 3938.0 C 4431.08 64.39
DVP 8CHCKAHM-8ELMONT 500.0 kV Ckt 1 line
314903 to 314908 ckt 1
DVP_P4-2: 563T576
CONTINGENCY 'DVP_P4-2: 563T576'
 OPEN BRANCH FROM BUS 314902 TO BUS 314914 CKT 1   /*8CARSON      500.0 - 8MDLTHAN     500.0
 OPEN BRANCH FROM BUS 314914 TO BUS 314918 CKT 1   /*8MDLTHAN     500.0 - 8NO ANNA     500.0
END
Breaker AC 113.19 % 113.5 % 3637.0 C 4128.14 94.53
DVP 8NO ANNA-8SPOTSYL 500.0 kV Ckt 1 line
314918 to 314934 ckt 1
DVP_P4-2: H1T575
CONTINGENCY 'DVP_P4-2: H1T575'
 OPEN BRANCH FROM BUS 314196 TO BUS 314911 CKT 1   /*6LADYSMITH   230.0 - 8LADYSMITH   500.0
 OPEN BRANCH FROM BUS 314911 TO BUS 962840 CKT 1   /*8LADYSMITH   500.0 - AG1-133 TAP  500.0
END
Breaker AC 111.52 % 112.12 % 3940.0 C 4417.65 68.25
DVP 8NO ANNA-AG1-133 TAP 500.0 kV Ckt 1 line
314918 to 962840 ckt 1
DVP_P4-2: 515T573
CONTINGENCY 'DVP_P4-2: 515T573'
 OPEN BRANCH FROM BUS 314918 TO BUS 314934 CKT 1   /*8NO ANNA     500.0 - 8SPOTSYL     500.0
 OPEN BRANCH FROM BUS 314934 TO BUS 926730 CKT 1   /*8SPOTSYL     500.0 - AC1-158 MAIN 500.0
 OPEN BUS 926730                                   /*AC1-158 MAIN 500.0
 OPEN BUS 926731                                   /*AC1-158 COL1  34.5
 OPEN BUS 926732                                   /*AC1-158 COL2  34.5
 OPEN BUS 926733                                   /*AC1-158 COL3  34.5
 OPEN BUS 926734                                   /*AC1-158 COL4  34.5
 OPEN BUS 926735                                   /*AC1-158 TER1  13.8
 OPEN BUS 926736                                   /*AC1-158 TER2  13.8
 OPEN BUS 926737                                   /*AC1-158 C1     0.4
 OPEN BUS 926738                                   /*AC1-158 C2     0.4
 OPEN BUS 926739                                   /*AC1-158 E1     0.4
 OPEN BUS 926740                                   /*AC1-158 E2     0.4
END
Breaker AC 111.31 % 111.72 % 3938.0 C 4399.53 64.22
DVP 8NO ANNA-AG1-133 TAP 500.0 kV Ckt 1 line
314918 to 962840 ckt 1
DVP_P4-2: H1T573
CONTINGENCY 'DVP_P4-2: H1T573'
 OPEN BRANCH FROM BUS 314755 TO BUS 314934 CKT 1   /*3SPOTSYL     115.0 - 8SPOTSYL     500.0
 OPEN BRANCH FROM BUS 314918 TO BUS 314934 CKT 1   /*8NO ANNA     500.0 - 8SPOTSYL     500.0
END
Breaker AC 110.86 % 111.3 % 3938.0 C 4382.95 64.39
DVP 6CHESTF B-6VARINA 230.0 kV Ckt 1 line
314287 to 314260 ckt 1
DVP_P4-2: 563T576
CONTINGENCY 'DVP_P4-2: 563T576'
 OPEN BRANCH FROM BUS 314902 TO BUS 314914 CKT 1   /*8CARSON      500.0 - 8MDLTHAN     500.0
 OPEN BRANCH FROM BUS 314914 TO BUS 314918 CKT 1   /*8MDLTHAN     500.0 - 8NO ANNA     500.0
END
Breaker AC 102.58 % 102.9 % 1204.0 C 1238.89 21.5
DVP 6VARINA-6CHARCTY 230.0 kV Ckt 1 line
314260 to 314225 ckt 1
DVP_P4-2: 563T576
CONTINGENCY 'DVP_P4-2: 563T576'
 OPEN BRANCH FROM BUS 314902 TO BUS 314914 CKT 1   /*8CARSON      500.0 - 8MDLTHAN     500.0
 OPEN BRANCH FROM BUS 314914 TO BUS 314918 CKT 1   /*8MDLTHAN     500.0 - 8NO ANNA     500.0
END
Breaker AC 102.28 % 102.6 % 1204.0 C 1235.28 21.5

Light Load Analysis

At this time light load analysis not required for this project.

System Reinforcements

The table below lists all network upgrades which resolve the identified overloaded facilities in this report.

Important to Note:

Note for Uprate Projects: Per Tariff Part VII, Subpart B, section 304 (B), if a project is an uprate (project relies on the Interconnection Facilities of a prior project) whose base project does not qualify for the expedited process, the uprate also will not qualify for the expedited process, regardless of analysis results.

Notes regarding Results displayed:

  1. Some flowgate overloads that a New Service Request contributes to, but does not contribute enough to meet cost allocation eligibility (per Manual 14A, Attachment B.3), may be reported in this Transition Sort report. These types of flowgates do not affect the classification of the New Service Request as either Expedited Process or Transition Cycle #1 because cost allocation eligibility has not been met.
  2. For projects that were determined to not meet Expedited Process eligibility and are being reprioritized to Transition Cycle #1, not all reinforcements in excess of $5,000,000 may be shown in this report. This report may only display a subset of those reinforcements determined to be in excess of $5,000,000 which would classify the project as not meeting Expedited Process Eligibility. This is not a formal System Impact Study.
  3. Reinforcements previously identified by Transmission Owners for violations on lower voltage facilities are included in this report. Transmission Owner analysis will be updated as part of the Expedited Process and Transition Cycle 1 retools.
System Reinforcements
RTEP ID Title Total Cost
b2990 PJM Baseline Upgrade b2990. $350,000
n6130 Rebuild 12.4 miles of 230 kV Line 259 from Chesterfield to Basin with 2-636 ACSR. $31,000,000
b3694.8 Partial wreck and rebuild 10.34 miles of 230 kV line #249 Carson-Locks to achieve a minimum summer emergency rating of 1047 MVA. $15,365,000
n6581 Rebuild 12.68 miles of 230 kV Line 2002 from Carson to Poe with 2-636 ACSR. $31,700,000
b3694.7 Energize in-service spare 500-230 kV Carson Tx#1 $1,000,000
n8238 Rebuild 1.38 mi miles of 230 kV Line 217 from Varina to Charles City with 2-768.2 ACSS 250 C $2,070,000
s2609.8 Rebuild approximately 10 miles segment of 230kV Line #205 from Locks to Tyler and upgrade the terminal equipment. The minimum summer normal rating of the line segment will be 1572MVA. $27,000,000
n6179 Rebuild 12.3 miles of 230 kV Line 2003 from Poe to Harrowgate with 2-636 ACSR. $30,750,000
b3056 PJM Baseline Upgrade b3056. Partial Rebuild 230 kV Line #2113 Waller to Lightfoot. $0
n8152 Add additional 500/230 kV transformer at Midlothian Substation $22,000,000
n6178 Rebuild 4.5 miles of 230 kV Line 2003 from Harrowgate to Tyler with 2-636 ACSR. $11,250,000
n8239 Rebuild 9.46 miles of 230 kV Line 217 from Chesterfield to Varina with 2-768.2 ACSS 250 C $14,190,000
n6172 Rebuild 37.41 miles of 500 kV Line 563 from Carson to Midlothian with 3-1351.5 125C ACSR. $115,971,000
n6539 Build new 500 kV Line from Rawlings to Morrisville Substation 110 miles $400,000,000
b3692 Rebuild approximately 27.7-miles of 500 kV transmission line from Elmont to Chickahominy. $0
b3020 PJM baseline upgrade b3020: Rebuild 500kV Line #574 Ladysmith to Elmont . $0
n6063 Replace Wave traps at Ladysmith and Possum Pt 500 kV substations. $500,000
n6157 Relay Change Outs (CT) at Ladysmith and Possum Pt 500 kV substations. $120,000
n7611 Rebuild 9.1 miles of 500 kV Line 575 from Ladysmith to AG1-133 Tap with 3-1351.5 113C ACSR. Replace wave Trap, Lien lead at Ladysmith terminal. $28,510,000
n5609 Rebuild 41.13 miles of 500 kV Line 576 from Midlothian to North Anna with 3-1351.5 125C ACSR. $127,503,000
n6160 Rebuild 18.75 miles of 500 kV Line 594 from Spotsylvania to Morrisvile with 3-1351.5 113C ACSR. $58,125,000
n6132 Rebuild 14.02 miles of 500 kV Line 573 from North Anna to Spotsylvania with 3-1351.5 113C ACSR. $43,462,000
n7634 Rebuild 500 kV Line #575 from North Anna to AG1-133 Tap. $17,086,500

Attachments

Export to CSV Download all tables in report

Uprate Chain
Project Project Status MFO MWE MWC Disposition
AG1-178 Active 500.0 500.0 324.94 Transition Cycle 1
AG1-184 Active 500.0 0.0 175.06 Transition Cycle 1

Conclusion

The Transition Sort load flow retool results indicate that AG1-178 is not eligible for the Expedited Process per PJM Tariff Part VII, Subpart B, section 304 (A) will be reprioritized to Transition Cycle #1. See next steps for your project in the "Introduction" section above.