AG1-171 Transition Sort Retool Results -- Qualifies for Expedited Process

v1.00 released 2023-12-14 10:58

Hopewell-Surry 230kV

12.0 MW Capacity / 20.0 MW Energy

Introduction

In accordance with Tariff Part VII, Subpart B, section 304, PJM performed load flow analysis (Transition Sort Retool) on all AE1 through AG1 projects that have met eligibility requirements according to Tariff, Part VII, Subpart B, section 303. The purpose of this study is to determine whether a project would be classified as eligible for the Expedited Process (Fast Lane) or if it would be reprioritized to be studied as part of Transition Cycle #1 (TC1) using the criteria from the Expedited Process Eligibility section of Tariff Part VII, section 304. This is not a System Impact Study report.

Below are the results of the study, how the study was performed, criterion used in the evaluation of the Expedited Process vs. TC1 determination, and next steps in the interconnection process for your project.

Eligible for Expedited Process:

The AG1-171 project has been determined to meet the initial screen to be eligible for the Expedited Process according to the Expedited Process Eligibility requirements in Tariff Part VII, Subpart B, section 304. Though your project initially screens as eligible for the Expedited Process, there are several conditions identified under Tariff Part VII, Subpart B, section 304 (B) that could shift your project from the Expedited Process into TC1. Please see "Expedited Process Rules" below.

Transition Sort Retool Study Process and Criteria:

In order to determine Expedited Process vs. Transition Cycle #1 classification, projects which met the Transition Eligibility requirements from Tariff Part VII, Subpart B, section 303 were studied on the base case model that was used for the original System Impact Study analysis. Both a summer peak and light load load flow analysis were performed. Projects that have cost allocation eligibility or are identified as the first to cause a system violation which requires the need for a Network Upgrade with a total estimated cost greater than $5 million will be reprioritized to Transition Cycle #1. All other projects will be eligible for the expedited procedures set forth in Tariff Part VII, Subpart B, section 304 (B).

Expedited Process Eligibility: OATT Tariff Part VII, section 304:

A project is not eligible for the expedited process if it has cost allocation eligibility or is identified as the first to cause, as determined according to Tariff, Part VI, section 217.3, for a Network Upgrade which has a total estimated cost of greater than $5,000,000. Such cost estimate will be based on Transmission Provider's most recently available data.

Not considered in the Transition Sorting: The cost of the Interconnection Facilities is not considered when determining a project's eligibility for the expedited process. Affected Systems upgrade costs are also not considered in the evaluation.

Transition Sort Retool Results Provided:

This report includes a list of:

  1. the overloaded flowgates (overloaded facilities + contingency pair) that the project contributes towards
  2. other interconnection projects that may also contribute to the overloaded facility, and
  3. the total estimated cost for any required Network Upgrades.

Important to Note: Some flowgate overloads that a New Service Request contributes to, but does not contribute enough to meet cost allocation eligibility (per Manual 14A, Attachment B.3), may be reported in this Transition Sort report. These types of flowgates do not affect the classification of the New Service Request as either Expedited Process or Transition Cycle #1 because cost allocation eligibility has not been met.

Next Steps for your project:

Refreshed Retool for Projects in Expedited Process:

After the initial sorting retool, PJM will conduct a refreshed analysis of the projects in the Expedited Process with the Transition Cycle #1 projects lifted from the study case model. After this refreshed analysis (including load flow, short circuit and stability analysis), retooled System Impact Study reports can be delivered to the Project Developers. Once the project's Facilities Study report is completed (and no conditions exist that would require the project to shift to TC1, see "Expedited Process Rules" below), the final GIA will be tendered along with the Facilities Study report.

Expedited Process Rules:

Though your project initially screens to be eligible for the Expedited Process, there are several conditions identified under Tariff Part VII, Subpart B, section 304 (B) that could shift your project into TC1 until the final GIA is tendered.

  • If stability analysis or a sag study is completed during the expedited process, and it is determined that a project has an estimated Network Upgrade cost greater than $5,000,000, the project will be removed from the expedited process and shifted to Transition Cycle #1.
  • If it is determined during the Facilities Study that the cost of a Network Upgrade is now estimated to be greater than $5,000,000, the project will be removed from the expedited process and shifted to Transition Cycle #1.
  • If a project is an uprate (project relies on the Interconnection Facilities of a prior project) whose base project does not qualify for the expedited process, the uprate also will not qualify for the expedited process, regardless of analysis results.
  • If the interconnected Transmission Owner identifies the need for a Network Upgrade due to a violation of their criteria that is in excess of $5M, the project will be removed from the expedited process and shifted to Transition Cycle #1.

General

The Interconnection Customer (IC), has proposed a Solar generating facility located in the Dominion zone — Surry County, Virginia. The installed facilities will have a total capability of 20.0 MW with 12.0 MW of this output being recognized by PJM as Capacity.

Project Information
Queue Number AG1-171
Project Name Hopewell-Surry 230kV
Developer Name SR-Colonial Trail LLC
State Virginia
County Surry
Transmission Owner Dominion
MFO 20.0 MW
MWE 20.0 MW
MWC 12.0 MW
Fuel Type Solar
Basecase Study Year 2024

Point of Interconnection

AG1-171 "Hopewell-Surry 230kV" will interconnect with the Dominion transmission system. The primary POI is a direct connect to the Colonial Trail 230 kV substation.

 

Summer Peak Analysis

The Queue Project was evaluated as a 20.0 MW (Capacity 12.0 MW) injection in the Dominion area. Project was evaluated for compliance with applicable reliability planning criteria (PJM, NERC, NERC Regional Reliability Councils, and Transmission Owners). Potential Summer peak period network impacts are listed below:

Important to Note: Some flowgate overloads that a New Service Request contributes to, but does not contribute enough to meet cost allocation eligibility (per Manual 14A, Attachment B.3), may be reported in this Transition Sort report. These types of flowgates do not affect the classification of the New Service Request as either Expedited Process or Transition Cycle #1 because cost allocation eligibility has not been met.

Summer Peak Analysis
Area Facility Description Contingency Name Contingency Type DC|AC Initial Loading Final Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Details
DVP 6HOPEWLL-6CHESTF B 230.0 kV Ckt 1 line
314303 to 314287 ckt 1
DVP_P1-2: LN 228
CONTINGENCY 'DVP_P1-2: LN 228'
 OPEN BRANCH FROM BUS 314286 TO BUS 314303 CKT 1   /*6CHESTF A    230.0 - 6HOPEWLL     230.0
END
Single AC 149.56 % 149.99 % 449.32 B 673.93 4.65
DVP 6HOPEWLL-6CHESTF A 230.0 kV Ckt 1 line
314303 to 314286 ckt 1
DVP_P4-2: 211T2124
CONTINGENCY 'DVP_P4-2: 211T2124'
 OPEN BRANCH FROM BUS 314269 TO BUS 314291 CKT 1   /*6PRGEORG     230.0 - 3PRGEORG     115.0
 OPEN BRANCH FROM BUS 314269 TO BUS 314303 CKT 1   /*6PRGEORG     230.0 - 6HOPEWLL     230.0
 OPEN BRANCH FROM BUS 314287 TO BUS 314303 CKT 1   /*6CHESTF B    230.0 - 6HOPEWLL     230.0
 OPEN BUS 314269                                   /*6PRGEORG     230.0
END
Breaker AC 166.73 % 168.01 % 549.0 C 922.38 8.51
DVP AD1-151 TAP-6HOPEWLL 230.0 kV Ckt 1 line
935160 to 314303 ckt 1
DVP_P4-2: 240T2041
CONTINGENCY 'DVP_P4-2: 240T2041'
 OPEN BRANCH FROM BUS 314303 TO BUS 925330 CKT 2   /*6HOPEWLL     230.0 - AB2-190 TAP  230.0
 OPEN BRANCH FROM BUS 942550 TO BUS 925330 CKT 2   /*AE2-270 TAP  230.0 - AB2-190 TAP  230.0
 OPEN BUS 315077                                   /*1HOPHCF1      13.8
 OPEN BUS 315078                                   /*1HOPHCF2      13.8
 OPEN BUS 315079                                   /*1HOPHCF3      13.8
 OPEN BUS 315080                                   /*1HOPHCF4      13.8
 OPEN BUS 316132                                   /*AB2-190 C    230.0
 OPEN BUS 925332                                   /*AB2-190 E    230.0
END
Breaker AC 119.58 % 120.8 % 830.0 C 1002.6 10.1
DVP 6HOPEWLL-6CHESTF A 230.0 kV Ckt 1 line
314303 to 314286 ckt 1
DVP_P7-1: LN 212-240-D
CONTINGENCY 'DVP_P7-1: LN 212-240-D'
 OPEN BRANCH FROM BUS 313896 TO BUS 314538 CKT 1   /*6COLONIAL TR 230.0 - 6SURRY       230.0
 OPEN BRANCH FROM BUS 961610 TO BUS 314538 CKT 2   /*AG1-000B TAP 230.0 - 6SURRY       230.0
END
Tower AC 162.18 % 163.68 % 549.0 C 898.61 8.97
DVP 6HOPEWLL-6CHESTF A 230.0 kV Ckt 1 line
314303 to 314286 ckt 1
DVP_P7-1: LN 212-240-C
CONTINGENCY 'DVP_P7-1: LN 212-240-C'
 OPEN BRANCH FROM BUS 313896 TO BUS 314538 CKT 1   /*6COLONIAL TR 230.0 - 6SURRY       230.0
 OPEN BRANCH FROM BUS 961610 TO BUS 942550 CKT 2   /*AG1-000B TAP 230.0 - AE2-270 TAP  230.0
END
Tower AC 156.08 % 157.64 % 549.0 C 865.46 8.97
DVP 6PRGEORG-3PRGEORG 230.0/115.0 kV Ckt 1 transformer
314269 to 314291 ckt 1
DVP_P7-1: LN 211-228
CONTINGENCY 'DVP_P7-1: LN 211-228'
 OPEN BRANCH FROM BUS 314286 TO BUS 314303 CKT 1   /*6CHESTF A    230.0 - 6HOPEWLL     230.0
 OPEN BRANCH FROM BUS 314287 TO BUS 314303 CKT 1   /*6CHESTF B    230.0 - 6HOPEWLL     230.0
END
Tower AC 137.33 % 138.61 % 287.5 C 398.51 3.8

Light Load Analysis

At this time light load analysis not required for this project.

System Reinforcements

The table below lists all network upgrades which resolve the identified overloaded facilities in this report.

Important to Note: Some flowgate overloads that a New Service Request contributes to, but does not contribute enough to meet cost allocation eligibility (per Manual 14A, Attachment B.3), may be reported in this Transition Sort report. These types of flowgates do not affect the classification of the New Service Request as either Expedited Process or Transition Cycle #1 because cost allocation eligibility has not been met.

Reinforcements previously identified by Transmission Owners for violations on lower voltage facilities are included in this report. Transmission Owner analysis will be updated as part of the Expedited Process and Transition Cycle 1 retools.

System Reinforcements
RTEP ID Title Total Cost
b3694.12 Upgrade equipment at Chesterfield substation to not limit ratings on Lines 211 and 228. $0
b3694.13 Upgrade equipment at Hopewell substation to not limit ratings on Lines 211 and 228. $0
b2922 PJM Baseline Upgrade b2922. Rebuild 8 of 11 miles of 230kV Lines #211 $0
b3694.11 Reconductor approximately 2.9 miles of 230 kV Line #228 Chesterfield – Hopewell to achieve a minimum summer emergency rating of 1046 MVA. $0
b3694.10 Reconductor approximately 2.9 miles of 230 kV Line #211 Chesterfield – Hopewell to achieve a minimum summer emergency rating of 1046 MVA. $0
n7199 Rebuild 1.63 miles of 230 kV Line 2197 from Hopewell to Colonial Trail with 2-636 ACSR. $2,445,000
n8056 Wreck and rebuild the existing 115 kV Line and Add new 230 kV Circuit $32,493,499

Attachments

Conclusion

The Transition Sort load flow retool results indicate that AG1-171 is eligible for the Expedited Process per PJM Tariff Part VII, Subpart B, section 304 (A). See next steps for your project in the "Introduction" section above.