AG1-120 Transition Sort Retool Results -- Reprioritized to Transition Cycle #1

v1.00 released 2023-12-14 10:52

Glidden-Cherry Valley 138 kV

71.16 MW Capacity / 118.6 MW Energy

Introduction

In accordance with Tariff Part VII, Subpart B, section 304, PJM performed load flow analysis (Transition Sort Retool) on all AE1 through AG1 projects that have met eligibility requirements according to Tariff, Part VII, Subpart B, section 303. The purpose of this study is to determine whether a project would be classified as eligible for the Expedited Process (Fast Lane) or if it would be reprioritized to be studied as part of Transition Cycle #1 (TC1) using the criteria from the Expedited Process Eligibility section of Tariff Part VII, section 304. This is not a System Impact Study report.

Below are the results of the study, details of how the study was performed, criterion used in the evaluation of the Expedited Process vs. TC1 determination, and next steps in the interconnection process for your project.

Transition Cycle #1:

The AG1-120 project has not met the Expedited Process Eligibility requirements in Tariff Part VII, Subpart B, section 304 and will therefore be reprioritized to Transition Cycle #1. Please see "Transition Cycle #1 Rules" below.

Transition Sort Retool Study Process and Criteria:

In order to determine Expedited Process vs. Transition Cycle #1 classification, projects which met the Transition Eligibility requirements from Tariff Part VII, Subpart B, section 303 were studied on the base case model that was used for the original System Impact Study analysis. Both a summer peak and light load load flow analysis were performed. Projects that have cost allocation eligibility or are identified as the first to cause a system violation which requires the need for a Network Upgrade with a total estimated cost greater than $5 million will be reprioritized to Transition Cycle #1. All other projects will be eligible for the expedited procedures set forth in Tariff Part VII, Subpart B, section 304 (B).

Expedited Process Eligibility: OATT Tariff Part VII, section 304:

A project is not eligible for the expedited process if it has cost allocation eligibility or is identified as the first to cause, as determined according to Tariff, Part VI, section 217.3, for a Network Upgrade which has a total estimated cost of greater than $5,000,000. Such cost estimate will be based on Transmission Provider's most recently available data.

Not considered in the Transition Sorting: The cost of the Interconnection Facilities is not considered when determining a project's eligibility for the expedited process. Affected Systems upgrade costs are also not considered in the evaluation.

Transition Sort Retool Results Provided:

This report includes a list of:

  1. the overloaded flowgates (overloaded facilities + contingency pair) that the project contributes towards
  2. other interconnection projects that may also contribute to the overloaded facility, and
  3. the total estimated cost for any required Network Upgrades.

Important Notes:

Note for Uprate Projects: Per Tariff Part VII, Subpart B, section 304 (B), if a project is an uprate (project relies on the Interconnection Facilities of a prior project) whose base project does not qualify for the expedited process, the uprate also will not qualify for the expedited process, regardless of analysis results.

Notes regarding Results displayed:

  1. Some flowgate overloads that a New Service Request contributes to, but does not contribute enough to meet cost allocation eligibility (per Manual 14A, Attachment B.3), may be reported in this Transition Sort report. These types of flowgates do not affect the classification of the New Service Request as either Expedited Process or Transition Cycle #1 because cost allocation eligibility has not been met.
  2. For projects that were determined to not meet Expedited Process eligibility and are being reprioritized to Transition Cycle #1, not all reinforcements in excess of $5,000,000 may be shown in this report. This report may only display a subset of those reinforcements determined to be in excess of $5,000,000 which would classify the project as not meeting Expedited Process Eligibility. This is not a formal System Impact Study.

Next Steps for your project:

Transition Cycle #1 Rules:

Refer to Tariff Part VII, Subpart B, section 304 (C) for the Transition Cycle #1 Project Rules.

Transition Cycle #1 will start no later than one year from the Transition Start Date (July 10, 2023). Transition Cycle #1 will run simultaneously with the expedited process, however Transition Cycle #1, Phase III will not begin until all expedited process projects have been completed.

Projects that are reprioritized to Transition Cycle #1 will not need to re-apply to the Interconnection Cycle Process. Therefore, there is no Application Review Phase for Transition Cycle #1. The cycle process for Transition Cycle #1 includes three Study Phases and three Decision Points:

  1. Phase I System Impact Study and Decision Point I; and
  2. Phase II System Impact Study and Decision Point II; and
  3. Phase III System Impact Study and Decision Point III

Refer to Tariff Part VII, Subpart D, section 307 for the Transition Cycle #1 study process.

General

The Interconnection Customer (IC), has proposed a Solar generating facility located in the ComEd zone — DeKalb County, Illinois. The installed facilities will have a total capability of 118.6 MW with 71.16 MW of this output being recognized by PJM as Capacity.

Project Information
Queue Number AG1-120
Project Name Glidden-Cherry Valley 138 kV
Developer Name Leeward Renewable Energy Development, LLC
State Illinois
County DeKalb
Transmission Owner ComEd
MFO 118.6 MW
MWE 118.6 MW
MWC 71.16 MW
Fuel Type Solar
Basecase Study Year 2024

Point of Interconnection

AG1-120 will interconnect on the ComEd transmission system at a new proposed 138 kV substation tapping the Glidden - Cherry Valley 138 kV line.

Summer Peak Analysis

The Queue Project was evaluated as a 118.6 MW (Capacity 71.16 MW) injection in the ComEd area. Project was evaluated for compliance with applicable reliability planning criteria (PJM, NERC, NERC Regional Reliability Councils, and Transmission Owners). Potential Summer peak period network impacts are listed below:

Important to Note:

Note for Uprate Projects: Per Tariff Part VII, Subpart B, section 304 (B), if a project is an uprate (project relies on the Interconnection Facilities of a prior project) whose base project does not qualify for the expedited process, the uprate also will not qualify for the expedited process, regardless of analysis results.

Notes regarding Results displayed:

  1. Some flowgate overloads that a New Service Request contributes to, but does not contribute enough to meet cost allocation eligibility (per Manual 14A, Attachment B.3), may be reported in this Transition Sort report. These types of flowgates do not affect the classification of the New Service Request as either Expedited Process or Transition Cycle #1 because cost allocation eligibility has not been met.
  2. For projects that were determined to not meet Expedited Process eligibility and are being reprioritized to Transition Cycle #1, not all reinforcements in excess of $5,000,000 may be shown in this report. This report may only display a subset of those reinforcements determined to be in excess of $5,000,000 which would classify the project as not meeting Expedited Process Eligibility. This is not a formal System Impact Study.
Summer Peak Analysis
Area Facility Description Contingency Name Contingency Type DC|AC Initial Loading Final Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Details
CE GARDEN PR; R-SILVER LK; R 345.0 kV Ckt 1 line
924470 to 270883 ckt 1
COMED_P1-2_345-L15502_B-R-C
CONTINGENCY 'COMED_P1-2_345-L15502_B-R-C'
 TRIP BRANCH FROM BUS 957470 TO BUS 270730 CKT 1   /*AF2-041 TAP  345.0 - ELECT JCT; B 345.0
END
Single AC 99.89 % 100.36 % 1568.0 STE 1573.57 9.5
AEP 05DUMONT-05SORENS 765.0 kV Ckt 1 line
243206 to 246999 ckt 1
AEP_P1-2_#709_546
CONTINGENCY 'AEP_P1-2_#709_546'
 OPEN BRANCH FROM BUS 242924 TO BUS 243208 CKT 1   /*05HANG R     765.0 - 05JEFRSO     765.0
END
Single AC 99.98 % 100.2 % 4142.0 B 4150.16 14.96
AEP/CE AF2-359 TAP-05OLIVE 345.0 kV Ckt 1 line
960680 to 243229 ckt 1
COMED_P4_112-65-BT4-5__
CONTINGENCY 'COMED_P4_112-65-BT4-5__'
 REMOVE SHUNT 1 FROM BUS 270644                    /*WILTON   ;   765.0
 TRIP BRANCH FROM BUS 270644 TO BUS 243206 CKT 1   /*WILTON   ;   765.0 - 05DUMONT     765.0
 TRIP BRANCH FROM BUS 275233 TO BUS 270644 CKT 1   /*WILTON   ;4M 345.0 - WILTON   ;   765.0
 TRIP BRANCH FROM BUS 275233 TO BUS 270927 CKT 1   /*WILTON   ;4M 345.0 - WILTON   ; R 345.0
 TRIP BRANCH FROM BUS 275233 TO BUS 275333 CKT 1   /*WILTON   ;4M 345.0 - WILTON   ;4C  33.0
END
Breaker AC 158.44 % 158.92 % 971.0 B 1543.13 11.73
AEP/CE AF2-359 TAP-05OLIVE 345.0 kV Ckt 1 line
960680 to 243229 ckt 1
COMED_P4_112-65-BT3-4__
CONTINGENCY 'COMED_P4_112-65-BT3-4__'
 REMOVE SHUNT 1 FROM BUS 270644                    /*WILTON   ;   765.0
 TRIP BRANCH FROM BUS 270644 TO BUS 243206 CKT 1   /*WILTON   ;   765.0 - 05DUMONT     765.0
 TRIP BRANCH FROM BUS 275232 TO BUS 270644 CKT 1   /*WILTON   ;3M 345.0 - WILTON   ;   765.0
 TRIP BRANCH FROM BUS 275232 TO BUS 270926 CKT 1   /*WILTON   ;3M 345.0 - WILTON   ; B 345.0
 TRIP BRANCH FROM BUS 275232 TO BUS 275332 CKT 1   /*WILTON   ;3M 345.0 - WILTON   ;3C  33.0
END
Breaker AC 158.43 % 158.92 % 971.0 B 1543.13 11.73
CE WILTON ; R-WILTON ;4M 345.0 kV Ckt 1 line
270927 to 275233 ckt 1
COMED_P4_112-65-BT2-3__
CONTINGENCY 'COMED_P4_112-65-BT2-3__'
 TRIP BRANCH FROM BUS 270644 TO BUS 270607 CKT 1   /*WILTON   ;   765.0 - COLLINS  ;   765.0
 TRIP BRANCH FROM BUS 275232 TO BUS 270644 CKT 1   /*WILTON   ;3M 345.0 - WILTON   ;   765.0
 TRIP BRANCH FROM BUS 275232 TO BUS 270926 CKT 1   /*WILTON   ;3M 345.0 - WILTON   ; B 345.0
 TRIP BRANCH FROM BUS 275232 TO BUS 275332 CKT 1   /*WILTON   ;3M 345.0 - WILTON   ;3C  33.0
END
Breaker AC 153.94 % 154.0 % 1469.0 STE 2262.26 17.84
CE WILTON ;4M-WILTON ; 345.0/765.0 kV Ckt 1 transformer
275233 to 270644 ckt 1
COMED_P4_112-65-BT2-3__
CONTINGENCY 'COMED_P4_112-65-BT2-3__'
 TRIP BRANCH FROM BUS 270644 TO BUS 270607 CKT 1   /*WILTON   ;   765.0 - COLLINS  ;   765.0
 TRIP BRANCH FROM BUS 275232 TO BUS 270644 CKT 1   /*WILTON   ;3M 345.0 - WILTON   ;   765.0
 TRIP BRANCH FROM BUS 275232 TO BUS 270926 CKT 1   /*WILTON   ;3M 345.0 - WILTON   ; B 345.0
 TRIP BRANCH FROM BUS 275232 TO BUS 275332 CKT 1   /*WILTON   ;3M 345.0 - WILTON   ;3C  33.0
END
Breaker AC 153.94 % 154.0 % 1469.0 STE 2262.25 17.84
CE WILTON ;3M-WILTON ; 345.0/765.0 kV Ckt 1 transformer
275232 to 270644 ckt 1
COMED_P4_112-65-BT5-6__
CONTINGENCY 'COMED_P4_112-65-BT5-6__'
 TRIP BRANCH FROM BUS 270644 TO BUS 270607 CKT 1   /*WILTON   ;   765.0 - COLLINS  ;   765.0
 TRIP BRANCH FROM BUS 275233 TO BUS 270644 CKT 1   /*WILTON   ;4M 345.0 - WILTON   ;   765.0
 TRIP BRANCH FROM BUS 275233 TO BUS 270927 CKT 1   /*WILTON   ;4M 345.0 - WILTON   ; R 345.0
 TRIP BRANCH FROM BUS 275233 TO BUS 275333 CKT 1   /*WILTON   ;4M 345.0 - WILTON   ;4C  33.0
END
Breaker AC 150.76 % 150.81 % 1469.0 STE 2215.46 17.47
CE WILTON ; B-WILTON ;3M 345.0 kV Ckt 1 line
270926 to 275232 ckt 1
COMED_P4_112-65-BT5-6__
CONTINGENCY 'COMED_P4_112-65-BT5-6__'
 TRIP BRANCH FROM BUS 270644 TO BUS 270607 CKT 1   /*WILTON   ;   765.0 - COLLINS  ;   765.0
 TRIP BRANCH FROM BUS 275233 TO BUS 270644 CKT 1   /*WILTON   ;4M 345.0 - WILTON   ;   765.0
 TRIP BRANCH FROM BUS 275233 TO BUS 270927 CKT 1   /*WILTON   ;4M 345.0 - WILTON   ; R 345.0
 TRIP BRANCH FROM BUS 275233 TO BUS 275333 CKT 1   /*WILTON   ;4M 345.0 - WILTON   ;4C  33.0
END
Breaker AC 150.76 % 150.81 % 1469.0 STE 2215.46 17.47
CE GARDEN PR; R-SILVER LK; R 345.0 kV Ckt 1 line
924470 to 270883 ckt 1
COMED_P4_144-45-BT6-8__
CONTINGENCY 'COMED_P4_144-45-BT6-8__'
 TRIP BRANCH FROM BUS 270730 TO BUS 270916 CKT 1   /*ELECT JCT; B 345.0 - WAYNE    ; B 345.0
 TRIP BRANCH FROM BUS 270916 TO BUS 270917 CKT 1   /*WAYNE    ; B 345.0 - WAYNE    ; R 345.0
 TRIP BRANCH FROM BUS 965553 TO BUS 270916 CKT 1   /*AG1-423 TP   345.0 - WAYNE    ; B 345.0
END
Breaker AC 138.98 % 140.0 % 1568.0 STE 2195.25 18.31
CE GARDEN PR; R-SILVER LK; R 345.0 kV Ckt 1 line
924470 to 270883 ckt 1
COMED_P4_144-45-BT6-7__
CONTINGENCY 'COMED_P4_144-45-BT6-7__'
 DISCONNECT BUS 275228                             /*WAYNE    ;1M 138.0
 TRIP BRANCH FROM BUS 270730 TO BUS 270916 CKT 1   /*ELECT JCT; B 345.0 - WAYNE    ; B 345.0
 TRIP BRANCH FROM BUS 270916 TO BUS 270900 CKT 1   /*WAYNE    ; B 345.0 - TOLLWAY ; B  345.0
 TRIP BRANCH FROM BUS 270916 TO BUS 270917 CKT 1   /*WAYNE    ; B 345.0 - WAYNE    ; R 345.0
END
Breaker AC 138.98 % 140.0 % 1568.0 STE 2195.19 18.31
CE UNIV PK N;RP-AF2-359 TAP 345.0 kV Ckt 1 line
274804 to 960680 ckt 1
COMED_P4_112-65-BT4-5__
CONTINGENCY 'COMED_P4_112-65-BT4-5__'
 REMOVE SHUNT 1 FROM BUS 270644                    /*WILTON   ;   765.0
 TRIP BRANCH FROM BUS 270644 TO BUS 243206 CKT 1   /*WILTON   ;   765.0 - 05DUMONT     765.0
 TRIP BRANCH FROM BUS 275233 TO BUS 270644 CKT 1   /*WILTON   ;4M 345.0 - WILTON   ;   765.0
 TRIP BRANCH FROM BUS 275233 TO BUS 270927 CKT 1   /*WILTON   ;4M 345.0 - WILTON   ; R 345.0
 TRIP BRANCH FROM BUS 275233 TO BUS 275333 CKT 1   /*WILTON   ;4M 345.0 - WILTON   ;4C  33.0
END
Breaker AC 147.13 % 147.32 % 971.0 STE 1430.5 11.73
CE UNIV PK N;RP-AF2-359 TAP 345.0 kV Ckt 1 line
274804 to 960680 ckt 1
COMED_P4_112-65-BT3-4__
CONTINGENCY 'COMED_P4_112-65-BT3-4__'
 REMOVE SHUNT 1 FROM BUS 270644                    /*WILTON   ;   765.0
 TRIP BRANCH FROM BUS 270644 TO BUS 243206 CKT 1   /*WILTON   ;   765.0 - 05DUMONT     765.0
 TRIP BRANCH FROM BUS 275232 TO BUS 270644 CKT 1   /*WILTON   ;3M 345.0 - WILTON   ;   765.0
 TRIP BRANCH FROM BUS 275232 TO BUS 270926 CKT 1   /*WILTON   ;3M 345.0 - WILTON   ; B 345.0
 TRIP BRANCH FROM BUS 275232 TO BUS 275332 CKT 1   /*WILTON   ;3M 345.0 - WILTON   ;3C  33.0
END
Breaker AC 147.13 % 147.32 % 971.0 STE 1430.5 11.73
CE CHERRY VA; B-GARDEN PR; R 345.0 kV Ckt 1 line
270694 to 924470 ckt 1
COMED_P4_144-45-BT6-8__
CONTINGENCY 'COMED_P4_144-45-BT6-8__'
 TRIP BRANCH FROM BUS 270730 TO BUS 270916 CKT 1   /*ELECT JCT; B 345.0 - WAYNE    ; B 345.0
 TRIP BRANCH FROM BUS 270916 TO BUS 270917 CKT 1   /*WAYNE    ; B 345.0 - WAYNE    ; R 345.0
 TRIP BRANCH FROM BUS 965553 TO BUS 270916 CKT 1   /*AG1-423 TP   345.0 - WAYNE    ; B 345.0
END
Breaker AC 129.52 % 130.53 % 1568.0 STE 2046.71 18.31
CE CHERRY VA; B-GARDEN PR; R 345.0 kV Ckt 1 line
270694 to 924470 ckt 1
COMED_P4_144-45-BT6-7__
CONTINGENCY 'COMED_P4_144-45-BT6-7__'
 DISCONNECT BUS 275228                             /*WAYNE    ;1M 138.0
 TRIP BRANCH FROM BUS 270730 TO BUS 270916 CKT 1   /*ELECT JCT; B 345.0 - WAYNE    ; B 345.0
 TRIP BRANCH FROM BUS 270916 TO BUS 270900 CKT 1   /*WAYNE    ; B 345.0 - TOLLWAY ; B  345.0
 TRIP BRANCH FROM BUS 270916 TO BUS 270917 CKT 1   /*WAYNE    ; B 345.0 - WAYNE    ; R 345.0
END
Breaker AC 129.51 % 130.53 % 1568.0 STE 2046.65 18.31
CE/NIPS CRETE EC ;BP-17STJOHN 345.0 kV Ckt 1 line
274750 to 255112 ckt 1
COMED_P4_112-65-BT4-5__
CONTINGENCY 'COMED_P4_112-65-BT4-5__'
 REMOVE SHUNT 1 FROM BUS 270644                    /*WILTON   ;   765.0
 TRIP BRANCH FROM BUS 270644 TO BUS 243206 CKT 1   /*WILTON   ;   765.0 - 05DUMONT     765.0
 TRIP BRANCH FROM BUS 275233 TO BUS 270644 CKT 1   /*WILTON   ;4M 345.0 - WILTON   ;   765.0
 TRIP BRANCH FROM BUS 275233 TO BUS 270927 CKT 1   /*WILTON   ;4M 345.0 - WILTON   ; R 345.0
 TRIP BRANCH FROM BUS 275233 TO BUS 275333 CKT 1   /*WILTON   ;4M 345.0 - WILTON   ;4C  33.0
END
Breaker AC 137.94 % 137.99 % 1399.0 B 1930.48 14.85
CE/NIPS CRETE EC ;BP-17STJOHN 345.0 kV Ckt 1 line
274750 to 255112 ckt 1
COMED_P4_112-65-BT3-4__
CONTINGENCY 'COMED_P4_112-65-BT3-4__'
 REMOVE SHUNT 1 FROM BUS 270644                    /*WILTON   ;   765.0
 TRIP BRANCH FROM BUS 270644 TO BUS 243206 CKT 1   /*WILTON   ;   765.0 - 05DUMONT     765.0
 TRIP BRANCH FROM BUS 275232 TO BUS 270644 CKT 1   /*WILTON   ;3M 345.0 - WILTON   ;   765.0
 TRIP BRANCH FROM BUS 275232 TO BUS 270926 CKT 1   /*WILTON   ;3M 345.0 - WILTON   ; B 345.0
 TRIP BRANCH FROM BUS 275232 TO BUS 275332 CKT 1   /*WILTON   ;3M 345.0 - WILTON   ;3C  33.0
END
Breaker AC 137.92 % 137.97 % 1399.0 B 1930.27 14.85
CE E FRANKFO; B-CRETE EC ;BP 345.0 kV Ckt 1 line
270728 to 274750 ckt 1
COMED_P4_112-65-BT4-5__
CONTINGENCY 'COMED_P4_112-65-BT4-5__'
 REMOVE SHUNT 1 FROM BUS 270644                    /*WILTON   ;   765.0
 TRIP BRANCH FROM BUS 270644 TO BUS 243206 CKT 1   /*WILTON   ;   765.0 - 05DUMONT     765.0
 TRIP BRANCH FROM BUS 275233 TO BUS 270644 CKT 1   /*WILTON   ;4M 345.0 - WILTON   ;   765.0
 TRIP BRANCH FROM BUS 275233 TO BUS 270927 CKT 1   /*WILTON   ;4M 345.0 - WILTON   ; R 345.0
 TRIP BRANCH FROM BUS 275233 TO BUS 275333 CKT 1   /*WILTON   ;4M 345.0 - WILTON   ;4C  33.0
END
Breaker AC 114.88 % 114.92 % 1483.0 STE 1704.29 15.03
CE E FRANKFO; B-CRETE EC ;BP 345.0 kV Ckt 1 line
270728 to 274750 ckt 1
COMED_P4_112-65-BT3-4__
CONTINGENCY 'COMED_P4_112-65-BT3-4__'
 REMOVE SHUNT 1 FROM BUS 270644                    /*WILTON   ;   765.0
 TRIP BRANCH FROM BUS 270644 TO BUS 243206 CKT 1   /*WILTON   ;   765.0 - 05DUMONT     765.0
 TRIP BRANCH FROM BUS 275232 TO BUS 270644 CKT 1   /*WILTON   ;3M 345.0 - WILTON   ;   765.0
 TRIP BRANCH FROM BUS 275232 TO BUS 270926 CKT 1   /*WILTON   ;3M 345.0 - WILTON   ; B 345.0
 TRIP BRANCH FROM BUS 275232 TO BUS 275332 CKT 1   /*WILTON   ;3M 345.0 - WILTON   ;3C  33.0
END
Breaker AC 114.87 % 114.91 % 1483.0 STE 1704.14 15.03
CE AE2-341 TAP-W PLANO ; R 138.0 kV Ckt 1 line
943120 to 272803 ckt 1
COMED_P4_156-38-TR81___
CONTINGENCY 'COMED_P4_156-38-TR81___'
 REMOVE SWSHUNT FROM BUS 271193                    /*CHERRY VA; R 138.0
 TRIP BRANCH FROM BUS 271193 TO BUS 271387 CKT 1   /*CHERRY VA; R 138.0 - E ROCKFOR;RT 138.0
 TRIP BRANCH FROM BUS 271193 TO BUS 271581 CKT 1   /*CHERRY VA; R 138.0 - ESS B200 ; R 138.0
 TRIP BRANCH FROM BUS 271193 TO BUS 272517 CKT 1   /*CHERRY VA; R 138.0 - STILLMAN ;RT 138.0
 TRIP BRANCH FROM BUS 275165 TO BUS 270695 CKT 1   /*CHERRY VA;1M 138.0 - CHERRY VA; R 345.0
 TRIP BRANCH FROM BUS 275165 TO BUS 271193 CKT 1   /*CHERRY VA;1M 138.0 - CHERRY VA; R 138.0
 TRIP BRANCH FROM BUS 275165 TO BUS 275265 CKT 1   /*CHERRY VA;1M 138.0 - CHERRY VA;1C  34.5
END
Breaker AC 94.63 % 103.85 % 459.0 STE 476.67 44.12

Light Load Analysis

At this time light load analysis not required for this project.

System Reinforcements

The table below lists all network upgrades which resolve the identified overloaded facilities in this report.

Important to Note:

Note for Uprate Projects: Per Tariff Part VII, Subpart B, section 304 (B), if a project is an uprate (project relies on the Interconnection Facilities of a prior project) whose base project does not qualify for the expedited process, the uprate also will not qualify for the expedited process, regardless of analysis results.

Notes regarding Results displayed:

  1. Some flowgate overloads that a New Service Request contributes to, but does not contribute enough to meet cost allocation eligibility (per Manual 14A, Attachment B.3), may be reported in this Transition Sort report. These types of flowgates do not affect the classification of the New Service Request as either Expedited Process or Transition Cycle #1 because cost allocation eligibility has not been met.
  2. For projects that were determined to not meet Expedited Process eligibility and are being reprioritized to Transition Cycle #1, not all reinforcements in excess of $5,000,000 may be shown in this report. This report may only display a subset of those reinforcements determined to be in excess of $5,000,000 which would classify the project as not meeting Expedited Process Eligibility. This is not a formal System Impact Study.
  3. Reinforcements previously identified by Transmission Owners for violations on lower voltage facilities are included in this report. Transmission Owner analysis will be updated as part of the Expedited Process and Transition Cycle 1 retools.
System Reinforcements
RTEP ID Title Total Cost
n4056.1 Replace the 2 3000A 765kV CB's at Dumont station $6,000,000
b3775.1 Swap the NIPSCO Green Acre Tap towers from the St. John-Green Acres-Olive 345 kV line $0
s2509 NextEra review required: Acquired from ComEd. NextEra section SE rating is 1091 MVA $0
b3775.10 Sag study on the Olive – University Park $0
b3775.8 Upgrade existing terminal equipment at St. John on the existing Crete to St. John 345 kV line $0
b3775.2 Reconductor NEET’s section of Crete(IN/IL border)-St. John 345 kV line (6.95 miles). $0
b3775.3 Rebuild ComEd’s section of 345 kV double circuit in IL from St. John to Crete $0
b3775.5 Replace E. Frankfort 345 kV circuit breaker “9-14” with 3150A SF6 circuit breaker. $0
b3775.4 Rebuild 345 kV double circuit extending from Crete to E. Frankfort. $0
n5318.1 Garden Prarie - Silver Lake R 345 kV Line - Reconductor and Station Bus Work $45,700,000
n6779 Plano 138 KV re-conductor a portion of the line $5,600,000
n5145 Reconfigure Wilton 765kV bus $55,229,373
s2929 Move 345 kV line 11126 (Electric Junction-Wayne) to Bus 6 and install 345 kV Bus Tie 5-6 CB. $0

Attachments

Conclusion

The Transition Sort load flow retool results indicate that AG1-120 is not eligible for the Expedited Process per PJM Tariff Part VII, Subpart B, section 304 (A) will be reprioritized to Transition Cycle #1. See next steps for your project in the "Introduction" section above.