Export to CSV

AF2-143 Transition Sort Retool Results -- Reprioritized to Transition Cycle #1

v1.00 released 2023-12-14 11:09

Powerton-Nevada 345 kV

90.0 MW Capacity / 150.0 MW Energy

Introduction

In accordance with Tariff Part VII, Subpart B, section 304, PJM performed load flow analysis (Transition Sort Retool) on all AE1 through AG1 projects that have met eligibility requirements according to Tariff, Part VII, Subpart B, section 303. The purpose of this study is to determine whether a project would be classified as eligible for the Expedited Process (Fast Lane) or if it would be reprioritized to be studied as part of Transition Cycle #1 (TC1) using the criteria from the Expedited Process Eligibility section of Tariff Part VII, section 304. This is not a System Impact Study report.

Below are the results of the study, details of how the study was performed, criterion used in the evaluation of the Expedited Process vs. TC1 determination, and next steps in the interconnection process for your project.

Transition Cycle #1:

The AF2-143 project has not met the Expedited Process Eligibility requirements in Tariff Part VII, Subpart B, section 304 and will therefore be reprioritized to Transition Cycle #1. Please see "Transition Cycle #1 Rules" below.

Transition Sort Retool Study Process and Criteria:

In order to determine Expedited Process vs. Transition Cycle #1 classification, projects which met the Transition Eligibility requirements from Tariff Part VII, Subpart B, section 303 were studied on the base case model that was used for the original System Impact Study analysis. Both a summer peak and light load load flow analysis were performed. Projects that have cost allocation eligibility or are identified as the first to cause a system violation which requires the need for a Network Upgrade with a total estimated cost greater than $5 million will be reprioritized to Transition Cycle #1. All other projects will be eligible for the expedited procedures set forth in Tariff Part VII, Subpart B, section 304 (B).

Expedited Process Eligibility: OATT Tariff Part VII, section 304:

A project is not eligible for the expedited process if it has cost allocation eligibility or is identified as the first to cause, as determined according to Tariff, Part VI, section 217.3, for a Network Upgrade which has a total estimated cost of greater than $5,000,000. Such cost estimate will be based on Transmission Provider's most recently available data.

Not considered in the Transition Sorting: The cost of the Interconnection Facilities is not considered when determining a project's eligibility for the expedited process. Affected Systems upgrade costs are also not considered in the evaluation.

Transition Sort Retool Results Provided:

This report includes a list of:

  1. the overloaded flowgates (overloaded facilities + contingency pair) that the project contributes towards
  2. other interconnection projects that may also contribute to the overloaded facility, and
  3. the total estimated cost for any required Network Upgrades.

Important Notes:

Note for Uprate Projects: Per Tariff Part VII, Subpart B, section 304 (B), if a project is an uprate (project relies on the Interconnection Facilities of a prior project) whose base project does not qualify for the expedited process, the uprate also will not qualify for the expedited process, regardless of analysis results.

Notes regarding Results displayed:

  1. Some flowgate overloads that a New Service Request contributes to, but does not contribute enough to meet cost allocation eligibility (per Manual 14A, Attachment B.3), may be reported in this Transition Sort report. These types of flowgates do not affect the classification of the New Service Request as either Expedited Process or Transition Cycle #1 because cost allocation eligibility has not been met.
  2. For projects that were determined to not meet Expedited Process eligibility and are being reprioritized to Transition Cycle #1, not all reinforcements in excess of $5,000,000 may be shown in this report. This report may only display a subset of those reinforcements determined to be in excess of $5,000,000 which would classify the project as not meeting Expedited Process Eligibility. This is not a formal System Impact Study.

Next Steps for your project:

Transition Cycle #1 Rules:

Refer to Tariff Part VII, Subpart B, section 304 (C) for the Transition Cycle #1 Project Rules.

Transition Cycle #1 will start no later than one year from the Transition Start Date (July 10, 2023). Transition Cycle #1 will run simultaneously with the expedited process, however Transition Cycle #1, Phase III will not begin until all expedited process projects have been completed.

Projects that are reprioritized to Transition Cycle #1 will not need to re-apply to the Interconnection Cycle Process. Therefore, there is no Application Review Phase for Transition Cycle #1. The cycle process for Transition Cycle #1 includes three Study Phases and three Decision Points:

  1. Phase I System Impact Study and Decision Point I; and
  2. Phase II System Impact Study and Decision Point II; and
  3. Phase III System Impact Study and Decision Point III

Refer to Tariff Part VII, Subpart D, section 307 for the Transition Cycle #1 study process.

General

The Interconnection Customer (IC), has proposed a Solar generating facility located in the ComEd zone — Lasalle County, Illinois. The installed facilities will have a total capability of 150.0 MW with 90.0 MW of this output being recognized by PJM as Capacity.

Project Information
Queue Number AF2-143
Project Name Powerton-Nevada 345 kV
Developer Name Aurora Solar LLC
State Illinois
County Lasalle
Transmission Owner ComEd
MFO 150.0 MW
MWE 150.0 MW
MWC 90.0 MW
Fuel Type Solar
Basecase Study Year 2023

Point of Interconnection

AF2-143 will interconnect on the ComEd transmission system at the AD2-038 substation which taps the Powerton - Goodings Grove 345 kV line..

Summer Peak Analysis

The Queue Project was evaluated as a 150.0 MW (Capacity 90.0 MW) injection in the ComEd area. Project was evaluated for compliance with applicable reliability planning criteria (PJM, NERC, NERC Regional Reliability Councils, and Transmission Owners). Potential Summer peak period network impacts are listed below:

Important to Note:

Note for Uprate Projects: Per Tariff Part VII, Subpart B, section 304 (B), if a project is an uprate (project relies on the Interconnection Facilities of a prior project) whose base project does not qualify for the expedited process, the uprate also will not qualify for the expedited process, regardless of analysis results.

Notes regarding Results displayed:

  1. Some flowgate overloads that a New Service Request contributes to, but does not contribute enough to meet cost allocation eligibility (per Manual 14A, Attachment B.3), may be reported in this Transition Sort report. These types of flowgates do not affect the classification of the New Service Request as either Expedited Process or Transition Cycle #1 because cost allocation eligibility has not been met.
  2. For projects that were determined to not meet Expedited Process eligibility and are being reprioritized to Transition Cycle #1, not all reinforcements in excess of $5,000,000 may be shown in this report. This report may only display a subset of those reinforcements determined to be in excess of $5,000,000 which would classify the project as not meeting Expedited Process Eligibility. This is not a formal System Impact Study.
Summer Peak Analysis
Area Facility Description Contingency Name Contingency Type DC|AC Initial Loading Final Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Details
CE WILTON ; R-WILTON ;4M 345.0 kV Ckt 1 line
270927 to 275233 ckt 1
COMED_P4_112-65-BT2-3__
CONTINGENCY 'COMED_P4_112-65-BT2-3__'
 TRIP BRANCH FROM BUS 270644 TO BUS 270607 CKT 1   /*WILTON   ;   765.0 - COLLINS  ;   765.0
 TRIP BRANCH FROM BUS 275232 TO BUS 270644 CKT 1   /*WILTON   ;3M 345.0 - WILTON   ;   765.0
 TRIP BRANCH FROM BUS 275232 TO BUS 270926 CKT 1   /*WILTON   ;3M 345.0 - WILTON   ; B 345.0
 TRIP BRANCH FROM BUS 275232 TO BUS 275332 CKT 1   /*WILTON   ;3M 345.0 - WILTON   ;3C  33.0
END
Breaker AC 120.67 % 120.85 % 1469.0 STE 1775.32 22.49
CE WILTON ;4M-WILTON ; 345.0/765.0 kV Ckt 1 transformer
275233 to 270644 ckt 1
COMED_P4_112-65-BT2-3__
CONTINGENCY 'COMED_P4_112-65-BT2-3__'
 TRIP BRANCH FROM BUS 270644 TO BUS 270607 CKT 1   /*WILTON   ;   765.0 - COLLINS  ;   765.0
 TRIP BRANCH FROM BUS 275232 TO BUS 270644 CKT 1   /*WILTON   ;3M 345.0 - WILTON   ;   765.0
 TRIP BRANCH FROM BUS 275232 TO BUS 270926 CKT 1   /*WILTON   ;3M 345.0 - WILTON   ; B 345.0
 TRIP BRANCH FROM BUS 275232 TO BUS 275332 CKT 1   /*WILTON   ;3M 345.0 - WILTON   ;3C  33.0
END
Breaker AC 120.65 % 120.83 % 1469.0 STE 1775.05 22.49
CE WILTON ; B-WILTON ;3M 345.0 kV Ckt 1 line
270926 to 275232 ckt 1
COMED_P4_112-65-BT5-6__
CONTINGENCY 'COMED_P4_112-65-BT5-6__'
 TRIP BRANCH FROM BUS 270644 TO BUS 270607 CKT 1   /*WILTON   ;   765.0 - COLLINS  ;   765.0
 TRIP BRANCH FROM BUS 275233 TO BUS 270644 CKT 1   /*WILTON   ;4M 345.0 - WILTON   ;   765.0
 TRIP BRANCH FROM BUS 275233 TO BUS 270927 CKT 1   /*WILTON   ;4M 345.0 - WILTON   ; R 345.0
 TRIP BRANCH FROM BUS 275233 TO BUS 275333 CKT 1   /*WILTON   ;4M 345.0 - WILTON   ;4C  33.0
END
Breaker AC 118.2 % 118.37 % 1469.0 STE 1738.92 22.01
CE WILTON ;3M-WILTON ; 345.0/765.0 kV Ckt 1 transformer
275232 to 270644 ckt 1
COMED_P4_112-65-BT5-6__
CONTINGENCY 'COMED_P4_112-65-BT5-6__'
 TRIP BRANCH FROM BUS 270644 TO BUS 270607 CKT 1   /*WILTON   ;   765.0 - COLLINS  ;   765.0
 TRIP BRANCH FROM BUS 275233 TO BUS 270644 CKT 1   /*WILTON   ;4M 345.0 - WILTON   ;   765.0
 TRIP BRANCH FROM BUS 275233 TO BUS 270927 CKT 1   /*WILTON   ;4M 345.0 - WILTON   ; R 345.0
 TRIP BRANCH FROM BUS 275233 TO BUS 275333 CKT 1   /*WILTON   ;4M 345.0 - WILTON   ;4C  33.0
END
Breaker AC 118.18 % 118.36 % 1469.0 STE 1738.64 22.01
AMIL/CE POWERTON ; R-7TAZEWELL 345.0 kV Ckt 1 line
270855 to 349662 ckt 1
COMED_P4_012-45-BT4-5__
CONTINGENCY 'COMED_P4_012-45-BT4-5__'
 TRIP BRANCH FROM BUS 270716 TO BUS 270736 CKT 1   /*DRESDEN  ; B 345.0 - ELWOOD   ; B 345.0
 TRIP BRANCH FROM BUS 270716 TO BUS 930750 CKT 1   /*DRESDEN  ; B 345.0 - AB1-122 TAP  345.0
 TRIP BRANCH FROM BUS 270736 TO BUS 270737 CKT 1   /*ELWOOD   ; B 345.0 - ELWOOD   ; R 345.0
END
Breaker AC 118.46 % 123.2 % 1489.0 B 1834.45 69.85
CE GOODINGS ;4B-GOODINGS ;3B 345.0 kV Ckt 1 line
270770 to 270766 ckt 1
COMED_P4_116-45-L11614_
CONTINGENCY 'COMED_P4_116-45-L11614_'
 DISCONNECT BUS 270769                             /*GOODINGS ;2R 345.0
 TRIP BRANCH FROM BUS 270667 TO BUS 270665 CKT 1   /*BLUE ISL ;RT 345.0 - BLUE ISL ; R 345.0
 TRIP BRANCH FROM BUS 270667 TO BUS 270927 CKT 1   /*BLUE ISL ;RT 345.0 - WILTON   ; R 345.0
 TRIP BRANCH FROM BUS 270769 TO BUS 270667 CKT 1   /*GOODINGS ;2R 345.0 - BLUE ISL ;RT 345.0
END
Breaker AC 99.19 % 100.04 % 2083.0 STE 2083.83 21.36
AEP/CE AF2-359 TAP-05OLIVE 345.0 kV Ckt 1 line
960680 to 243229 ckt 1
COMED_P4_023-65-BT2-3__
CONTINGENCY 'COMED_P4_023-65-BT2-3__'
 TRIP BRANCH FROM BUS 270607 TO BUS 270630 CKT 1   /*COLLINS  ;   765.0 - PLANO    ;   765.0
 TRIP BRANCH FROM BUS 270644 TO BUS 243206 CKT 1   /*WILTON   ;   765.0 - 05DUMONT     765.0
END
Breaker AC 112.84 % 113.14 % 971.0 B 1098.59 15.33
AEP/CE AF2-359 TAP-05OLIVE 345.0 kV Ckt 1 line
960680 to 243229 ckt 1
COMED_P4_112-65-BT4-5__
CONTINGENCY 'COMED_P4_112-65-BT4-5__'
 TRIP BRANCH FROM BUS 270644 TO BUS 243206 CKT 1   /*WILTON   ;   765.0 - 05DUMONT     765.0
 TRIP BRANCH FROM BUS 275233 TO BUS 270644 CKT 1   /*WILTON   ;4M 345.0 - WILTON   ;   765.0
 TRIP BRANCH FROM BUS 275233 TO BUS 270927 CKT 1   /*WILTON   ;4M 345.0 - WILTON   ; R 345.0
 TRIP BRANCH FROM BUS 275233 TO BUS 275333 CKT 1   /*WILTON   ;4M 345.0 - WILTON   ;4C  33.0
END
Breaker AC 112.74 % 113.04 % 971.0 B 1097.62 15.33
AEP/CE AF2-359 TAP-05OLIVE 345.0 kV Ckt 1 line
960680 to 243229 ckt 1
COMED_P4_112-65-BT3-4__
CONTINGENCY 'COMED_P4_112-65-BT3-4__'
 TRIP BRANCH FROM BUS 270644 TO BUS 243206 CKT 1   /*WILTON   ;   765.0 - 05DUMONT     765.0
 TRIP BRANCH FROM BUS 275232 TO BUS 270644 CKT 1   /*WILTON   ;3M 345.0 - WILTON   ;   765.0
 TRIP BRANCH FROM BUS 275232 TO BUS 270926 CKT 1   /*WILTON   ;3M 345.0 - WILTON   ; B 345.0
 TRIP BRANCH FROM BUS 275232 TO BUS 275332 CKT 1   /*WILTON   ;3M 345.0 - WILTON   ;3C  33.0
END
Breaker AC 112.73 % 113.04 % 971.0 B 1097.62 15.33
AEP/CE AF2-359 TAP-05OLIVE 345.0 kV Ckt 1 line
960680 to 243229 ckt 1
AEP_P4_#2978_05DUMONT 765_B
CONTINGENCY 'AEP_P4_#2978_05DUMONT 765_B'
 OPEN BRANCH FROM BUS 243206 TO' BUS 243207 CKT 1   /*05DUMONT     765.0 - 05GRNTWN     765.0
 OPEN BRANCH FROM BUS 243206 TO BUS 270644 CKT 1   /*05DUMONT     765.0 - WILTON   ;   765.0
END
Breaker AC 113.01 % 113.25 % 971.0 B 1099.66 15.23
CE UNIV PK N;RP-AF2-359 TAP 345.0 kV Ckt 1 line
274804 to 960680 ckt 1
AEP_P4_#2978_05DUMONT 765_B
CONTINGENCY 'AEP_P4_#2978_05DUMONT 765_B'
 OPEN BRANCH FROM BUS 243206 TO' BUS 243207 CKT 1   /*05DUMONT     765.0 - 05GRNTWN     765.0
 OPEN BRANCH FROM BUS 243206 TO BUS 270644 CKT 1   /*05DUMONT     765.0 - WILTON   ;   765.0
END
Breaker AC 112.25 % 112.44 % 971.0 STE 1091.79 15.23
CE UNIV PK N;RP-AF2-359 TAP 345.0 kV Ckt 1 line
274804 to 960680 ckt 1
COMED_P4_023-65-BT2-3__
CONTINGENCY 'COMED_P4_023-65-BT2-3__'
 TRIP BRANCH FROM BUS 270607 TO BUS 270630 CKT 1   /*COLLINS  ;   765.0 - PLANO    ;   765.0
 TRIP BRANCH FROM BUS 270644 TO BUS 243206 CKT 1   /*WILTON   ;   765.0 - 05DUMONT     765.0
END
Breaker AC 111.66 % 111.86 % 971.0 STE 1086.16 15.33
CE UNIV PK N;RP-AF2-359 TAP 345.0 kV Ckt 1 line
274804 to 960680 ckt 1
COMED_P4_112-65-BT4-5__
CONTINGENCY 'COMED_P4_112-65-BT4-5__'
 TRIP BRANCH FROM BUS 270644 TO BUS 243206 CKT 1   /*WILTON   ;   765.0 - 05DUMONT     765.0
 TRIP BRANCH FROM BUS 275233 TO BUS 270644 CKT 1   /*WILTON   ;4M 345.0 - WILTON   ;   765.0
 TRIP BRANCH FROM BUS 275233 TO BUS 270927 CKT 1   /*WILTON   ;4M 345.0 - WILTON   ; R 345.0
 TRIP BRANCH FROM BUS 275233 TO BUS 275333 CKT 1   /*WILTON   ;4M 345.0 - WILTON   ;4C  33.0
END
Breaker AC 111.56 % 111.76 % 971.0 STE 1085.19 15.33
CE UNIV PK N;RP-AF2-359 TAP 345.0 kV Ckt 1 line
274804 to 960680 ckt 1
COMED_P4_112-65-BT3-4__
CONTINGENCY 'COMED_P4_112-65-BT3-4__'
 TRIP BRANCH FROM BUS 270644 TO BUS 243206 CKT 1   /*WILTON   ;   765.0 - 05DUMONT     765.0
 TRIP BRANCH FROM BUS 275232 TO BUS 270644 CKT 1   /*WILTON   ;3M 345.0 - WILTON   ;   765.0
 TRIP BRANCH FROM BUS 275232 TO BUS 270926 CKT 1   /*WILTON   ;3M 345.0 - WILTON   ; B 345.0
 TRIP BRANCH FROM BUS 275232 TO BUS 275332 CKT 1   /*WILTON   ;3M 345.0 - WILTON   ;3C  33.0
END
Breaker AC 111.56 % 111.76 % 971.0 STE 1085.19 15.33
CE/NIPS CRETE EC ;BP-17STJOHN 345.0 kV Ckt 1 line
274750 to 255112 ckt 1
COMED_P4_023-65-BT2-3__
CONTINGENCY 'COMED_P4_023-65-BT2-3__'
 TRIP BRANCH FROM BUS 270607 TO BUS 270630 CKT 1   /*COLLINS  ;   765.0 - PLANO    ;   765.0
 TRIP BRANCH FROM BUS 270644 TO BUS 243206 CKT 1   /*WILTON   ;   765.0 - 05DUMONT     765.0
END
Breaker AC 110.81 % 110.83 % 1399.0 B 1550.51 18.09
CE/NIPS CRETE EC ;BP-17STJOHN 345.0 kV Ckt 1 line
274750 to 255112 ckt 1
AEP_P4_#2978_05DUMONT 765_B
CONTINGENCY 'AEP_P4_#2978_05DUMONT 765_B'
 OPEN BRANCH FROM BUS 243206 TO' BUS 243207 CKT 1   /*05DUMONT     765.0 - 05GRNTWN     765.0
 OPEN BRANCH FROM BUS 243206 TO BUS 270644 CKT 1   /*05DUMONT     765.0 - WILTON   ;   765.0
END
Breaker AC 110.71 % 110.74 % 1399.0 B 1549.25 18.01
CE/NIPS CRETE EC ;BP-17STJOHN 345.0 kV Ckt 1 line
274750 to 255112 ckt 1
COMED_P4_112-65-BT4-5__
CONTINGENCY 'COMED_P4_112-65-BT4-5__'
 TRIP BRANCH FROM BUS 270644 TO BUS 243206 CKT 1   /*WILTON   ;   765.0 - 05DUMONT     765.0
 TRIP BRANCH FROM BUS 275233 TO BUS 270644 CKT 1   /*WILTON   ;4M 345.0 - WILTON   ;   765.0
 TRIP BRANCH FROM BUS 275233 TO BUS 270927 CKT 1   /*WILTON   ;4M 345.0 - WILTON   ; R 345.0
 TRIP BRANCH FROM BUS 275233 TO BUS 275333 CKT 1   /*WILTON   ;4M 345.0 - WILTON   ;4C  33.0
END
Breaker AC 110.48 % 110.5 % 1399.0 B 1545.89 18.09
CE/NIPS CRETE EC ;BP-17STJOHN 345.0 kV Ckt 1 line
274750 to 255112 ckt 1
COMED_P4_112-65-BT3-4__
CONTINGENCY 'COMED_P4_112-65-BT3-4__'
 TRIP BRANCH FROM BUS 270644 TO BUS 243206 CKT 1   /*WILTON   ;   765.0 - 05DUMONT     765.0
 TRIP BRANCH FROM BUS 275232 TO BUS 270644 CKT 1   /*WILTON   ;3M 345.0 - WILTON   ;   765.0
 TRIP BRANCH FROM BUS 275232 TO BUS 270926 CKT 1   /*WILTON   ;3M 345.0 - WILTON   ; B 345.0
 TRIP BRANCH FROM BUS 275232 TO BUS 275332 CKT 1   /*WILTON   ;3M 345.0 - WILTON   ;3C  33.0
END
Breaker AC 110.46 % 110.48 % 1399.0 B 1545.62 18.09
CE/NIPS CRETE EC ;BP-17STJOHN 345.0 kV Ckt 1 line
274750 to 255112 ckt 1
COMED_P4_023-65-BT4-5__
CONTINGENCY 'COMED_P4_023-65-BT4-5__'
 TRIP BRANCH FROM BUS 270644 TO BUS 243206 CKT 1   /*WILTON   ;   765.0 - 05DUMONT     765.0
 TRIP BRANCH FROM BUS 275168 TO BUS 270607 CKT 1   /*COLLINS  ;2M 345.0 - COLLINS  ;   765.0
 TRIP BRANCH FROM BUS 275168 TO BUS 270697 CKT 1   /*COLLINS  ;2M 345.0 - COLLINS  ; R 345.0
 TRIP BRANCH FROM BUS 275168 TO BUS 275268 CKT 1   /*COLLINS  ;2M 345.0 - COLLINS  ;2C  33.0
END
Breaker AC 110.39 % 110.42 % 1399.0 B 1544.78 18.09
AMIL/CE POWERTON ; R-7TAZEWELL 345.0 kV Ckt 1 line
270855 to 349662 ckt 1
COMED_P7_345-L19601_B-S_+_345-L9801__R-S_FSA
CONTINGENCY 'COMED_P7_345-L19601_B-S_+_345-L9801__R-S_FSA'
 TRIP BRANCH FROM BUS 270790 TO BUS 270770 CKT 1   /*KATYDID  ; B 345.0 - GOODINGS ;4B 345.0
 TRIP BRANCH FROM BUS 918050 TO BUS 270769 CKT 1   /*AA1-018 TAP  345.0 - GOODINGS ;2R 345.0
END
Tower AC 135.71 % 142.92 % 1489.0 B 2128.08 110.72
AMIL/CE POWERTON ; R-7TAZEWELL 345.0 kV Ckt 1 line
270855 to 349662 ckt 1
COMED_P7_345-L0301__B-S_+_345-L9801__R-S_FSA
CONTINGENCY 'COMED_P7_345-L0301__B-S_+_345-L9801__R-S_FSA'
 TRIP BRANCH FROM BUS 270854 TO BUS 270790 CKT 1   /*POWERTON ; B 345.0 - KATYDID  ; B 345.0
 TRIP BRANCH FROM BUS 918050 TO BUS 270769 CKT 1   /*AA1-018 TAP  345.0 - GOODINGS ;2R 345.0
END
Tower AC 121.31 % 128.43 % 1489.0 B 1912.32 110.76
AEP/NIPS 17STILLWELL-05DUMONT 345.0 kV Ckt 1 line
255113 to 243219 ckt 1
AEP_P4_#2978_05DUMONT 765_B
CONTINGENCY 'AEP_P4_#2978_05DUMONT 765_B'
 OPEN BRANCH FROM BUS 243206 TO' BUS 243207 CKT 1   /*05DUMONT     765.0 - 05GRNTWN     765.0
 OPEN BRANCH FROM BUS 243206 TO BUS 270644 CKT 1   /*05DUMONT     765.0 - WILTON   ;   765.0
END
Breaker AC 104.29 % 104.44 % 1409.0 B 1471.56 20.61
AEP/NIPS 17STILLWELL-05DUMONT 345.0 kV Ckt 1 line
255113 to 243219 ckt 1
COMED_P4_023-65-BT4-5__
CONTINGENCY 'COMED_P4_023-65-BT4-5__'
 TRIP BRANCH FROM BUS 270644 TO BUS 243206 CKT 1   /*WILTON   ;   765.0 - 05DUMONT     765.0
 TRIP BRANCH FROM BUS 275168 TO BUS 270607 CKT 1   /*COLLINS  ;2M 345.0 - COLLINS  ;   765.0
 TRIP BRANCH FROM BUS 275168 TO BUS 270697 CKT 1   /*COLLINS  ;2M 345.0 - COLLINS  ; R 345.0
 TRIP BRANCH FROM BUS 275168 TO BUS 275268 CKT 1   /*COLLINS  ;2M 345.0 - COLLINS  ;2C  33.0
END
Breaker AC 101.87 % 102.04 % 1409.0 B 1437.74 21.07

Light Load Analysis

At this time light load analysis not required for this project.

System Reinforcements

The table below lists all network upgrades which resolve the identified overloaded facilities in this report.

Important to Note:

Note for Uprate Projects: Per Tariff Part VII, Subpart B, section 304 (B), if a project is an uprate (project relies on the Interconnection Facilities of a prior project) whose base project does not qualify for the expedited process, the uprate also will not qualify for the expedited process, regardless of analysis results.

Notes regarding Results displayed:

  1. Some flowgate overloads that a New Service Request contributes to, but does not contribute enough to meet cost allocation eligibility (per Manual 14A, Attachment B.3), may be reported in this Transition Sort report. These types of flowgates do not affect the classification of the New Service Request as either Expedited Process or Transition Cycle #1 because cost allocation eligibility has not been met.
  2. For projects that were determined to not meet Expedited Process eligibility and are being reprioritized to Transition Cycle #1, not all reinforcements in excess of $5,000,000 may be shown in this report. This report may only display a subset of those reinforcements determined to be in excess of $5,000,000 which would classify the project as not meeting Expedited Process Eligibility. This is not a formal System Impact Study.
  3. Reinforcements previously identified by Transmission Owners for violations on lower voltage facilities are included in this report. Transmission Owner analysis will be updated as part of the Expedited Process and Transition Cycle 1 retools.
System Reinforcements
RTEP ID Title Total Cost
b3775.11 Upgrade the limiting element at Stillwell substation to increase the rating of the Stillwell-Dumont. $0
b3775.7 Upgrade limiting element at Dumont substation on the Stillwell-Dumont 345 kV line. $0
b3775.6 Perform sag study mitigation work on the Dumont-Stillwell 345 kV line $0
b3775.1 Swap the NIPSCO Green Acre Tap towers from the St. John-Green Acres-Olive 345 kV line $0
b3775.10 Sag study on the Olive – University Park $0
s2509 NextEra review required: Acquired from ComEd. NextEra section SE rating is 1091 MVA $0
b3775.8 Upgrade existing terminal equipment at St. John on the existing Crete to St. John 345 kV line $0
b3775.3 Rebuild ComEd’s section of 345 kV double circuit in IL from St. John to Crete $0
b3775.2 Reconductor NEET’s section of Crete(IN/IL border)-St. John 345 kV line (6.95 miles). $0
n6279 TSS 116 Replace 345 kV Circuit Breaker $3,200,000
n8162 Powerton - Tazewell 345 kV Line Sag Mitigation and Disconnect Switch Replacement $9,700,000
(TBD) Ameren - Powerton - Tazewell 345 kV Line Reconductoring $750,000
n6280 Mitigate the sag on the ComEd Powerton - Tazewell L0304 345 kV line. $2,470,796
n5145 Reconfigure Wilton 765kV bus $55,229,373

Attachments

Conclusion

The Transition Sort load flow retool results indicate that AF2-143 is not eligible for the Expedited Process per PJM Tariff Part VII, Subpart B, section 304 (A) will be reprioritized to Transition Cycle #1. See next steps for your project in the "Introduction" section above.