AE2-261 Transition Sort Retool Results -- Reprioritized to Transition Cycle #1

v1.00 released 2023-12-14 11:14

Kincaid-Pana

179.4 MW Capacity / 299.0 MW Energy

Introduction

In accordance with Tariff Part VII, Subpart B, section 304, PJM performed load flow analysis (Transition Sort Retool) on all AE1 through AG1 projects that have met eligibility requirements according to Tariff, Part VII, Subpart B, section 303. The purpose of this study is to determine whether a project would be classified as eligible for the Expedited Process (Fast Lane) or if it would be reprioritized to be studied as part of Transition Cycle #1 (TC1) using the criteria from the Expedited Process Eligibility section of Tariff Part VII, section 304. This is not a System Impact Study report.

Below are the results of the study, details of how the study was performed, criterion used in the evaluation of the Expedited Process vs. TC1 determination, and next steps in the interconnection process for your project.

Transition Cycle #1:

The AE2-261 project has not met the Expedited Process Eligibility requirements in Tariff Part VII, Subpart B, section 304 and will therefore be reprioritized to Transition Cycle #1. Please see "Transition Cycle #1 Rules" below.

Transition Sort Retool Study Process and Criteria:

In order to determine Expedited Process vs. Transition Cycle #1 classification, projects which met the Transition Eligibility requirements from Tariff Part VII, Subpart B, section 303 were studied on the base case model that was used for the original System Impact Study analysis. Both a summer peak and light load load flow analysis were performed. Projects that have cost allocation eligibility or are identified as the first to cause a system violation which requires the need for a Network Upgrade with a total estimated cost greater than $5 million will be reprioritized to Transition Cycle #1. All other projects will be eligible for the expedited procedures set forth in Tariff Part VII, Subpart B, section 304 (B).

Expedited Process Eligibility: OATT Tariff Part VII, section 304:

A project is not eligible for the expedited process if it has cost allocation eligibility or is identified as the first to cause, as determined according to Tariff, Part VI, section 217.3, for a Network Upgrade which has a total estimated cost of greater than $5,000,000. Such cost estimate will be based on Transmission Provider's most recently available data.

Not considered in the Transition Sorting: The cost of the Interconnection Facilities is not considered when determining a project's eligibility for the expedited process. Affected Systems upgrade costs are also not considered in the evaluation.

Transition Sort Retool Results Provided:

This report includes a list of:

  1. the overloaded flowgates (overloaded facilities + contingency pair) that the project contributes towards
  2. other interconnection projects that may also contribute to the overloaded facility, and
  3. the total estimated cost for any required Network Upgrades.

Important Notes:

Note for Uprate Projects: Per Tariff Part VII, Subpart B, section 304 (B), if a project is an uprate (project relies on the Interconnection Facilities of a prior project) whose base project does not qualify for the expedited process, the uprate also will not qualify for the expedited process, regardless of analysis results.

Notes regarding Results displayed:

  1. Some flowgate overloads that a New Service Request contributes to, but does not contribute enough to meet cost allocation eligibility (per Manual 14A, Attachment B.3), may be reported in this Transition Sort report. These types of flowgates do not affect the classification of the New Service Request as either Expedited Process or Transition Cycle #1 because cost allocation eligibility has not been met.
  2. For projects that were determined to not meet Expedited Process eligibility and are being reprioritized to Transition Cycle #1, not all reinforcements in excess of $5,000,000 may be shown in this report. This report may only display a subset of those reinforcements determined to be in excess of $5,000,000 which would classify the project as not meeting Expedited Process Eligibility. This is not a formal System Impact Study.

Next Steps for your project:

Transition Cycle #1 Rules:

Refer to Tariff Part VII, Subpart B, section 304 (C) for the Transition Cycle #1 Project Rules.

Transition Cycle #1 will start no later than one year from the Transition Start Date (July 10, 2023). Transition Cycle #1 will run simultaneously with the expedited process, however Transition Cycle #1, Phase III will not begin until all expedited process projects have been completed.

Projects that are reprioritized to Transition Cycle #1 will not need to re-apply to the Interconnection Cycle Process. Therefore, there is no Application Review Phase for Transition Cycle #1. The cycle process for Transition Cycle #1 includes three Study Phases and three Decision Points:

  1. Phase I System Impact Study and Decision Point I; and
  2. Phase II System Impact Study and Decision Point II; and
  3. Phase III System Impact Study and Decision Point III

Refer to Tariff Part VII, Subpart D, section 307 for the Transition Cycle #1 study process.

General

The Interconnection Customer (IC), has proposed a Solar generating facility located in the ComEd zone — Christian County, Illinois. The installed facilities will have a total capability of 299.0 MW with 179.4 MW of this output being recognized by PJM as Capacity.

Project Information
Queue Number AE2-261
Project Name Kincaid-Pana
Developer Name Black Diamond Solar Power, LLC
State Illinois
County Christian
Transmission Owner ComEd
MFO 299.0 MW
MWE 299.0 MW
MWC 179.4 MW
Fuel Type Solar
Basecase Study Year 2022

Point of Interconnection

AE2-261 will interconnect on the ComEd transmission system tapping the Kincaid - Pana 345 kV line.

Summer Peak Analysis

The Queue Project was evaluated as a 299.0 MW (Capacity 179.4 MW) injection in the ComEd area. Project was evaluated for compliance with applicable reliability planning criteria (PJM, NERC, NERC Regional Reliability Councils, and Transmission Owners). Potential Summer peak period network impacts are listed below:

Important to Note:

Note for Uprate Projects: Per Tariff Part VII, Subpart B, section 304 (B), if a project is an uprate (project relies on the Interconnection Facilities of a prior project) whose base project does not qualify for the expedited process, the uprate also will not qualify for the expedited process, regardless of analysis results.

Notes regarding Results displayed:

  1. Some flowgate overloads that a New Service Request contributes to, but does not contribute enough to meet cost allocation eligibility (per Manual 14A, Attachment B.3), may be reported in this Transition Sort report. These types of flowgates do not affect the classification of the New Service Request as either Expedited Process or Transition Cycle #1 because cost allocation eligibility has not been met.
  2. For projects that were determined to not meet Expedited Process eligibility and are being reprioritized to Transition Cycle #1, not all reinforcements in excess of $5,000,000 may be shown in this report. This report may only display a subset of those reinforcements determined to be in excess of $5,000,000 which would classify the project as not meeting Expedited Process Eligibility. This is not a formal System Impact Study.
Summer Peak Analysis
Area Facility Description Contingency Name Contingency Type DC|AC Initial Loading Final Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Details
CE AE1-172 TAP-AD1-100 TAP 345.0 kV Ckt 1 line
939400 to 934720 ckt 1
COMED_P4_012-45-BT12-14
CONTINGENCY 'COMED_P4_012-45-BT12-14'
 TRIP BRANCH FROM BUS 270717 TO BUS 930740 CKT 1   /*DRESDEN  ; R 345.0 - AB1-122 TAP  345.0
 TRIP BRANCH FROM BUS 270853 TO BUS 270717 CKT 1   /*PONTIAC  ; R 345.0 - DRESDEN  ; R 345.0
END
Breaker AC 137.35 % 140.26 % 2107.0 STE 2955.3 60.6
CE LORETTO ; B-AE1-172 TAP 345.0 kV Ckt 1 line
270704 to 939400 ckt 1
COMED_P4_012-45-BT12-14
CONTINGENCY 'COMED_P4_012-45-BT12-14'
 TRIP BRANCH FROM BUS 270717 TO BUS 930740 CKT 1   /*DRESDEN  ; R 345.0 - AB1-122 TAP  345.0
 TRIP BRANCH FROM BUS 270853 TO BUS 270717 CKT 1   /*PONTIAC  ; R 345.0 - DRESDEN  ; R 345.0
END
Breaker AC 149.77 % 153.09 % 1846.0 STE 2826.04 60.6
CE PONTIAC ; B-LORETTO ; B 345.0 kV Ckt 1 line
270852 to 270704 ckt 1
COMED_P4_012-45-BT12-14
CONTINGENCY 'COMED_P4_012-45-BT12-14'
 TRIP BRANCH FROM BUS 270717 TO BUS 930740 CKT 1   /*DRESDEN  ; R 345.0 - AB1-122 TAP  345.0
 TRIP BRANCH FROM BUS 270853 TO BUS 270717 CKT 1   /*PONTIAC  ; R 345.0 - DRESDEN  ; R 345.0
END
Breaker DC 140.52 % 143.84 % 1837.0 STE 2642.37 60.7
CE AD1-100 TAP-WILTON ; B 345.0 kV Ckt 1 line
934720 to 270926 ckt 1
COMED_P4_012-45-BT12-14
CONTINGENCY 'COMED_P4_012-45-BT12-14'
 TRIP BRANCH FROM BUS 270717 TO BUS 930740 CKT 1   /*DRESDEN  ; R 345.0 - AB1-122 TAP  345.0
 TRIP BRANCH FROM BUS 270853 TO BUS 270717 CKT 1   /*PONTIAC  ; R 345.0 - DRESDEN  ; R 345.0
END
Breaker AC 110.87 % 112.18 % 1846.0 STE 2070.9 29.15
AEP/AMIL J1180 TAP-05SULLIVAN 345.0 kV Ckt 1 line
966790 to 247712 ckt 1
AEP_P4_#3128_05EUGENE 345_A2
CONTINGENCY 'AEP_P4_#3128_05EUGENE 345_A2'
 OPEN BRANCH FROM BUS 243221 TO BUS 249504 CKT 1   /*05EUGENE     345.0 - 08CAYSUB     345.0
 OPEN BRANCH FROM BUS 243221 TO BUS 348885 CKT 1   /*05EUGENE     345.0 - 7BUNSONVILLE 345.0
END
Breaker AC 111.67 % 113.83 % 1685.0 B 1918.11 52.2
CE AB2-070 TAP-BROKAW ; T 345.0 kV Ckt 1 line
924260 to 270673 ckt 1
COMED_P4_021-45-BT5-7__
CONTINGENCY 'COMED_P4_021-45-BT5-7__'
 TRIP BRANCH FROM BUS 270796 TO BUS 347955 CKT 1   /*KINCAID  ; B 345.0 - 7AUSTIN      345.0
 TRIP BRANCH FROM BUS 270804 TO BUS 270796 CKT 1   /*LATHAM   ; T 345.0 - KINCAID  ; B 345.0
 TRIP BRANCH FROM BUS 270804 TO BUS 348856 CKT 1   /*LATHAM   ; T 345.0 - 7LATHAM      345.0
 TRIP BRANCH FROM BUS 270804 TO BUS 905080 CKT 1   /*LATHAM   ; T 345.0 - W4-005 TAP   345.0
END
Breaker AC 108.7 % 115.57 % 1346.0 STE 1555.61 91.85
CE AC1-053 TAP-AB2-070 TAP 345.0 kV Ckt 1 line
925770 to 924260 ckt 1
COMED_P4_021-45-BT5-7__
CONTINGENCY 'COMED_P4_021-45-BT5-7__'
 TRIP BRANCH FROM BUS 270796 TO BUS 347955 CKT 1   /*KINCAID  ; B 345.0 - 7AUSTIN      345.0
 TRIP BRANCH FROM BUS 270804 TO BUS 270796 CKT 1   /*LATHAM   ; T 345.0 - KINCAID  ; B 345.0
 TRIP BRANCH FROM BUS 270804 TO BUS 348856 CKT 1   /*LATHAM   ; T 345.0 - 7LATHAM      345.0
 TRIP BRANCH FROM BUS 270804 TO BUS 905080 CKT 1   /*LATHAM   ; T 345.0 - W4-005 TAP   345.0
END
Breaker AC 98.3 % 105.17 % 1346.0 STE 1415.65 91.85
AEP/OVEC 05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line
242865 to 248000 ckt Z1
AEP_P4_#1760_05JEFRSO 765_A
CONTINGENCY 'AEP_P4_#1760_05JEFRSO 765_A'
 OPEN BRANCH FROM BUS 242924 TO BUS 243208 CKT 1   /*05HANG R     765.0 - 05JEFRSO     765.0
 OPEN BRANCH FROM BUS 243207 TO BUS 243208 CKT 1   /*05GRNTWN     765.0 - 05JEFRSO     765.0
END
Breaker DC 114.07 % 115.0 % 2255.0 B 2593.17 24.73

Light Load Analysis

At this time light load analysis not required for this project.

System Reinforcements

The table below lists all network upgrades which resolve the identified overloaded facilities in this report.

Important to Note:

Note for Uprate Projects: Per Tariff Part VII, Subpart B, section 304 (B), if a project is an uprate (project relies on the Interconnection Facilities of a prior project) whose base project does not qualify for the expedited process, the uprate also will not qualify for the expedited process, regardless of analysis results.

Notes regarding Results displayed:

  1. Some flowgate overloads that a New Service Request contributes to, but does not contribute enough to meet cost allocation eligibility (per Manual 14A, Attachment B.3), may be reported in this Transition Sort report. These types of flowgates do not affect the classification of the New Service Request as either Expedited Process or Transition Cycle #1 because cost allocation eligibility has not been met.
  2. For projects that were determined to not meet Expedited Process eligibility and are being reprioritized to Transition Cycle #1, not all reinforcements in excess of $5,000,000 may be shown in this report. This report may only display a subset of those reinforcements determined to be in excess of $5,000,000 which would classify the project as not meeting Expedited Process Eligibility. This is not a formal System Impact Study.
  3. Reinforcements previously identified by Transmission Owners for violations on lower voltage facilities are included in this report. Transmission Owner analysis will be updated as part of the Expedited Process and Transition Cycle 1 retools.
System Reinforcements
RTEP ID Title Total Cost
n4106.3 Extend One (1) Tower on the Jefferson - Clifty Creek (IKEC) 345 kV Circuit $409,714
n4106 Replace Two (2) Switches at the Clifty Creek 345 kV Station $412,916
b3748 Replace four Clifty Creek 345 kV 3000A switches with 5000 A 345 kV switches $850,000
b2878 Upgrade the Clifty Creek 345 kV risers $3,675,000
(TBD) Brokaw - AB2-070 - AC1-053 345 kV Line - Mitigate Sag on the Line. $17,300,000
(TBD) MISO (AMIL) Review required $0
n5808 AEP: eliminate the Eugene stuck breaker contingency. (AMIL upgrade will not be required) $3,424,014
n6840 Install a new 345kV bus tie circuit breaker at Station 12 Dresden $3,444,645

Attachments

Export to CSV Download all tables in report

Uprate Chain
Project Project Status MFO MWE MWC Disposition
AE2-261 Active 299.0 299.0 179.4 Transition Cycle 1
AG1-460 Active 329.0 30.0 12.0 Transition Cycle 1

Conclusion

The Transition Sort load flow retool results indicate that AE2-261 is not eligible for the Expedited Process per PJM Tariff Part VII, Subpart B, section 304 (A) will be reprioritized to Transition Cycle #1. See next steps for your project in the "Introduction" section above.