Export to CSV

AG1-424 Transition Sort Retool Results -- Reprioritized to Transition Cycle #1

v1.00 released 2023-12-14 11:00

Sowers 138 kV

60.0 MW Capacity / 100.0 MW Energy

Introduction

In accordance with Tariff Part VII, Subpart B, section 304, PJM performed load flow analysis (Transition Sort Retool) on all AE1 through AG1 projects that have met eligibility requirements according to Tariff, Part VII, Subpart B, section 303. The purpose of this study is to determine whether a project would be classified as eligible for the Expedited Process (Fast Lane) or if it would be reprioritized to be studied as part of Transition Cycle #1 (TC1) using the criteria from the Expedited Process Eligibility section of Tariff Part VII, section 304. This is not a System Impact Study report.

Below are the results of the study, details of how the study was performed, criterion used in the evaluation of the Expedited Process vs. TC1 determination, and next steps in the interconnection process for your project.

Transition Cycle #1:

The AG1-424 project has not met the Expedited Process Eligibility requirements in Tariff Part VII, Subpart B, section 304 and will therefore be reprioritized to Transition Cycle #1. Please see "Transition Cycle #1 Rules" below.

Transition Sort Retool Study Process and Criteria:

In order to determine Expedited Process vs. Transition Cycle #1 classification, projects which met the Transition Eligibility requirements from Tariff Part VII, Subpart B, section 303 were studied on the base case model that was used for the original System Impact Study analysis. Both a summer peak and light load load flow analysis were performed. Projects that have cost allocation eligibility or are identified as the first to cause a system violation which requires the need for a Network Upgrade with a total estimated cost greater than $5 million will be reprioritized to Transition Cycle #1. All other projects will be eligible for the expedited procedures set forth in Tariff Part VII, Subpart B, section 304 (B).

Expedited Process Eligibility: OATT Tariff Part VII, section 304:

A project is not eligible for the expedited process if it has cost allocation eligibility or is identified as the first to cause, as determined according to Tariff, Part VI, section 217.3, for a Network Upgrade which has a total estimated cost of greater than $5,000,000. Such cost estimate will be based on Transmission Provider's most recently available data.

Not considered in the Transition Sorting: The cost of the Interconnection Facilities is not considered when determining a project's eligibility for the expedited process. Affected Systems upgrade costs are also not considered in the evaluation.

Transition Sort Retool Results Provided:

This report includes a list of:

  1. the overloaded flowgates (overloaded facilities + contingency pair) that the project contributes towards
  2. other interconnection projects that may also contribute to the overloaded facility, and
  3. the total estimated cost for any required Network Upgrades.

Important Notes:

Note for Uprate Projects: Per Tariff Part VII, Subpart B, section 304 (B), if a project is an uprate (project relies on the Interconnection Facilities of a prior project) whose base project does not qualify for the expedited process, the uprate also will not qualify for the expedited process, regardless of analysis results.

Notes regarding Results displayed:

  1. Some flowgate overloads that a New Service Request contributes to, but does not contribute enough to meet cost allocation eligibility (per Manual 14A, Attachment B.3), may be reported in this Transition Sort report. These types of flowgates do not affect the classification of the New Service Request as either Expedited Process or Transition Cycle #1 because cost allocation eligibility has not been met.
  2. For projects that were determined to not meet Expedited Process eligibility and are being reprioritized to Transition Cycle #1, not all reinforcements in excess of $5,000,000 may be shown in this report. This report may only display a subset of those reinforcements determined to be in excess of $5,000,000 which would classify the project as not meeting Expedited Process Eligibility. This is not a formal System Impact Study.

Next Steps for your project:

Transition Cycle #1 Rules:

Refer to Tariff Part VII, Subpart B, section 304 (C) for the Transition Cycle #1 Project Rules.

Transition Cycle #1 will start no later than one year from the Transition Start Date (July 10, 2023). Transition Cycle #1 will run simultaneously with the expedited process, however Transition Cycle #1, Phase III will not begin until all expedited process projects have been completed.

Projects that are reprioritized to Transition Cycle #1 will not need to re-apply to the Interconnection Cycle Process. Therefore, there is no Application Review Phase for Transition Cycle #1. The cycle process for Transition Cycle #1 includes three Study Phases and three Decision Points:

  1. Phase I System Impact Study and Decision Point I; and
  2. Phase II System Impact Study and Decision Point II; and
  3. Phase III System Impact Study and Decision Point III

Refer to Tariff Part VII, Subpart D, section 307 for the Transition Cycle #1 study process.

General

The Interconnection Customer (IC), has proposed a Solar generating facility located in the AEP zone — Allen County, Indiana. The installed facilities will have a total capability of 100.0 MW with 60.0 MW of this output being recognized by PJM as Capacity.

Project Information
Queue Number AG1-424
Project Name Sowers 138 kV
Developer Name Leeward Renewable Energy Development, LLC
State Indiana
County Allen
Transmission Owner AEP
MFO 100.0 MW
MWE 100.0 MW
MWC 60.0 MW
Fuel Type Solar
Basecase Study Year 2024

Point of Interconnection

AG1-424 will interconnect on the AEP transmission system at the Sowers 138 kV substation.

Summer Peak Analysis

The Queue Project was evaluated as a 100.0 MW (Capacity 60.0 MW) injection in the AEP area. Project was evaluated for compliance with applicable reliability planning criteria (PJM, NERC, NERC Regional Reliability Councils, and Transmission Owners). Potential Summer peak period network impacts are listed below:

Important to Note:

Note for Uprate Projects: Per Tariff Part VII, Subpart B, section 304 (B), if a project is an uprate (project relies on the Interconnection Facilities of a prior project) whose base project does not qualify for the expedited process, the uprate also will not qualify for the expedited process, regardless of analysis results.

Notes regarding Results displayed:

  1. Some flowgate overloads that a New Service Request contributes to, but does not contribute enough to meet cost allocation eligibility (per Manual 14A, Attachment B.3), may be reported in this Transition Sort report. These types of flowgates do not affect the classification of the New Service Request as either Expedited Process or Transition Cycle #1 because cost allocation eligibility has not been met.
  2. For projects that were determined to not meet Expedited Process eligibility and are being reprioritized to Transition Cycle #1, not all reinforcements in excess of $5,000,000 may be shown in this report. This report may only display a subset of those reinforcements determined to be in excess of $5,000,000 which would classify the project as not meeting Expedited Process Eligibility. This is not a formal System Impact Study.
Summer Peak Analysis
Area Facility Description Contingency Name Contingency Type DC|AC Initial Loading Final Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Details
ATSI AF2-321 TAP-02STRYKE 138.0 kV Ckt 1 line
960300 to 239127 ckt 1
ATSI-P1-2-TE-138-001B
CONTINGENCY 'ATSI-P1-2-TE-138-001B'
 DISCONNECT BRANCH FROM BUS 239070 TO BUS 239165 CKT 1   /*02RICHLD     138.0 - 02WAUSEO     138.0
END
Single AC 104.69 % 107.09 % 192.0 B 205.61 4.7
ATSI AF2-321 TAP-02STRYKE 138.0 kV Ckt 1 line
960300 to 239127 ckt 1
ATSI-P1-3-TE-138-022
CONTINGENCY 'ATSI-P1-3-TE-138-022'
 DISCONNECT BRANCH FROM BUS 239164 TO BUS 239165 CKT 2   /*02WAUS        69.0 - 02WAUSEO     138.0
 DISCONNECT BUS 239165                                   /*02WAUSEO     138.0
END
Single AC 98.65 % 100.83 % 192.0 B 193.6 4.49
AEP/ATSI AE2-072 TAP-05E.LEIPSIC2 138.0 kV Ckt 1 line
940840 to 242993 ckt 1
ATSI-P2-3-TE-138-033A
CONTINGENCY 'ATSI-P2-3-TE-138-033A'
 DISCONNECT BUS 238505   /*02DELTA      138.0
 DISCONNECT BUS 239165   /*02WAUSEO     138.0
 DISCONNECT BUS 239312   /*02NS-YORK    138.0
 DISCONNECT BUS 239347   /*02LEAR       138.0
 DISCONNECT BUS 239348   /*02WORTHST    138.0
 DISCONNECT BUS 240842   /*02NFF        138.0
END
Breaker AC 119.59 % 121.69 % 223.0 B 271.38 5.46
ATSI 02RICHLD-02WAUSEO 138.0 kV Ckt 1 line
239070 to 239165 ckt 1
ATSI-P2-3-TE-138-010C
CONTINGENCY 'ATSI-P2-3-TE-138-010C'
 DISCONNECT BRANCH FROM BUS 960300 TO BUS 239127 CKT 1   /*AF2-321 TAP  138.0 - 02STRYKE     138.0
 DISCONNECT BUS 239127                                   /*02STRYKE     138.0
 DISCONNECT BUS 239202                                   /*02STRYCT      13.2
 REMOVE MACHINE 1 FROM BUS 239202                        /*02STRYCT      13.2
END
Breaker AC 117.47 % 121.02 % 192.0 B 232.37 7.96
AEP 05GRBLOP-05ROB PK34 138.0 kV Ckt 1 line
243014 to 245476 ckt 1
AEP_P4_#14806_05VARNER 138_XXX
CONTINGENCY 'AEP_P4_#14806_05VARNER 138_XXX'
 OPEN BRANCH FROM BUS 247105 TO BUS 247106 CKT 2   /*05VARNER     345.0 - 05VARNER     138.0
 OPEN BRANCH FROM BUS 247106 TO BUS 944230 CKT 1   /*05VARNER     138.0 - AF1-091 TAP  138.0
END
Breaker AC 88.76 % 109.59 % 255.0 B 279.46 54.96
AEP 05ALLEN-05RPMONE 345.0 kV Ckt 1 line
243211 to 242933 ckt 1
AEP_P4_#7445_05MARYSV 765_B
CONTINGENCY 'AEP_P4_#7445_05MARYSV 765_B'
 OPEN BRANCH FROM BUS 242928 TO BUS 958430 CKT 1   /*05MARYSV     765.0 - AF2-137 TAP  765.0
 OPEN BRANCH FROM BUS 962760 TO BUS 242928 CKT 1   /*AG1-125 TAP  765.0 - 05MARYSV     765.0
END
Breaker AC 100.49 % 101.67 % 897.0 B 911.94 10.48
ATSI 02RICHLD-02WAUSEO 138.0 kV Ckt 1 line
239070 to 239165 ckt 1
ATSI-P2-2-TE-138-004
CONTINGENCY 'ATSI-P2-2-TE-138-004'
 DISCONNECT BUS 239127   /*02STRYKE     138.0
 DISCONNECT BUS 239202   /*02STRYCT      13.2
END
Bus AC 117.5 % 121.05 % 192.0 B 232.41 7.96

Light Load Analysis

At this time light load analysis not required for this project.

System Reinforcements

The table below lists all network upgrades which resolve the identified overloaded facilities in this report.

Important to Note:

Note for Uprate Projects: Per Tariff Part VII, Subpart B, section 304 (B), if a project is an uprate (project relies on the Interconnection Facilities of a prior project) whose base project does not qualify for the expedited process, the uprate also will not qualify for the expedited process, regardless of analysis results.

Notes regarding Results displayed:

  1. Some flowgate overloads that a New Service Request contributes to, but does not contribute enough to meet cost allocation eligibility (per Manual 14A, Attachment B.3), may be reported in this Transition Sort report. These types of flowgates do not affect the classification of the New Service Request as either Expedited Process or Transition Cycle #1 because cost allocation eligibility has not been met.
  2. For projects that were determined to not meet Expedited Process eligibility and are being reprioritized to Transition Cycle #1, not all reinforcements in excess of $5,000,000 may be shown in this report. This report may only display a subset of those reinforcements determined to be in excess of $5,000,000 which would classify the project as not meeting Expedited Process Eligibility. This is not a formal System Impact Study.
  3. Reinforcements previously identified by Transmission Owners for violations on lower voltage facilities are included in this report. Transmission Owner analysis will be updated as part of the Expedited Process and Transition Cycle 1 retools.
System Reinforcements
RTEP ID Title Total Cost
(TBD) Replace (1) substation conductor at Stryker. $125,600
n7546 Reconductor the Richland-Wauseon 138 kV line. $66,891,420
n7547 Reconductor the line from Stryker 138 kV substation to the new 3 breaker ring for the AF2-321 gen queue project of the Richland-Stryker 138 kV line. $7,099,053
n8395 Perform Sag Study on 10.2 miles of line with ACSR " 636 " 26/7 " GROSBEAK-Conductor to mitigate the overload. $40,800
s2685.1 s2685.1 Robison Park – Sowers 138kV line: Rebuild the 13.6 miles of wood construction with double circuit capable 138kV with one side strung. $0
n6740 Sag Study - Allen and Rpmone 345 kV line (12.25 miles). Completed, Rate B should be 1057MVA. $49,000

Attachments

Conclusion

The Transition Sort load flow retool results indicate that AG1-424 is not eligible for the Expedited Process per PJM Tariff Part VII, Subpart B, section 304 (A) will be reprioritized to Transition Cycle #1. See next steps for your project in the "Introduction" section above.