Export to CSV

AG1-308 Transition Sort Retool Results -- Reprioritized to Transition Cycle #1

v1.00 released 2023-12-14 10:51

Shawville-Philipsburg 34.5 kV

8.3 MW Capacity / 19.9 MW Energy

Introduction

In accordance with Tariff Part VII, Subpart B, section 304, PJM performed load flow analysis (Transition Sort Retool) on all AE1 through AG1 projects that have met eligibility requirements according to Tariff, Part VII, Subpart B, section 303. The purpose of this study is to determine whether a project would be classified as eligible for the Expedited Process (Fast Lane) or if it would be reprioritized to be studied as part of Transition Cycle #1 (TC1) using the criteria from the Expedited Process Eligibility section of Tariff Part VII, section 304. This is not a System Impact Study report.

Below are the results of the study, details of how the study was performed, criterion used in the evaluation of the Expedited Process vs. TC1 determination, and next steps in the interconnection process for your project.

Transition Cycle #1:

The AG1-308 project has not met the Expedited Process Eligibility requirements in Tariff Part VII, Subpart B, section 304 and will therefore be reprioritized to Transition Cycle #1. Please see "Transition Cycle #1 Rules" below.

Transition Sort Retool Study Process and Criteria:

In order to determine Expedited Process vs. Transition Cycle #1 classification, projects which met the Transition Eligibility requirements from Tariff Part VII, Subpart B, section 303 were studied on the base case model that was used for the original System Impact Study analysis. Both a summer peak and light load load flow analysis were performed. Projects that have cost allocation eligibility or are identified as the first to cause a system violation which requires the need for a Network Upgrade with a total estimated cost greater than $5 million will be reprioritized to Transition Cycle #1. All other projects will be eligible for the expedited procedures set forth in Tariff Part VII, Subpart B, section 304 (B).

Expedited Process Eligibility: OATT Tariff Part VII, section 304:

A project is not eligible for the expedited process if it has cost allocation eligibility or is identified as the first to cause, as determined according to Tariff, Part VI, section 217.3, for a Network Upgrade which has a total estimated cost of greater than $5,000,000. Such cost estimate will be based on Transmission Provider's most recently available data.

Not considered in the Transition Sorting: The cost of the Interconnection Facilities is not considered when determining a project's eligibility for the expedited process. Affected Systems upgrade costs are also not considered in the evaluation.

Transition Sort Retool Results Provided:

This report includes a list of:

  1. the overloaded flowgates (overloaded facilities + contingency pair) that the project contributes towards
  2. other interconnection projects that may also contribute to the overloaded facility, and
  3. the total estimated cost for any required Network Upgrades.

Important Notes:

Note for Uprate Projects: Per Tariff Part VII, Subpart B, section 304 (B), if a project is an uprate (project relies on the Interconnection Facilities of a prior project) whose base project does not qualify for the expedited process, the uprate also will not qualify for the expedited process, regardless of analysis results.

Notes regarding Results displayed:

  1. Some flowgate overloads that a New Service Request contributes to, but does not contribute enough to meet cost allocation eligibility (per Manual 14A, Attachment B.3), may be reported in this Transition Sort report. These types of flowgates do not affect the classification of the New Service Request as either Expedited Process or Transition Cycle #1 because cost allocation eligibility has not been met.
  2. For projects that were determined to not meet Expedited Process eligibility and are being reprioritized to Transition Cycle #1, not all reinforcements in excess of $5,000,000 may be shown in this report. This report may only display a subset of those reinforcements determined to be in excess of $5,000,000 which would classify the project as not meeting Expedited Process Eligibility. This is not a formal System Impact Study.

Next Steps for your project:

Transition Cycle #1 Rules:

Refer to Tariff Part VII, Subpart B, section 304 (C) for the Transition Cycle #1 Project Rules.

Transition Cycle #1 will start no later than one year from the Transition Start Date (July 10, 2023). Transition Cycle #1 will run simultaneously with the expedited process, however Transition Cycle #1, Phase III will not begin until all expedited process projects have been completed.

Projects that are reprioritized to Transition Cycle #1 will not need to re-apply to the Interconnection Cycle Process. Therefore, there is no Application Review Phase for Transition Cycle #1. The cycle process for Transition Cycle #1 includes three Study Phases and three Decision Points:

  1. Phase I System Impact Study and Decision Point I; and
  2. Phase II System Impact Study and Decision Point II; and
  3. Phase III System Impact Study and Decision Point III

Refer to Tariff Part VII, Subpart D, section 307 for the Transition Cycle #1 study process.

General

The Interconnection Customer (IC), has proposed a Solar generating facility located in the PENELEC zone — Clearfield County, Pennsylvania. The installed facilities will have a total capability of 19.9 MW with 8.3 MW of this output being recognized by PJM as Capacity.

Project Information
Queue Number AG1-308
Project Name Shawville-Philipsburg 34.5 kV
Developer Name Morrisdale Solar I, LLC
State Pennsylvania
County Clearfield
Transmission Owner PENELEC
MFO 19.9 MW
MWE 19.9 MW
MWC 8.3 MW
Fuel Type Solar
Basecase Study Year 2024

Point of Interconnection

The AG1-308 secondary point of interconnect request with the Penelec distribution system was via a tap on the Philipsburg #2 34.5 kV Shawville circuit #00154-22 at or near pole #SBF-30822.

 

Based on existing PJM projects AF2-121 and AE2-129 the generation capacity has exceeded any distribution conductor and equipment required ratings therefore DER at this point of interconnection is not possible.  Additional circuit DER will be required to have dedicated facilities from our substation.

 

AG1-308 will be required to interconnect with the Penelec distribution system via a new 34.5kV circuit on the #2 bus (200653) at the Philipsburg substation from a customer owned line.

 

The IC will be responsible for acquiring all easements, properties, and permits that may be required to construct the new interconnection station and the associated facilities.

 

Attachment 1 shows a one-line diagram of the proposed primary direct connection facilities for the AG1-308 generation project to connect to the Penelec distribution system. 

 

Summer Peak Analysis

The Queue Project was evaluated as a 19.9 MW (Capacity 8.3 MW) injection in the PENELEC area. Project was evaluated for compliance with applicable reliability planning criteria (PJM, NERC, NERC Regional Reliability Councils, and Transmission Owners). Potential Summer peak period network impacts are listed below:

Important to Note:

Note for Uprate Projects: Per Tariff Part VII, Subpart B, section 304 (B), if a project is an uprate (project relies on the Interconnection Facilities of a prior project) whose base project does not qualify for the expedited process, the uprate also will not qualify for the expedited process, regardless of analysis results.

Notes regarding Results displayed:

  1. Some flowgate overloads that a New Service Request contributes to, but does not contribute enough to meet cost allocation eligibility (per Manual 14A, Attachment B.3), may be reported in this Transition Sort report. These types of flowgates do not affect the classification of the New Service Request as either Expedited Process or Transition Cycle #1 because cost allocation eligibility has not been met.
  2. For projects that were determined to not meet Expedited Process eligibility and are being reprioritized to Transition Cycle #1, not all reinforcements in excess of $5,000,000 may be shown in this report. This report may only display a subset of those reinforcements determined to be in excess of $5,000,000 which would classify the project as not meeting Expedited Process Eligibility. This is not a formal System Impact Study.
Summer Peak Analysis
Area Facility Description Contingency Name Contingency Type DC|AC Initial Loading Final Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Details
PENELEC 26SHAWVL 2-26SHAWVL 2 115.0/230.0 kV Ckt 2A transformer
999332 to 200726 ckt 2A
PN-P2-3-PN-230-21DT
CONTINGENCY 'PN-P2-3-PN-230-21DT'
 DISCONNECT BRANCH FROM BUS 200665 TO BUS 200710 CKT 1          /*26SHAWVL 3    22.0 - 26SHAWVL 1   230.0
 DISCONNECT BRANCH FROM BUS 200710 TO BUS 200714 TO BUS 200715 CKT 1A /*26SHAWVL 1   230.0 - 26SHAWVL 1   115.0 - 26SHAWVL 1    18.0
 DISCONNECT BRANCH FROM BUS 200710 TO BUS 200726 CKT ZB         /*26SHAWVL 1   230.0 - 26SHAWVL 2   230.0
 DISCONNECT BRANCH FROM BUS 200710 TO BUS 944320 CKT 1          /*26SHAWVL 1   230.0 - AF1-100 TAP  230.0
END
Breaker AC 172.35 % 176.63 % 149.0 B 263.17 6.52
PENELEC 26SHAWVL 2-26SHAWVL 2 115.0/230.0 kV Ckt 2A transformer
999332 to 200726 ckt 2A
PN-P2-3-PN-115-59A
CONTINGENCY 'PN-P2-3-PN-115-59A'
 DISCONNECT BRANCH FROM BUS 200597 TO BUS 200713 CKT 1          /*26ROCK MT     34.5 - 26ROCKTON    115.0
 DISCONNECT BRANCH FROM BUS 200607 TO BUS 200712 CKT 3          /*26DUBOIS 2    34.5 - 26DUBOIS     115.0
 DISCONNECT BRANCH FROM BUS 200710 TO BUS 200714 TO BUS 200715 CKT 1A /*26SHAWVL 1   230.0 - 26SHAWVL 1   115.0 - 26SHAWVL 1    18.0
 DISCONNECT BRANCH FROM BUS 200712 TO BUS 200713 CKT 1          /*26DUBOIS     115.0 - 26ROCKTON    115.0
 DISCONNECT BRANCH FROM BUS 200713 TO BUS 200714 CKT 1          /*26ROCKTON    115.0 - 26SHAWVL 1   115.0
 DISCONNECT BRANCH FROM BUS 200714 TO BUS 200555 TO BUS 200913 CKT 14 /*26SHAWVL 1   115.0 - 26SHAW.NO1    34.5 - 26SHAW-D       4.2
 DISCONNECT BRANCH FROM BUS 200714 TO BUS 200555 TO BUS 200913 CKT 14 /*26SHAWVL 1   115.0 - 26SHAW.NO1    34.5 - 26SHAW-D       4.2
 DISCONNECT BRANCH FROM BUS 200714 TO BUS 200715 CKT 1B         /*26SHAWVL 1   115.0 - 26SHAWVL 1    18.0
 DISCONNECT BRANCH FROM BUS 200714 TO BUS 200722 CKT 2B         /*26SHAWVL 1   115.0 - 26SHAWVL 2    18.0
 DISCONNECT BRANCH FROM BUS 200714 TO BUS 200727 CKT ZB         /*26SHAWVL 1   115.0 - 26SHAW. 2    115.0
 DISCONNECT BRANCH FROM BUS 200714 TO BUS 200872 CKT 1          /*26SHAWVL 1   115.0 - 26BIOEN TP   115.0
END
Breaker AC 140.63 % 147.07 % 149.0 B 219.13 10.35
PENELEC 26SHAWVL 2-26SHAWVL 2 115.0/230.0 kV Ckt 2A transformer
999332 to 200726 ckt 2A
PN-P2-3-PN-115-73-11
CONTINGENCY 'PN-P2-3-PN-115-73-11'
 DISCONNECT BRANCH FROM BUS 200527 TO BUS 200528 CKT 1   /*26TYRONE N   115.0 - 26WESTFALL   115.0
 DISCONNECT BRANCH FROM BUS 200527 TO BUS 200543 CKT 2   /*26TYRONE N   115.0 - 26TYRNE #2    46.0
 DISCONNECT BRANCH FROM BUS 200527 TO BUS 200544 CKT 1   /*26TYRONE N   115.0 - 26TYRNE #1    46.0
 DISCONNECT BRANCH FROM BUS 200527 TO BUS 200904 CKT 1   /*26TYRONE N   115.0 - 26EAGL VAL   115.0
 DISCONNECT BRANCH FROM BUS 200528 TO BUS 200545 CKT 3   /*26WESTFALL   115.0 - 26WESTFALL    46.0
END
Breaker AC 133.67 % 137.59 % 149.0 B 205.0 6.72
PENELEC 26SHAWVL 1-26SHAWVL 1 115.0/230.0 kV Ckt 1A transformer
999333 to 200710 ckt 1A
PN-P2-3-PN-230-21AT
CONTINGENCY 'PN-P2-3-PN-230-21AT'
 DISCONNECT BRANCH FROM BUS 200666 TO BUS 200726 CKT 1          /*26SHAWVL 4    22.0 - 26SHAWVL 2   230.0
 DISCONNECT BRANCH FROM BUS 200710 TO BUS 200726 CKT ZB         /*26SHAWVL 1   230.0 - 26SHAWVL 2   230.0
 DISCONNECT BRANCH FROM BUS 200726 TO BUS 200727 TO BUS 200722 CKT 2A /*26SHAWVL 2   230.0 - 26SHAW. 2    115.0 - 26SHAWVL 2    18.0
 DISCONNECT BRANCH FROM BUS 200726 TO BUS 235175 CKT 1          /*26SHAWVL 2   230.0 - 01ELKO       230.0
 DISCONNECT BRANCH FROM BUS 200726 TO BUS 235248 CKT 1          /*26SHAWVL 2   230.0 - 01SHINGL     230.0
END
Breaker AC 111.14 % 114.21 % 201.0 B 229.56 6.32
PENELEC 26SHAWVL 1-26SHAWVL 1 115.0/230.0 kV Ckt 1A transformer
999333 to 200710 ckt 1A
PN-P2-3-PN-115-73-11
CONTINGENCY 'PN-P2-3-PN-115-73-11'
 DISCONNECT BRANCH FROM BUS 200527 TO BUS 200528 CKT 1   /*26TYRONE N   115.0 - 26WESTFALL   115.0
 DISCONNECT BRANCH FROM BUS 200527 TO BUS 200543 CKT 2   /*26TYRONE N   115.0 - 26TYRNE #2    46.0
 DISCONNECT BRANCH FROM BUS 200527 TO BUS 200544 CKT 1   /*26TYRONE N   115.0 - 26TYRNE #1    46.0
 DISCONNECT BRANCH FROM BUS 200527 TO BUS 200904 CKT 1   /*26TYRONE N   115.0 - 26EAGL VAL   115.0
 DISCONNECT BRANCH FROM BUS 200528 TO BUS 200545 CKT 3   /*26WESTFALL   115.0 - 26WESTFALL    46.0
END
Breaker AC 97.44 % 100.29 % 201.0 B 201.58 6.54
PENELEC 26SHAWVL 1-26SHAWVL 1 115.0/230.0 kV Ckt 1A transformer
999333 to 200710 ckt 1A
PN-P2-3-PN-115-73-15
CONTINGENCY 'PN-P2-3-PN-115-73-15'
 DISCONNECT BRANCH FROM BUS 200527 TO BUS 200528 CKT 1   /*26TYRONE N   115.0 - 26WESTFALL   115.0
 DISCONNECT BRANCH FROM BUS 200527 TO BUS 200543 CKT 2   /*26TYRONE N   115.0 - 26TYRNE #2    46.0
 DISCONNECT BRANCH FROM BUS 200527 TO BUS 200544 CKT 1   /*26TYRONE N   115.0 - 26TYRNE #1    46.0
 DISCONNECT BRANCH FROM BUS 200527 TO BUS 200904 CKT 1   /*26TYRONE N   115.0 - 26EAGL VAL   115.0
 DISCONNECT BRANCH FROM BUS 200528 TO BUS 200545 CKT 5   /*26WESTFALL   115.0 - 26WESTFALL    46.0
END
Breaker AC 97.44 % 100.29 % 201.0 B 201.57 6.54
PENELEC 26SHAWVL 1-26SHAWVL 1 115.0/230.0 kV Ckt 1A transformer
999333 to 200710 ckt 1A
PN-P2_3-PN-115-0406-C
CONTINGENCY 'PN-P2_3-PN-115-0406-C'
 OPEN BRANCH FROM BUS 200527 TO BUS 200543 CKT 2   /*26TYRONE N   115.0 - 26TYRNE #2    46.0
 OPEN BRANCH FROM BUS 200527 TO BUS 200904 CKT 1   /*26TYRONE N   115.0 - 26EAGL VAL   115.0
END
Breaker AC 97.24 % 100.09 % 201.0 B 201.18 6.54
PENELEC 26SHAWVL 1-26SHAWVL 1 115.0/230.0 kV Ckt 1A transformer
999333 to 200710 ckt 1A
PN-P2_3-PN-115-0406-B
CONTINGENCY 'PN-P2_3-PN-115-0406-B'
 OPEN BRANCH FROM BUS 200527 TO BUS 200544 CKT 1   /*26TYRONE N   115.0 - 26TYRNE #1    46.0
 OPEN BRANCH FROM BUS 200527 TO BUS 200904 CKT 1   /*26TYRONE N   115.0 - 26EAGL VAL   115.0
END
Breaker AC 97.18 % 100.03 % 201.0 B 201.07 6.54
PENELEC 26SHAWVL 1-26ROCKTON 115.0 kV Ckt 1 line
200714 to 200713 ckt 1
AP-P2-3-WP-230-446T
CONTINGENCY 'AP-P2-3-WP-230-446T'
 DISCONNECT BRANCH FROM BUS 200726 TO BUS 235175 CKT 1    /*26SHAWVL 2   230.0 - 01ELKO       230.0
 DISCONNECT BRANCH FROM BUS 235158 TO BUS 235175 CKT 1    /*01CARB       230.0 - 01ELKO       230.0
 DISCONNECT BRANCH FROM BUS 235175 TO BUS 235236 CKT 1    /*01ELKO       230.0 - 01QUEHAN     230.0
 DISCONNECT BRANCH FROM BUS 235220 TO BUS 235236 CKT 1    /*01MOSHAN     230.0 - 01QUEHAN     230.0
 DISCONNECT BRANCH FROM BUS 235236 TO BUS 236732 CKT 81   /*01QUEHAN     230.0 - 01QUEHANNA    46.0
 OPEN BUS 235158                                          /*01CARB       230.0
END
Breaker AC 99.84 % 101.19 % 190.0 B 192.26 2.67
PENELEC 26SHAWVL 1-26ROCKTON 115.0 kV Ckt 1 line
200714 to 200713 ckt 1
AP-P2-3-WP-230-443T *
CONTINGENCY 'AP-P2-3-WP-230-443T *'
 DISCONNECT BRANCH FROM BUS 200726 TO BUS 235175 CKT 1   /*26SHAWVL 2   230.0 - 01ELKO       230.0
 DISCONNECT BRANCH FROM BUS 235175 TO BUS 235236 CKT 1   /*01ELKO       230.0 - 01QUEHAN     230.0
 DISCONNECT BUS 235158                                   /*01CARB       230.0
END
Breaker AC 99.76 % 101.11 % 190.0 B 192.11 2.67
PENELEC 26CONEMAGH-CONEM-GH 230.0/500.0 kV Ckt 3 transformer
200912 to 200005 ckt 3
PN-P2_3-PN-230-0252-A
CONTINGENCY 'PN-P2_3-PN-230-0252-A'
 OPEN BRANCH FROM BUS 200795 TO BUS 200739 CKT 2   /*26SHELOCTA   230.0 - 26SHELOCTA   115.0
 OPEN BRANCH FROM BUS 200795 TO BUS 200810 CKT 1   /*26SHELOCTA   230.0 - 26KEYSTONE   230.0
END
Breaker AC 99.9 % 100.2 % 1066.0 B 1068.16 4.01
PENELEC 26CONEMAGH-CONEM-GH 230.0/500.0 kV Ckt 3 transformer
200912 to 200005 ckt 3
PN-P2_3-PN-230-0252-C
CONTINGENCY 'PN-P2_3-PN-230-0252-C'
 OPEN BRANCH FROM BUS 200795 TO BUS 200739 CKT 2   /*26SHELOCTA   230.0 - 26SHELOCTA   115.0
 OPEN BRANCH FROM BUS 200795 TO BUS 200767 CKT 1   /*26SHELOCTA   230.0 - 26HOMER CT   230.0
END
Breaker AC 99.9 % 100.2 % 1066.0 B 1068.16 4.01
PENELEC 26CONEMAGH-CONEM-GH 230.0/500.0 kV Ckt 3 transformer
200912 to 200005 ckt 3
PN-P2_3-PN-230-0252-B
CONTINGENCY 'PN-P2_3-PN-230-0252-B'
 OPEN BRANCH FROM BUS 200795 TO BUS 200767 CKT 1   /*26SHELOCTA   230.0 - 26HOMER CT   230.0
 OPEN BRANCH FROM BUS 200795 TO BUS 200810 CKT 1   /*26SHELOCTA   230.0 - 26KEYSTONE   230.0
END
Breaker AC 99.9 % 100.2 % 1066.0 B 1068.16 4.01
PENELEC 26ROCKTON-26DUBOIS 115.0 kV Ckt 1 line
200713 to 200712 ckt 1
AP-P2-3-WP-230-446T
CONTINGENCY 'AP-P2-3-WP-230-446T'
 DISCONNECT BRANCH FROM BUS 200726 TO BUS 235175 CKT 1    /*26SHAWVL 2   230.0 - 01ELKO       230.0
 DISCONNECT BRANCH FROM BUS 235158 TO BUS 235175 CKT 1    /*01CARB       230.0 - 01ELKO       230.0
 DISCONNECT BRANCH FROM BUS 235175 TO BUS 235236 CKT 1    /*01ELKO       230.0 - 01QUEHAN     230.0
 DISCONNECT BRANCH FROM BUS 235220 TO BUS 235236 CKT 1    /*01MOSHAN     230.0 - 01QUEHAN     230.0
 DISCONNECT BRANCH FROM BUS 235236 TO BUS 236732 CKT 81   /*01QUEHAN     230.0 - 01QUEHANNA    46.0
 OPEN BUS 235158                                          /*01CARB       230.0
END
Breaker AC 98.83 % 100.17 % 190.0 B 190.33 2.67
PENELEC 26ROCKTON-26DUBOIS 115.0 kV Ckt 1 line
200713 to 200712 ckt 1
AP-P2-3-WP-230-443T *
CONTINGENCY 'AP-P2-3-WP-230-443T *'
 DISCONNECT BRANCH FROM BUS 200726 TO BUS 235175 CKT 1   /*26SHAWVL 2   230.0 - 01ELKO       230.0
 DISCONNECT BRANCH FROM BUS 235175 TO BUS 235236 CKT 1   /*01ELKO       230.0 - 01QUEHAN     230.0
 DISCONNECT BUS 235158                                   /*01CARB       230.0
END
Breaker AC 98.75 % 100.1 % 190.0 B 190.18 2.67
PENELEC 26SHAWVL 2-26SHAWVL 2 115.0/230.0 kV Ckt 2A transformer
999332 to 200726 ckt 2A
PN-P2-2-PN-230-013T
CONTINGENCY 'PN-P2-2-PN-230-013T'
 DISCONNECT BRANCH FROM BUS 200710 TO BUS 200665 CKT 1    /*26SHAWVL 1   230.0 - 26SHAWVL 3    22.0
 DISCONNECT BRANCH FROM BUS 200710 TO BUS 200726 CKT ZB   /*26SHAWVL 1   230.0 - 26SHAWVL 2   230.0
 DISCONNECT BRANCH FROM BUS 200710 TO BUS 944320 CKT 1    /*26SHAWVL 1   230.0 - AF1-100 TAP  230.0
END
Bus AC 172.96 % 177.2 % 149.0 B 264.03 6.52
PENELEC 26SHAWVL 2-26SHAWVL 2 115.0/230.0 kV Ckt 2A transformer
999332 to 200726 ckt 2A
PN-P2-2-PN-115-062T
CONTINGENCY 'PN-P2-2-PN-115-062T'
 DISCONNECT BRANCH FROM BUS 200555 TO BUS 200714 TO BUS 200913 CKT 14 /*26SHAW.NO1    34.5 - 26SHAWVL 1   115.0 - 26SHAW-D       4.2
 DISCONNECT BRANCH FROM BUS 200710 TO BUS 200714 TO BUS 200715 CKT 1A /*26SHAWVL 1   230.0 - 26SHAWVL 1   115.0 - 26SHAWVL 1    18.0
 DISCONNECT BRANCH FROM BUS 200714 TO BUS 200713 CKT 1          /*26SHAWVL 1   115.0 - 26ROCKTON    115.0
 DISCONNECT BRANCH FROM BUS 200714 TO BUS 200715 CKT 1B         /*26SHAWVL 1   115.0 - 26SHAWVL 1    18.0
 DISCONNECT BRANCH FROM BUS 200714 TO BUS 200722 CKT 2B         /*26SHAWVL 1   115.0 - 26SHAWVL 2    18.0
 DISCONNECT BRANCH FROM BUS 200714 TO BUS 200727 CKT ZB         /*26SHAWVL 1   115.0 - 26SHAW. 2    115.0
 DISCONNECT BRANCH FROM BUS 200714 TO BUS 200872 CKT 1          /*26SHAWVL 1   115.0 - 26BIOEN TP   115.0
 REDUCE BUS 200714 SHUNT BY 100 PERCENT                         /*26SHAWVL 1   115.0
END
Bus AC 141.27 % 147.71 % 149.0 B 220.09 10.35
PENELEC 26SHAWVL 1-26SHAWVL 1 115.0/230.0 kV Ckt 1A transformer
999333 to 200710 ckt 1A
PN-P2-2-PN-230-014T
CONTINGENCY 'PN-P2-2-PN-230-014T'
 DISCONNECT BRANCH FROM BUS 200726 TO BUS 200666 CKT 1    /*26SHAWVL 2   230.0 - 26SHAWVL 4    22.0
 DISCONNECT BRANCH FROM BUS 200726 TO BUS 200710 CKT ZB   /*26SHAWVL 2   230.0 - 26SHAWVL 1   230.0
 DISCONNECT BRANCH FROM BUS 200726 TO BUS 235175 CKT 1    /*26SHAWVL 2   230.0 - 01ELKO       230.0
 DISCONNECT BRANCH FROM BUS 200726 TO BUS 235248 CKT 1    /*26SHAWVL 2   230.0 - 01SHINGL     230.0
END
Bus AC 111.54 % 114.59 % 201.0 B 230.32 6.32
PENELEC 26SHAWVL 1-26ROCKTON 115.0 kV Ckt 1 line
200714 to 200713 ckt 1
AP-P2-2-WP-230-001T
CONTINGENCY 'AP-P2-2-WP-230-001T'
 DISCONNECT BRANCH FROM BUS 235175 TO BUS 200726 CKT 1   /*01ELKO       230.0 - 26SHAWVL 2   230.0
 DISCONNECT BRANCH FROM BUS 235175 TO BUS 235158 CKT 1   /*01ELKO       230.0 - 01CARB       230.0
 DISCONNECT BRANCH FROM BUS 235175 TO BUS 235236 CKT 1   /*01ELKO       230.0 - 01QUEHAN     230.0
END
Bus AC 99.72 % 101.06 % 190.0 B 192.02 2.67
PENELEC 26ROCKTON-26DUBOIS 115.0 kV Ckt 1 line
200713 to 200712 ckt 1
AP-P2-2-WP-230-001T
CONTINGENCY 'AP-P2-2-WP-230-001T'
 DISCONNECT BRANCH FROM BUS 235175 TO BUS 200726 CKT 1   /*01ELKO       230.0 - 26SHAWVL 2   230.0
 DISCONNECT BRANCH FROM BUS 235175 TO BUS 235158 CKT 1   /*01ELKO       230.0 - 01CARB       230.0
 DISCONNECT BRANCH FROM BUS 235175 TO BUS 235236 CKT 1   /*01ELKO       230.0 - 01QUEHAN     230.0
END
Bus AC 98.7 % 100.05 % 190.0 B 190.09 2.67

Light Load Analysis

At this time light load analysis not required for this project.

System Reinforcements

The table below lists all network upgrades which resolve the identified overloaded facilities in this report.

Important to Note:

Note for Uprate Projects: Per Tariff Part VII, Subpart B, section 304 (B), if a project is an uprate (project relies on the Interconnection Facilities of a prior project) whose base project does not qualify for the expedited process, the uprate also will not qualify for the expedited process, regardless of analysis results.

Notes regarding Results displayed:

  1. Some flowgate overloads that a New Service Request contributes to, but does not contribute enough to meet cost allocation eligibility (per Manual 14A, Attachment B.3), may be reported in this Transition Sort report. These types of flowgates do not affect the classification of the New Service Request as either Expedited Process or Transition Cycle #1 because cost allocation eligibility has not been met.
  2. For projects that were determined to not meet Expedited Process eligibility and are being reprioritized to Transition Cycle #1, not all reinforcements in excess of $5,000,000 may be shown in this report. This report may only display a subset of those reinforcements determined to be in excess of $5,000,000 which would classify the project as not meeting Expedited Process Eligibility. This is not a formal System Impact Study.
  3. Reinforcements previously identified by Transmission Owners for violations on lower voltage facilities are included in this report. Transmission Owner analysis will be updated as part of the Expedited Process and Transition Cycle 1 retools.
System Reinforcements
RTEP ID Title Total Cost
(TBD) FAC-008 Rating Increase (Scheduled 6/2024) $0
n7652 Replace line trap at Shawville. $200,000
n7654 Replace Shawville 230/115-17.2 kV transformer 1A with a larger unit. $5,600,000
b3708 Install a new 230/115 kV transformer and associated facilities at Shawville. (Projected ISD 6/1/2026) $8,775,000
n8328 Shelocta 230kV: Convert station to Double Breaker-Double Bus $10,354,231

Attachments

Conclusion

The Transition Sort load flow retool results indicate that AG1-308 is not eligible for the Expedited Process per PJM Tariff Part VII, Subpart B, section 304 (A) will be reprioritized to Transition Cycle #1. See next steps for your project in the "Introduction" section above.