Export to CSV

AG1-169 Transition Sort Retool Results -- Reprioritized to Transition Cycle #1

v1.00 released 2023-12-14 10:42

Lone Pine 115 kV

12.0 MW Capacity / 20.0 MW Energy

Introduction

In accordance with Tariff Part VII, Subpart B, section 304, PJM performed load flow analysis (Transition Sort Retool) on all AE1 through AG1 projects that have met eligibility requirements according to Tariff, Part VII, Subpart B, section 303. The purpose of this study is to determine whether a project would be classified as eligible for the Expedited Process (Fast Lane) or if it would be reprioritized to be studied as part of Transition Cycle #1 (TC1) using the criteria from the Expedited Process Eligibility section of Tariff Part VII, section 304. This is not a System Impact Study report.

Below are the results of the study, details of how the study was performed, criterion used in the evaluation of the Expedited Process vs. TC1 determination, and next steps in the interconnection process for your project.

Transition Cycle #1:

The AG1-169 project has not met the Expedited Process Eligibility requirements in Tariff Part VII, Subpart B, section 304 and will therefore be reprioritized to Transition Cycle #1. Please see "Transition Cycle #1 Rules" below.

Transition Sort Retool Study Process and Criteria:

In order to determine Expedited Process vs. Transition Cycle #1 classification, projects which met the Transition Eligibility requirements from Tariff Part VII, Subpart B, section 303 were studied on the base case model that was used for the original System Impact Study analysis. Both a summer peak and light load load flow analysis were performed. Projects that have cost allocation eligibility or are identified as the first to cause a system violation which requires the need for a Network Upgrade with a total estimated cost greater than $5 million will be reprioritized to Transition Cycle #1. All other projects will be eligible for the expedited procedures set forth in Tariff Part VII, Subpart B, section 304 (B).

Expedited Process Eligibility: OATT Tariff Part VII, section 304:

A project is not eligible for the expedited process if it has cost allocation eligibility or is identified as the first to cause, as determined according to Tariff, Part VI, section 217.3, for a Network Upgrade which has a total estimated cost of greater than $5,000,000. Such cost estimate will be based on Transmission Provider's most recently available data.

Not considered in the Transition Sorting: The cost of the Interconnection Facilities is not considered when determining a project's eligibility for the expedited process. Affected Systems upgrade costs are also not considered in the evaluation.

Transition Sort Retool Results Provided:

This report includes a list of:

  1. the overloaded flowgates (overloaded facilities + contingency pair) that the project contributes towards
  2. other interconnection projects that may also contribute to the overloaded facility, and
  3. the total estimated cost for any required Network Upgrades.

Important Notes:

Note for Uprate Projects: Per Tariff Part VII, Subpart B, section 304 (B), if a project is an uprate (project relies on the Interconnection Facilities of a prior project) whose base project does not qualify for the expedited process, the uprate also will not qualify for the expedited process, regardless of analysis results.

Notes regarding Results displayed:

  1. Some flowgate overloads that a New Service Request contributes to, but does not contribute enough to meet cost allocation eligibility (per Manual 14A, Attachment B.3), may be reported in this Transition Sort report. These types of flowgates do not affect the classification of the New Service Request as either Expedited Process or Transition Cycle #1 because cost allocation eligibility has not been met.
  2. For projects that were determined to not meet Expedited Process eligibility and are being reprioritized to Transition Cycle #1, not all reinforcements in excess of $5,000,000 may be shown in this report. This report may only display a subset of those reinforcements determined to be in excess of $5,000,000 which would classify the project as not meeting Expedited Process Eligibility. This is not a formal System Impact Study.

Next Steps for your project:

Transition Cycle #1 Rules:

Refer to Tariff Part VII, Subpart B, section 304 (C) for the Transition Cycle #1 Project Rules.

Transition Cycle #1 will start no later than one year from the Transition Start Date (July 10, 2023). Transition Cycle #1 will run simultaneously with the expedited process, however Transition Cycle #1, Phase III will not begin until all expedited process projects have been completed.

Projects that are reprioritized to Transition Cycle #1 will not need to re-apply to the Interconnection Cycle Process. Therefore, there is no Application Review Phase for Transition Cycle #1. The cycle process for Transition Cycle #1 includes three Study Phases and three Decision Points:

  1. Phase I System Impact Study and Decision Point I; and
  2. Phase II System Impact Study and Decision Point II; and
  3. Phase III System Impact Study and Decision Point III

Refer to Tariff Part VII, Subpart D, section 307 for the Transition Cycle #1 study process.

General

The Interconnection Customer (IC), has proposed a Solar generating facility located in the Dominion zone — Nottoway County, Virginia. The installed facilities will have a total capability of 20.0 MW with 12.0 MW of this output being recognized by PJM as Capacity.

Project Information
Queue Number AG1-169
Project Name Lone Pine 115 kV
Developer Name NW-Rocky Ford LLC
State Virginia
County Nottoway
Transmission Owner Dominion
MFO 20.0 MW
MWE 20.0 MW
MWC 12.0 MW
Fuel Type Solar
Basecase Study Year 2024

Point of Interconnection

AG1-169 "Lone Pine 115 kV" will interconnect with the Dominion transmission system at Lone Pine substation, sharing the POI and Attachment Facilities as AG1-166.  

Summer Peak Analysis

The Queue Project was evaluated as a 20.0 MW (Capacity 12.0 MW) injection in the Dominion area. Project was evaluated for compliance with applicable reliability planning criteria (PJM, NERC, NERC Regional Reliability Councils, and Transmission Owners). Potential Summer peak period network impacts are listed below:

Important to Note:

Note for Uprate Projects: Per Tariff Part VII, Subpart B, section 304 (B), if a project is an uprate (project relies on the Interconnection Facilities of a prior project) whose base project does not qualify for the expedited process, the uprate also will not qualify for the expedited process, regardless of analysis results.

Notes regarding Results displayed:

  1. Some flowgate overloads that a New Service Request contributes to, but does not contribute enough to meet cost allocation eligibility (per Manual 14A, Attachment B.3), may be reported in this Transition Sort report. These types of flowgates do not affect the classification of the New Service Request as either Expedited Process or Transition Cycle #1 because cost allocation eligibility has not been met.
  2. For projects that were determined to not meet Expedited Process eligibility and are being reprioritized to Transition Cycle #1, not all reinforcements in excess of $5,000,000 may be shown in this report. This report may only display a subset of those reinforcements determined to be in excess of $5,000,000 which would classify the project as not meeting Expedited Process Eligibility. This is not a formal System Impact Study.
Summer Peak Analysis
Area Facility Description Contingency Name Contingency Type DC|AC Initial Loading Final Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Details
DVP 3FARMVIL-6FARMVIL 115.0/230.0 kV Ckt 2 transformer
314691 to 314692 ckt 2
DVP_P1-2: LN 235-A
CONTINGENCY 'DVP_P1-2: LN 235-A'
 OPEN BRANCH FROM BUS 313802 TO BUS 314268 CKT 1   /*6PRINCE EDW  230.0 - 6BRIERY      230.0
 OPEN BRANCH FROM BUS 313802 TO BUS 314692 CKT 1   /*6PRINCE EDW  230.0 - 6FARMVIL     230.0
 OPEN BRANCH FROM BUS 314268 TO BUS 934620 CKT 1   /*6BRIERY      230.0 - AD1-088 TAP  230.0
 OPEN BRANCH FROM BUS 314691 TO BUS 314692 CKT 1   /*3FARMVIL     115.0 - 6FARMVIL     230.0
 OPEN BRANCH FROM BUS 962490 TO BUS 934620 CKT 1   /*AG1-098 TAP  230.0 - AD1-088 TAP  230.0
 OPEN BUS 313802                                   /*6PRINCE EDW  230.0
 OPEN BUS 314268                                   /*6BRIERY      230.0
 OPEN BUS 934620                                   /*AD1-088 TAP  230.0
 OPEN BUS 934621                                   /*AD1-088 MAIN 230.0
 OPEN BUS 934622                                   /*AD1-088 COL1  34.5
 OPEN BUS 934623                                   /*AD1-088 TER   13.8
 OPEN BUS 934624                                   /*AD1-088 COL2  34.5
 OPEN BUS 934625                                   /*AD1-088 C      0.7
 OPEN BUS 934626                                   /*AD1-088 E      0.7
END
Single AC 149.63 % 152.6 % 182.64 B 278.72 5.52
DVP 3FARMVIL-6FARMVIL 115.0/230.0 kV Ckt 2 transformer
314691 to 314692 ckt 2
DVP_P1-2: LN 1045
CONTINGENCY 'DVP_P1-2: LN 1045'
 OPEN BRANCH FROM BUS 313898 TO BUS 314267 CKT 1   /*3BUTCHER CRK 115.0 - 3CHASCTY2    115.0
END
Single AC 104.16 % 107.31 % 182.64 B 195.99 5.76
DVP 3FLAT CREEK-3MORAN 115.0 kV Ckt 1 line
313755 to 314707 ckt 1
DVP_P1-2: LN 1045
CONTINGENCY 'DVP_P1-2: LN 1045'
 OPEN BRANCH FROM BUS 313898 TO BUS 314267 CKT 1   /*3BUTCHER CRK 115.0 - 3CHASCTY2    115.0
END
Single AC 122.77 % 128.46 % 203.98 B 262.03 12.0
DVP 3MORAN-3FARMVIL 115.0 kV Ckt 1 line
314707 to 314691 ckt 1
DVP_P1-2: LN 1045
CONTINGENCY 'DVP_P1-2: LN 1045'
 OPEN BRANCH FROM BUS 313898 TO BUS 314267 CKT 1   /*3BUTCHER CRK 115.0 - 3CHASCTY2    115.0
END
Single AC 119.54 % 125.23 % 203.98 B 255.44 12.0
DVP 3FLAT CREEK-3MORAN 115.0 kV Ckt 1 line
313755 to 314707 ckt 1
DVP_P1-2: LN 98-A
CONTINGENCY 'DVP_P1-2: LN 98-A'
 OPEN BRANCH FROM BUS 313898 TO BUS 936260 CKT 1   /*3BUTCHER CRK 115.0 - AD2-033 TAP  115.0
END
Single AC 97.35 % 103.09 % 203.98 B 210.28 12.0
DVP 3FARMVIL-6FARMVIL 115.0/230.0 kV Ckt 2 transformer
314691 to 314692 ckt 2
DVP_P4-6: CHASE C T342
CONTINGENCY 'DVP_P4-6: CHASE C T342'
 OPEN BUS 313527   /*AB2-043 C      0.6
 OPEN BUS 313528   /*AB2-043 COL   34.5
 OPEN BUS 313529   /*3BLUE STONE  115.0
 OPEN BUS 314267   /*3CHASCTY2    115.0
 OPEN BUS 314518   /*3CHASC_1     115.0
 OPEN BUS 314681   /*3CHASCTY     115.0
 OPEN BUS 924022   /*AB2-043 E O1   0.6
END
Breaker DC 234.77 % 240.07 % 208.7 C 501.04 11.07
DVP 3FARMVIL-6FARMVIL 115.0/230.0 kV Ckt 1 transformer
314691 to 314692 ckt 1
DVP_P4-6: CHASE C T342
CONTINGENCY 'DVP_P4-6: CHASE C T342'
 OPEN BUS 313527   /*AB2-043 C      0.6
 OPEN BUS 313528   /*AB2-043 COL   34.5
 OPEN BUS 313529   /*3BLUE STONE  115.0
 OPEN BUS 314267   /*3CHASCTY2    115.0
 OPEN BUS 314518   /*3CHASC_1     115.0
 OPEN BUS 314681   /*3CHASCTY     115.0
 OPEN BUS 924022   /*AB2-043 E O1   0.6
END
Breaker DC 178.24 % 182.27 % 221.4 C 403.54 8.92
DVP 3FARMVIL-6FARMVIL 115.0/230.0 kV Ckt 1 transformer
314691 to 314692 ckt 1
DVP_P4-2: 29822
CONTINGENCY 'DVP_P4-2: 29822'
 OPEN BRANCH FROM BUS 313867 TO BUS 314747 CKT 1   /*6BREMODIST   230.0 - 6BREMO       230.0
 OPEN BRANCH FROM BUS 313868 TO BUS 314747 CKT 1   /*6CARTERV     230.0 - 6BREMO       230.0
 OPEN BRANCH FROM BUS 314326 TO BUS 314747 CKT 1   /*6BEARGRDN    230.0 - 6BREMO       230.0
 OPEN BRANCH FROM BUS 314326 TO BUS 314747 CKT 2   /*6BEARGRDN    230.0 - 6BREMO       230.0
 OPEN BRANCH FROM BUS 314326 TO BUS 315191 CKT 1   /*6BEARGRDN    230.0 - 1BEARGRDN G1  18.0
 OPEN BRANCH FROM BUS 314326 TO BUS 315192 CKT 1   /*6BEARGRDN    230.0 - 1BEARGRDN G2  18.0
 OPEN BRANCH FROM BUS 314326 TO BUS 315193 CKT 1   /*6BEARGRDN    230.0 - 1BEARGRDN S1  22.0
 OPEN BRANCH FROM BUS 314677 TO BUS 314692 CKT 1   /*6BUCKING     230.0 - 6FARMVIL     230.0
 OPEN BRANCH FROM BUS 314677 TO BUS 314747 CKT 1   /*6BUCKING     230.0 - 6BREMO       230.0
 OPEN BRANCH FROM BUS 314691 TO BUS 314692 CKT 2   /*3FARMVIL     115.0 - 6FARMVIL     230.0
 OPEN BRANCH FROM BUS 314744 TO BUS 314747 CKT 1   /*3BREMO       115.0 - 6BREMO       230.0
 OPEN BUS 314326                                   /*6BEARGRDN    230.0
 OPEN BUS 314677                                   /*6BUCKING     230.0
 OPEN BUS 314747                                   /*6BREMO       230.0
 OPEN BUS 315191                                   /*1BEARGRDN G1  18.0
 OPEN BUS 315192                                   /*1BEARGRDN G2  18.0
 OPEN BUS 315193                                   /*1BEARGRDN S1  22.0
 OPEN BUS 924032                                   /*AB2-045 E    230.0
END
Breaker AC 145.84 % 149.25 % 221.4 C 330.44 8.25
DVP 6FARMVIL-6BUCKING 230.0 kV Ckt 1 line
314692 to 314677 ckt 1
DVP_P4-2: 556T591
CONTINGENCY 'DVP_P4-2: 556T591'
 OPEN BRANCH FROM BUS 314935 TO BUS 314936 CKT 1   /*8HERITAGE    500.0 - 8RAWLINGS    500.0
 OPEN BRANCH FROM BUS 966360 TO BUS 314936 CKT 1   /*AG1-505 TAP  500.0 - 8RAWLINGS    500.0
END
Breaker DC 178.31 % 179.49 % 684.0 C 1227.73 8.0
DVP 6FARMVIL-6BUCKING 230.0 kV Ckt 1 line
314692 to 314677 ckt 1
DVP_P4-2: 511T556
CONTINGENCY 'DVP_P4-2: 511T556'
 OPEN BRANCH FROM BUS 942930 TO BUS 314936 CKT 1   /*AE2-313 TAP  500.0 - 8RAWLINGS    500.0
 OPEN BRANCH FROM BUS 966360 TO BUS 314936 CKT 1   /*AG1-505 TAP  500.0 - 8RAWLINGS    500.0
END
Breaker DC 178.31 % 179.49 % 684.0 C 1227.72 8.0
DVP 6FARMVIL-6BUCKING 230.0 kV Ckt 1 line
314692 to 314677 ckt 1
DVP_P4-2: 511T591
CONTINGENCY 'DVP_P4-2: 511T591'
 OPEN BRANCH FROM BUS 314935 TO BUS 314936 CKT 1   /*8HERITAGE    500.0 - 8RAWLINGS    500.0
 OPEN BRANCH FROM BUS 942930 TO BUS 314936 CKT 1   /*AE2-313 TAP  500.0 - 8RAWLINGS    500.0
END
Breaker DC 178.26 % 179.44 % 684.0 C 1227.36 8.0
DVP 6BUCKING-6BREMO 230.0 kV Ckt 1 line
314677 to 314747 ckt 1
DVP_P4-2: 556T591
CONTINGENCY 'DVP_P4-2: 556T591'
 OPEN BRANCH FROM BUS 314935 TO BUS 314936 CKT 1   /*8HERITAGE    500.0 - 8RAWLINGS    500.0
 OPEN BRANCH FROM BUS 966360 TO BUS 314936 CKT 1   /*AG1-505 TAP  500.0 - 8RAWLINGS    500.0
END
Breaker DC 176.02 % 177.17 % 699.0 C 1238.43 8.0
DVP 6BUCKING-6BREMO 230.0 kV Ckt 1 line
314677 to 314747 ckt 1
DVP_P4-2: 511T556
CONTINGENCY 'DVP_P4-2: 511T556'
 OPEN BRANCH FROM BUS 942930 TO BUS 314936 CKT 1   /*AE2-313 TAP  500.0 - 8RAWLINGS    500.0
 OPEN BRANCH FROM BUS 966360 TO BUS 314936 CKT 1   /*AG1-505 TAP  500.0 - 8RAWLINGS    500.0
END
Breaker DC 176.02 % 177.17 % 699.0 C 1238.42 8.0
DVP 6BUCKING-6BREMO 230.0 kV Ckt 1 line
314677 to 314747 ckt 1
DVP_P4-2: 511T591
CONTINGENCY 'DVP_P4-2: 511T591'
 OPEN BRANCH FROM BUS 314935 TO BUS 314936 CKT 1   /*8HERITAGE    500.0 - 8RAWLINGS    500.0
 OPEN BRANCH FROM BUS 942930 TO BUS 314936 CKT 1   /*AE2-313 TAP  500.0 - 8RAWLINGS    500.0
END
Breaker DC 175.97 % 177.12 % 699.0 C 1238.06 8.0
CPLE/DVP 3KERR-3GW KING TAP 115.0 kV Ckt 1 line
314702 to 304102 ckt 1
DVP_P4-6: CAROLIN T122
CONTINGENCY 'DVP_P4-6: CAROLIN T122'
 OPEN BRANCH FROM BUS 313722 TO BUS 314559 CKT 1   /*3OCCONEECHEE 115.0 - 3CAROLNA     115.0
 OPEN BRANCH FROM BUS 313723 TO BUS 314559 CKT 1   /*3PECAN       115.0 - 3CAROLNA     115.0
 OPEN BRANCH FROM BUS 314559 TO BUS 314561 CKT 1   /*3CAROLNA     115.0 - 6CAROLNA     230.0
 OPEN BRANCH FROM BUS 314559 TO BUS 314571 CKT 1   /*3CAROLNA     115.0 - 3EATON F     115.0
 OPEN BRANCH FROM BUS 314559 TO BUS 314578 CKT 1   /*3CAROLNA     115.0 - 3HORNRTN     115.0
 OPEN BRANCH FROM BUS 314559 TO BUS 314585 CKT 1   /*3CAROLNA     115.0 - 3L GASTN     115.0
 OPEN BRANCH FROM BUS 314559 TO BUS 314600 CKT 1   /*3CAROLNA     115.0 - 3PLHITP      115.0
 OPEN BRANCH FROM BUS 314559 TO BUS 314835 CKT 1   /*3CAROLNA     115.0 - 3CAROL_1     115.0
 OPEN BRANCH FROM BUS 314559 TO BUS 315126 CKT 1   /*3CAROLNA     115.0 - 1ROARAP2      14.4
 OPEN BRANCH FROM BUS 314559 TO BUS 315128 CKT 1   /*3CAROLNA     115.0 - 1ROARAP4      14.4
 OPEN BUS 314559                                   /*3CAROLNA     115.0
 OPEN BUS 314835                                   /*3CAROL_1     115.0
 OPEN BUS 315126                                   /*1ROARAP2      14.4
 OPEN BUS 315128                                   /*1ROARAP4      14.4
END
Breaker AC 116.9 % 117.88 % 199.0 B 234.59 2.39
DVP 3BUTCHER CRK-3CHASCTY2 115.0 kV Ckt 1 line
313898 to 314267 ckt 1
DVP_P4-2: 235T298
CONTINGENCY 'DVP_P4-2: 235T298'
 OPEN BRANCH FROM BUS 313802 TO BUS 314268 CKT 1   /*6PRINCE EDW  230.0 - 6BRIERY      230.0
 OPEN BRANCH FROM BUS 313802 TO BUS 314692 CKT 1   /*6PRINCE EDW  230.0 - 6FARMVIL     230.0
 OPEN BRANCH FROM BUS 314268 TO BUS 934620 CKT 1   /*6BRIERY      230.0 - AD1-088 TAP  230.0
 OPEN BRANCH FROM BUS 314677 TO BUS 314692 CKT 1   /*6BUCKING     230.0 - 6FARMVIL     230.0
 OPEN BRANCH FROM BUS 314677 TO BUS 314747 CKT 1   /*6BUCKING     230.0 - 6BREMO       230.0
 OPEN BRANCH FROM BUS 314691 TO BUS 314692 CKT 1   /*3FARMVIL     115.0 - 6FARMVIL     230.0
 OPEN BRANCH FROM BUS 314691 TO BUS 314692 CKT 2   /*3FARMVIL     115.0 - 6FARMVIL     230.0
 OPEN BRANCH FROM BUS 962490 TO BUS 934620 CKT 1   /*AG1-098 TAP  230.0 - AD1-088 TAP  230.0
 OPEN BUS 313802                                   /*6PRINCE EDW  230.0
 OPEN BUS 314268                                   /*6BRIERY      230.0
 OPEN BUS 314677                                   /*6BUCKING     230.0
 OPEN BUS 924032                                   /*AB2-045 E    230.0
 OPEN BUS 934620                                   /*AD1-088 TAP  230.0
 OPEN BUS 934621                                   /*AD1-088 MAIN 230.0
 OPEN BUS 934622                                   /*AD1-088 COL1  34.5
 OPEN BUS 934623                                   /*AD1-088 TER   13.8
 OPEN BUS 934624                                   /*AD1-088 COL2  34.5
 OPEN BUS 934625                                   /*AD1-088 C      0.7
 OPEN BUS 934626                                   /*AD1-088 E      0.7
END
Breaker DC 147.57 % 151.89 % 349.0 C 530.08 15.06
DVP AG1-181 TAP-AG1-427 TAP 115.0 kV Ckt 1 line
963320 to 965590 ckt 1
DVP_P4-2: 235T298
CONTINGENCY 'DVP_P4-2: 235T298'
 OPEN BRANCH FROM BUS 313802 TO BUS 314268 CKT 1   /*6PRINCE EDW  230.0 - 6BRIERY      230.0
 OPEN BRANCH FROM BUS 313802 TO BUS 314692 CKT 1   /*6PRINCE EDW  230.0 - 6FARMVIL     230.0
 OPEN BRANCH FROM BUS 314268 TO BUS 934620 CKT 1   /*6BRIERY      230.0 - AD1-088 TAP  230.0
 OPEN BRANCH FROM BUS 314677 TO BUS 314692 CKT 1   /*6BUCKING     230.0 - 6FARMVIL     230.0
 OPEN BRANCH FROM BUS 314677 TO BUS 314747 CKT 1   /*6BUCKING     230.0 - 6BREMO       230.0
 OPEN BRANCH FROM BUS 314691 TO BUS 314692 CKT 1   /*3FARMVIL     115.0 - 6FARMVIL     230.0
 OPEN BRANCH FROM BUS 314691 TO BUS 314692 CKT 2   /*3FARMVIL     115.0 - 6FARMVIL     230.0
 OPEN BRANCH FROM BUS 962490 TO BUS 934620 CKT 1   /*AG1-098 TAP  230.0 - AD1-088 TAP  230.0
 OPEN BUS 313802                                   /*6PRINCE EDW  230.0
 OPEN BUS 314268                                   /*6BRIERY      230.0
 OPEN BUS 314677                                   /*6BUCKING     230.0
 OPEN BUS 924032                                   /*AB2-045 E    230.0
 OPEN BUS 934620                                   /*AD1-088 TAP  230.0
 OPEN BUS 934621                                   /*AD1-088 MAIN 230.0
 OPEN BUS 934622                                   /*AD1-088 COL1  34.5
 OPEN BUS 934623                                   /*AD1-088 TER   13.8
 OPEN BUS 934624                                   /*AD1-088 COL2  34.5
 OPEN BUS 934625                                   /*AD1-088 C      0.7
 OPEN BUS 934626                                   /*AD1-088 E      0.7
END
Breaker DC 105.85 % 107.26 % 349.0 C 374.34 4.93
CPLE/DVP 3KERR-3GW KING TAP 115.0 kV Ckt 1 line
314702 to 304102 ckt 1
DVP_P4-2: 13002
CONTINGENCY 'DVP_P4-2: 13002'
 OPEN BRANCH FROM BUS 313722 TO BUS 314559 CKT 1   /*3OCCONEECHEE 115.0 - 3CAROLNA     115.0
 OPEN BRANCH FROM BUS 313723 TO BUS 314559 CKT 1   /*3PECAN       115.0 - 3CAROLNA     115.0
 OPEN BRANCH FROM BUS 314559 TO BUS 314561 CKT 1   /*3CAROLNA     115.0 - 6CAROLNA     230.0
 OPEN BRANCH FROM BUS 314559 TO BUS 314571 CKT 1   /*3CAROLNA     115.0 - 3EATON F     115.0
 OPEN BRANCH FROM BUS 314559 TO BUS 314600 CKT 1   /*3CAROLNA     115.0 - 3PLHITP      115.0
 OPEN BRANCH FROM BUS 314559 TO BUS 314835 CKT 1   /*3CAROLNA     115.0 - 3CAROL_1     115.0
 OPEN BRANCH FROM BUS 314595 TO BUS 314600 CKT 1   /*3PL HILL     115.0 - 3PLHITP      115.0
 OPEN BRANCH FROM BUS 314600 TO BUS 314615 CKT 1   /*3PLHITP      115.0 - 3SKIPPERS    115.0
 OPEN BUS 314595                                   /*3PL HILL     115.0
 OPEN BUS 314600                                   /*3PLHITP      115.0
END
Breaker AC 101.62 % 102.51 % 199.0 B 203.99 2.09
CPLE/DVP 3KERR-3GW KING TAP 115.0 kV Ckt 1 line
314702 to 304102 ckt 1
DVP_P4-2: 102802
CONTINGENCY 'DVP_P4-2: 102802'
 OPEN BRANCH FROM BUS 313722 TO BUS 314559 CKT 1   /*3OCCONEECHEE 115.0 - 3CAROLNA     115.0
 OPEN BRANCH FROM BUS 313723 TO BUS 314559 CKT 1   /*3PECAN       115.0 - 3CAROLNA     115.0
 OPEN BRANCH FROM BUS 314559 TO BUS 314561 CKT 1   /*3CAROLNA     115.0 - 6CAROLNA     230.0
 OPEN BRANCH FROM BUS 314559 TO BUS 314571 CKT 1   /*3CAROLNA     115.0 - 3EATON F     115.0
 OPEN BRANCH FROM BUS 314559 TO BUS 314600 CKT 1   /*3CAROLNA     115.0 - 3PLHITP      115.0
 OPEN BRANCH FROM BUS 314559 TO BUS 314835 CKT 1   /*3CAROLNA     115.0 - 3CAROL_1     115.0
END
Breaker AC 101.62 % 102.51 % 199.0 B 203.99 2.09
DVP 3TWITTYS-3CENTRAL 115.0 kV Ckt 1 line
314722 to 314679 ckt 1
DVP_P4-2: 235T298
CONTINGENCY 'DVP_P4-2: 235T298'
 OPEN BRANCH FROM BUS 313802 TO BUS 314268 CKT 1   /*6PRINCE EDW  230.0 - 6BRIERY      230.0
 OPEN BRANCH FROM BUS 313802 TO BUS 314692 CKT 1   /*6PRINCE EDW  230.0 - 6FARMVIL     230.0
 OPEN BRANCH FROM BUS 314268 TO BUS 934620 CKT 1   /*6BRIERY      230.0 - AD1-088 TAP  230.0
 OPEN BRANCH FROM BUS 314677 TO BUS 314692 CKT 1   /*6BUCKING     230.0 - 6FARMVIL     230.0
 OPEN BRANCH FROM BUS 314677 TO BUS 314747 CKT 1   /*6BUCKING     230.0 - 6BREMO       230.0
 OPEN BRANCH FROM BUS 314691 TO BUS 314692 CKT 1   /*3FARMVIL     115.0 - 6FARMVIL     230.0
 OPEN BRANCH FROM BUS 314691 TO BUS 314692 CKT 2   /*3FARMVIL     115.0 - 6FARMVIL     230.0
 OPEN BRANCH FROM BUS 962490 TO BUS 934620 CKT 1   /*AG1-098 TAP  230.0 - AD1-088 TAP  230.0
 OPEN BUS 313802                                   /*6PRINCE EDW  230.0
 OPEN BUS 314268                                   /*6BRIERY      230.0
 OPEN BUS 314677                                   /*6BUCKING     230.0
 OPEN BUS 924032                                   /*AB2-045 E    230.0
 OPEN BUS 934620                                   /*AD1-088 TAP  230.0
 OPEN BUS 934621                                   /*AD1-088 MAIN 230.0
 OPEN BUS 934622                                   /*AD1-088 COL1  34.5
 OPEN BUS 934623                                   /*AD1-088 TER   13.8
 OPEN BUS 934624                                   /*AD1-088 COL2  34.5
 OPEN BUS 934625                                   /*AD1-088 C      0.7
 OPEN BUS 934626                                   /*AD1-088 E      0.7
END
Breaker DC 106.94 % 108.36 % 349.0 C 378.16 4.93
DVP 3CENTRAL-AG1-181 TAP 115.0 kV Ckt 1 line
314679 to 963320 ckt 1
DVP_P4-2: 235T298
CONTINGENCY 'DVP_P4-2: 235T298'
 OPEN BRANCH FROM BUS 313802 TO BUS 314268 CKT 1   /*6PRINCE EDW  230.0 - 6BRIERY      230.0
 OPEN BRANCH FROM BUS 313802 TO BUS 314692 CKT 1   /*6PRINCE EDW  230.0 - 6FARMVIL     230.0
 OPEN BRANCH FROM BUS 314268 TO BUS 934620 CKT 1   /*6BRIERY      230.0 - AD1-088 TAP  230.0
 OPEN BRANCH FROM BUS 314677 TO BUS 314692 CKT 1   /*6BUCKING     230.0 - 6FARMVIL     230.0
 OPEN BRANCH FROM BUS 314677 TO BUS 314747 CKT 1   /*6BUCKING     230.0 - 6BREMO       230.0
 OPEN BRANCH FROM BUS 314691 TO BUS 314692 CKT 1   /*3FARMVIL     115.0 - 6FARMVIL     230.0
 OPEN BRANCH FROM BUS 314691 TO BUS 314692 CKT 2   /*3FARMVIL     115.0 - 6FARMVIL     230.0
 OPEN BRANCH FROM BUS 962490 TO BUS 934620 CKT 1   /*AG1-098 TAP  230.0 - AD1-088 TAP  230.0
 OPEN BUS 313802                                   /*6PRINCE EDW  230.0
 OPEN BUS 314268                                   /*6BRIERY      230.0
 OPEN BUS 314677                                   /*6BUCKING     230.0
 OPEN BUS 924032                                   /*AB2-045 E    230.0
 OPEN BUS 934620                                   /*AD1-088 TAP  230.0
 OPEN BUS 934621                                   /*AD1-088 MAIN 230.0
 OPEN BUS 934622                                   /*AD1-088 COL1  34.5
 OPEN BUS 934623                                   /*AD1-088 TER   13.8
 OPEN BUS 934624                                   /*AD1-088 COL2  34.5
 OPEN BUS 934625                                   /*AD1-088 C      0.7
 OPEN BUS 934626                                   /*AD1-088 E      0.7
END
Breaker DC 105.85 % 107.27 % 349.0 C 374.36 4.93
DVP AD2-033 TAP-3BUTCHER CRK 115.0 kV Ckt 1 line
936260 to 313898 ckt 1
DVP_P4-2: 235T298
CONTINGENCY 'DVP_P4-2: 235T298'
 OPEN BRANCH FROM BUS 313802 TO BUS 314268 CKT 1   /*6PRINCE EDW  230.0 - 6BRIERY      230.0
 OPEN BRANCH FROM BUS 313802 TO BUS 314692 CKT 1   /*6PRINCE EDW  230.0 - 6FARMVIL     230.0
 OPEN BRANCH FROM BUS 314268 TO BUS 934620 CKT 1   /*6BRIERY      230.0 - AD1-088 TAP  230.0
 OPEN BRANCH FROM BUS 314677 TO BUS 314692 CKT 1   /*6BUCKING     230.0 - 6FARMVIL     230.0
 OPEN BRANCH FROM BUS 314677 TO BUS 314747 CKT 1   /*6BUCKING     230.0 - 6BREMO       230.0
 OPEN BRANCH FROM BUS 314691 TO BUS 314692 CKT 1   /*3FARMVIL     115.0 - 6FARMVIL     230.0
 OPEN BRANCH FROM BUS 314691 TO BUS 314692 CKT 2   /*3FARMVIL     115.0 - 6FARMVIL     230.0
 OPEN BRANCH FROM BUS 962490 TO BUS 934620 CKT 1   /*AG1-098 TAP  230.0 - AD1-088 TAP  230.0
 OPEN BUS 313802                                   /*6PRINCE EDW  230.0
 OPEN BUS 314268                                   /*6BRIERY      230.0
 OPEN BUS 314677                                   /*6BUCKING     230.0
 OPEN BUS 924032                                   /*AB2-045 E    230.0
 OPEN BUS 934620                                   /*AD1-088 TAP  230.0
 OPEN BUS 934621                                   /*AD1-088 MAIN 230.0
 OPEN BUS 934622                                   /*AD1-088 COL1  34.5
 OPEN BUS 934623                                   /*AD1-088 TER   13.8
 OPEN BUS 934624                                   /*AD1-088 COL2  34.5
 OPEN BUS 934625                                   /*AD1-088 C      0.7
 OPEN BUS 934626                                   /*AD1-088 E      0.7
END
Breaker DC 108.91 % 112.67 % 400.0 C 450.69 15.07
DVP AG1-030 TAP-3VICT DP 115.0 kV Ckt 1 line
961890 to 314725 ckt 1
DVP_P4-2: 235T298
CONTINGENCY 'DVP_P4-2: 235T298'
 OPEN BRANCH FROM BUS 313802 TO BUS 314268 CKT 1   /*6PRINCE EDW  230.0 - 6BRIERY      230.0
 OPEN BRANCH FROM BUS 313802 TO BUS 314692 CKT 1   /*6PRINCE EDW  230.0 - 6FARMVIL     230.0
 OPEN BRANCH FROM BUS 314268 TO BUS 934620 CKT 1   /*6BRIERY      230.0 - AD1-088 TAP  230.0
 OPEN BRANCH FROM BUS 314677 TO BUS 314692 CKT 1   /*6BUCKING     230.0 - 6FARMVIL     230.0
 OPEN BRANCH FROM BUS 314677 TO BUS 314747 CKT 1   /*6BUCKING     230.0 - 6BREMO       230.0
 OPEN BRANCH FROM BUS 314691 TO BUS 314692 CKT 1   /*3FARMVIL     115.0 - 6FARMVIL     230.0
 OPEN BRANCH FROM BUS 314691 TO BUS 314692 CKT 2   /*3FARMVIL     115.0 - 6FARMVIL     230.0
 OPEN BRANCH FROM BUS 962490 TO BUS 934620 CKT 1   /*AG1-098 TAP  230.0 - AD1-088 TAP  230.0
 OPEN BUS 313802                                   /*6PRINCE EDW  230.0
 OPEN BUS 314268                                   /*6BRIERY      230.0
 OPEN BUS 314677                                   /*6BUCKING     230.0
 OPEN BUS 924032                                   /*AB2-045 E    230.0
 OPEN BUS 934620                                   /*AD1-088 TAP  230.0
 OPEN BUS 934621                                   /*AD1-088 MAIN 230.0
 OPEN BUS 934622                                   /*AD1-088 COL1  34.5
 OPEN BUS 934623                                   /*AD1-088 TER   13.8
 OPEN BUS 934624                                   /*AD1-088 COL2  34.5
 OPEN BUS 934625                                   /*AD1-088 C      0.7
 OPEN BUS 934626                                   /*AD1-088 E      0.7
END
Breaker DC 97.27 % 101.59 % 349.0 C 354.55 15.07
DVP 3VICT DP-3VICTRIA 115.0 kV Ckt 1 line
314725 to 314723 ckt 1
DVP_P4-2: 235T298
CONTINGENCY 'DVP_P4-2: 235T298'
 OPEN BRANCH FROM BUS 313802 TO BUS 314268 CKT 1   /*6PRINCE EDW  230.0 - 6BRIERY      230.0
 OPEN BRANCH FROM BUS 313802 TO BUS 314692 CKT 1   /*6PRINCE EDW  230.0 - 6FARMVIL     230.0
 OPEN BRANCH FROM BUS 314268 TO BUS 934620 CKT 1   /*6BRIERY      230.0 - AD1-088 TAP  230.0
 OPEN BRANCH FROM BUS 314677 TO BUS 314692 CKT 1   /*6BUCKING     230.0 - 6FARMVIL     230.0
 OPEN BRANCH FROM BUS 314677 TO BUS 314747 CKT 1   /*6BUCKING     230.0 - 6BREMO       230.0
 OPEN BRANCH FROM BUS 314691 TO BUS 314692 CKT 1   /*3FARMVIL     115.0 - 6FARMVIL     230.0
 OPEN BRANCH FROM BUS 314691 TO BUS 314692 CKT 2   /*3FARMVIL     115.0 - 6FARMVIL     230.0
 OPEN BRANCH FROM BUS 962490 TO BUS 934620 CKT 1   /*AG1-098 TAP  230.0 - AD1-088 TAP  230.0
 OPEN BUS 313802                                   /*6PRINCE EDW  230.0
 OPEN BUS 314268                                   /*6BRIERY      230.0
 OPEN BUS 314677                                   /*6BUCKING     230.0
 OPEN BUS 924032                                   /*AB2-045 E    230.0
 OPEN BUS 934620                                   /*AD1-088 TAP  230.0
 OPEN BUS 934621                                   /*AD1-088 MAIN 230.0
 OPEN BUS 934622                                   /*AD1-088 COL1  34.5
 OPEN BUS 934623                                   /*AD1-088 TER   13.8
 OPEN BUS 934624                                   /*AD1-088 COL2  34.5
 OPEN BUS 934625                                   /*AD1-088 C      0.7
 OPEN BUS 934626                                   /*AD1-088 E      0.7
END
Breaker DC 96.3 % 100.62 % 349.0 C 351.15 15.07
DVP 3BUTCHER CRK-3CHASCTY2 115.0 kV Ckt 1 line
313898 to 314267 ckt 1
DVP_P4-2: 1T158
CONTINGENCY 'DVP_P4-2: 1T158'
 OPEN BRANCH FROM BUS 313755 TO BUS 314701 CKT 1   /*3FLAT CREEK  115.0 - 3LONEPN      115.0
 OPEN BRANCH FROM BUS 313755 TO BUS 314707 CKT 1   /*3FLAT CREEK  115.0 - 3MORAN       115.0
 OPEN BRANCH FROM BUS 314426 TO BUS 314701 CKT 1   /*3FT PKET     115.0 - 3LONEPN      115.0
 OPEN BRANCH FROM BUS 314519 TO BUS 314701 CKT 1   /*3LONEPINE_1  115.0 - 3LONEPN      115.0
 OPEN BRANCH FROM BUS 314691 TO BUS 314707 CKT 1   /*3FARMVIL     115.0 - 3MORAN       115.0
 OPEN BUS 313755                                   /*3FLAT CREEK  115.0
 OPEN BUS 314426                                   /*3FT PKET     115.0
 OPEN BUS 314519                                   /*3LONEPINE_1  115.0
 OPEN BUS 314707                                   /*3MORAN       115.0
END
Breaker AC 135.77 % 141.23 % 349.0 C 492.9 19.99
DVP AD2-033 TAP-3BUTCHER CRK 115.0 kV Ckt 1 line
936260 to 313898 ckt 1
DVP_P4-2: 1T158
CONTINGENCY 'DVP_P4-2: 1T158'
 OPEN BRANCH FROM BUS 313755 TO BUS 314701 CKT 1   /*3FLAT CREEK  115.0 - 3LONEPN      115.0
 OPEN BRANCH FROM BUS 313755 TO BUS 314707 CKT 1   /*3FLAT CREEK  115.0 - 3MORAN       115.0
 OPEN BRANCH FROM BUS 314426 TO BUS 314701 CKT 1   /*3FT PKET     115.0 - 3LONEPN      115.0
 OPEN BRANCH FROM BUS 314519 TO BUS 314701 CKT 1   /*3LONEPINE_1  115.0 - 3LONEPN      115.0
 OPEN BRANCH FROM BUS 314691 TO BUS 314707 CKT 1   /*3FARMVIL     115.0 - 3MORAN       115.0
 OPEN BUS 313755                                   /*3FLAT CREEK  115.0
 OPEN BUS 314426                                   /*3FT PKET     115.0
 OPEN BUS 314519                                   /*3LONEPINE_1  115.0
 OPEN BUS 314707                                   /*3MORAN       115.0
END
Breaker AC 100.54 % 105.38 % 400.0 C 421.54 20.0
CPLE/DVP 3KERR-3GW KING TAP 115.0 kV Ckt 1 line
314702 to 304102 ckt 1
DVP_P7-1: LN 22-90
CONTINGENCY 'DVP_P7-1: LN 22-90'
 OPEN BRANCH FROM BUS 314265 TO BUS 314584 CKT 1   /*3FIVEFORKSDP 115.0 - 3LITTLTN     115.0
 OPEN BRANCH FROM BUS 314265 TO BUS 314673 CKT 1   /*3FIVEFORKSDP 115.0 - 3PALMERSPRNG 115.0
 OPEN BRANCH FROM BUS 314559 TO BUS 314571 CKT 1   /*3CAROLNA     115.0 - 3EATON F     115.0
 OPEN BRANCH FROM BUS 314559 TO BUS 314585 CKT 1   /*3CAROLNA     115.0 - 3L GASTN     115.0
 OPEN BRANCH FROM BUS 314571 TO BUS 316125 CKT 1   /*3EATON F     115.0 - AC1-054 TAP  115.0
 OPEN BRANCH FROM BUS 314584 TO BUS 314585 CKT 1   /*3LITTLTN     115.0 - 3L GASTN     115.0
 OPEN BRANCH FROM BUS 314702 TO BUS 316125 CKT 1   /*3KERR        115.0 - AC1-054 TAP  115.0
 OPEN BUS 314265                                   /*3FIVEFORKSDP 115.0
 OPEN BUS 314571                                   /*3EATON F     115.0
 OPEN BUS 314584                                   /*3LITTLTN     115.0
 OPEN BUS 314585                                   /*3L GASTN     115.0
 OPEN BUS 316125                                   /*AC1-054 TAP  115.0
 OPEN BUS 316126                                   /*AC1-054 MAIN 115.0
 OPEN BUS 316127                                   /*AC1-054 COL2  22.9
 OPEN BUS 316128                                   /*AC1-054 COL1  22.9
 OPEN BUS 316129                                   /*AC1-054 C      0.4
 OPEN BUS 925785                                   /*AC1-054 E      0.4
END
Tower AC 115.0 % 115.97 % 199.0 B 230.79 2.36
DVP AC2-165 TAP-6POWHATN 230.0 kV Ckt 1 line
933500 to 314333 ckt 1
DVP_P7-1: LN 5-2028-C
CONTINGENCY 'DVP_P7-1: LN 5-2028-C'
 OPEN BRANCH FROM BUS 314744 TO BUS 314754 CKT 1   /*3BREMO       115.0 - 3CUNNING     115.0
 OPEN BRANCH FROM BUS 314749 TO BUS 314765 CKT 1   /*6CHARLVL     230.0 - 6MTEAGLE     230.0
 OPEN BRANCH FROM BUS 961060 TO BUS 314765 CKT 1   /*AF2-397 TAP  230.0 - 6MTEAGLE     230.0
 OPEN BUS 314754                                   /*3CUNNING     115.0
 OPEN BUS 314765                                   /*6MTEAGLE     230.0
END
Tower AC 99.77 % 100.17 % 980.0 C 981.63 3.83
DVP AC2-165 TAP-6POWHATN 230.0 kV Ckt 1 line
933500 to 314333 ckt 1
DVP_P7-1: LN 5-2028-B
CONTINGENCY 'DVP_P7-1: LN 5-2028-B'
 OPEN BRANCH FROM BUS 314744 TO BUS 314754 CKT 1   /*3BREMO       115.0 - 3CUNNING     115.0
 OPEN BRANCH FROM BUS 961060 TO BUS 314765 CKT 1   /*AF2-397 TAP  230.0 - 6MTEAGLE     230.0
 OPEN BUS 314754                                   /*3CUNNING     115.0
END
Tower AC 99.76 % 100.16 % 980.0 C 981.55 3.83

Light Load Analysis

At this time light load analysis not required for this project.

System Reinforcements

The table below lists all network upgrades which resolve the identified overloaded facilities in this report.

Important to Note:

Note for Uprate Projects: Per Tariff Part VII, Subpart B, section 304 (B), if a project is an uprate (project relies on the Interconnection Facilities of a prior project) whose base project does not qualify for the expedited process, the uprate also will not qualify for the expedited process, regardless of analysis results.

Notes regarding Results displayed:

  1. Some flowgate overloads that a New Service Request contributes to, but does not contribute enough to meet cost allocation eligibility (per Manual 14A, Attachment B.3), may be reported in this Transition Sort report. These types of flowgates do not affect the classification of the New Service Request as either Expedited Process or Transition Cycle #1 because cost allocation eligibility has not been met.
  2. For projects that were determined to not meet Expedited Process eligibility and are being reprioritized to Transition Cycle #1, not all reinforcements in excess of $5,000,000 may be shown in this report. This report may only display a subset of those reinforcements determined to be in excess of $5,000,000 which would classify the project as not meeting Expedited Process Eligibility. This is not a formal System Impact Study.
  3. Reinforcements previously identified by Transmission Owners for violations on lower voltage facilities are included in this report. Transmission Owner analysis will be updated as part of the Expedited Process and Transition Cycle 1 retools.
System Reinforcements
RTEP ID Title Total Cost
n7543 Rebuild 115 kV Line 1045 $3,445,000
n7675 Reconductor 115 kV Line#98 from AD2-033 Tap to Butcher Creek. $19,220,000
n7766 Rebuild 115 kV Line #1012 From AD2-063 Tap-AG1-181 Tap-Central-Twitty's Creek-AF2-222 Tap-Madsonav $24,835,000
n6246 Add additional 230/115 kV transformer (#3) for Circuit 1 at Farmville substation $6,000,000
n7550 Add additional 230/115 kV transformer (#4) for Circuit 2 at Farmville substation. $6,000,000
n7676 Rebuild 115 kV Line#158 $27,535,000
(TBD) Reconductor 20 miles with single 795 ACSS-TW per phase, replace breaker, disconnect switches, wave trap, line switch $60,000,000
s2614 For DEV portion, rebuild 4.7 miles of 115 kV Line 45 from Kerr Dam to GW King Tap with 768 ACSS. $6,123,000
n7662 Rebuild 115 kV Line #1034 from AG1-030 Tap to Victoria DP $9,115,000
n7688 Rebuild 115 kV Line #1034 $3,830,000
n7570 Wreck and Rebuild 230 kV Line #298 From Buckingham to Bremo $47,675,000
n6245 Rebuild 12.76 miles of 230 kV Line 298 from Buckingham to Farmville with 2-768.2 ACSS 250 C. Replace Line Lead, Line Switch, Relay (CT), Wave trap at Farmville terminal $19,710,000
n8243 Rebuild 4.01 miles of 230 kV Line 2027 from Powhatan to AC2-165 Tap with 2-795 ACSR (26/7) 150 C $10,025,000

Attachments

Conclusion

The Transition Sort load flow retool results indicate that AG1-169 is not eligible for the Expedited Process per PJM Tariff Part VII, Subpart B, section 304 (A) will be reprioritized to Transition Cycle #1. See next steps for your project in the "Introduction" section above.