AF2-406 Transition Sort Retool Results -- Reprioritized to Transition Cycle #1

v1.00 released 2023-12-14 11:06

Sayre 115 kV

75.0 MW Capacity / 75.0 MW Energy

Introduction

In accordance with Tariff Part VII, Subpart B, section 304, PJM performed load flow analysis (Transition Sort Retool) on all AE1 through AG1 projects that have met eligibility requirements according to Tariff, Part VII, Subpart B, section 303. The purpose of this study is to determine whether a project would be classified as eligible for the Expedited Process (Fast Lane) or if it would be reprioritized to be studied as part of Transition Cycle #1 (TC1) using the criteria from the Expedited Process Eligibility section of Tariff Part VII, section 304. This is not a System Impact Study report.

Below are the results of the study, details of how the study was performed, criterion used in the evaluation of the Expedited Process vs. TC1 determination, and next steps in the interconnection process for your project.

Transition Cycle #1:

The AF2-406 project has not met the Expedited Process Eligibility requirements in Tariff Part VII, Subpart B, section 304 and will therefore be reprioritized to Transition Cycle #1. Please see "Transition Cycle #1 Rules" below.

Transition Sort Retool Study Process and Criteria:

In order to determine Expedited Process vs. Transition Cycle #1 classification, projects which met the Transition Eligibility requirements from Tariff Part VII, Subpart B, section 303 were studied on the base case model that was used for the original System Impact Study analysis. Both a summer peak and light load load flow analysis were performed. Projects that have cost allocation eligibility or are identified as the first to cause a system violation which requires the need for a Network Upgrade with a total estimated cost greater than $5 million will be reprioritized to Transition Cycle #1. All other projects will be eligible for the expedited procedures set forth in Tariff Part VII, Subpart B, section 304 (B).

Expedited Process Eligibility: OATT Tariff Part VII, section 304:

A project is not eligible for the expedited process if it has cost allocation eligibility or is identified as the first to cause, as determined according to Tariff, Part VI, section 217.3, for a Network Upgrade which has a total estimated cost of greater than $5,000,000. Such cost estimate will be based on Transmission Provider's most recently available data.

Not considered in the Transition Sorting: The cost of the Interconnection Facilities is not considered when determining a project's eligibility for the expedited process. Affected Systems upgrade costs are also not considered in the evaluation.

Transition Sort Retool Results Provided:

This report includes a list of:

  1. the overloaded flowgates (overloaded facilities + contingency pair) that the project contributes towards
  2. other interconnection projects that may also contribute to the overloaded facility, and
  3. the total estimated cost for any required Network Upgrades.

Important Notes:

Note for Uprate Projects: Per Tariff Part VII, Subpart B, section 304 (B), if a project is an uprate (project relies on the Interconnection Facilities of a prior project) whose base project does not qualify for the expedited process, the uprate also will not qualify for the expedited process, regardless of analysis results.

Notes regarding Results displayed:

  1. Some flowgate overloads that a New Service Request contributes to, but does not contribute enough to meet cost allocation eligibility (per Manual 14A, Attachment B.3), may be reported in this Transition Sort report. These types of flowgates do not affect the classification of the New Service Request as either Expedited Process or Transition Cycle #1 because cost allocation eligibility has not been met.
  2. For projects that were determined to not meet Expedited Process eligibility and are being reprioritized to Transition Cycle #1, not all reinforcements in excess of $5,000,000 may be shown in this report. This report may only display a subset of those reinforcements determined to be in excess of $5,000,000 which would classify the project as not meeting Expedited Process Eligibility. This is not a formal System Impact Study.

Next Steps for your project:

Transition Cycle #1 Rules:

Refer to Tariff Part VII, Subpart B, section 304 (C) for the Transition Cycle #1 Project Rules.

Transition Cycle #1 will start no later than one year from the Transition Start Date (July 10, 2023). Transition Cycle #1 will run simultaneously with the expedited process, however Transition Cycle #1, Phase III will not begin until all expedited process projects have been completed.

Projects that are reprioritized to Transition Cycle #1 will not need to re-apply to the Interconnection Cycle Process. Therefore, there is no Application Review Phase for Transition Cycle #1. The cycle process for Transition Cycle #1 includes three Study Phases and three Decision Points:

  1. Phase I System Impact Study and Decision Point I; and
  2. Phase II System Impact Study and Decision Point II; and
  3. Phase III System Impact Study and Decision Point III

Refer to Tariff Part VII, Subpart D, section 307 for the Transition Cycle #1 study process.

General

The Interconnection Customer (IC), has proposed a Storage generating facility located in the PENELEC zone — Bradford County, Pennsylvania. The installed facilities will have a total capability of 75.0 MW with 75.0 MW of this output being recognized by PJM as Capacity.

Project Information
Queue Number AF2-406
Project Name Sayre 115 kV
Developer Name Juno Power Management LLC
State Pennsylvania
County Bradford
Transmission Owner PENELEC
MFO 75.0 MW
MWE 75.0 MW
MWC 75.0 MW
Fuel Type Storage
Basecase Study Year 2023

Point of Interconnection

AF2-406 will interconnect on the PENELEC transmission system, which will be accomplished by expanding East Sayre Substation to a 115 kV five breaker ring bus substation. The project will also require Non-Direct Connection upgrades at East Towanda Substation. NYSEG may require additional remote upgrades on their system.

 

Summer Peak Analysis

The Queue Project was evaluated as a 75.0 MW (Capacity 75.0 MW) injection in the PENELEC area. Project was evaluated for compliance with applicable reliability planning criteria (PJM, NERC, NERC Regional Reliability Councils, and Transmission Owners). Potential Summer peak period network impacts are listed below:

Important to Note:

Note for Uprate Projects: Per Tariff Part VII, Subpart B, section 304 (B), if a project is an uprate (project relies on the Interconnection Facilities of a prior project) whose base project does not qualify for the expedited process, the uprate also will not qualify for the expedited process, regardless of analysis results.

Notes regarding Results displayed:

  1. Some flowgate overloads that a New Service Request contributes to, but does not contribute enough to meet cost allocation eligibility (per Manual 14A, Attachment B.3), may be reported in this Transition Sort report. These types of flowgates do not affect the classification of the New Service Request as either Expedited Process or Transition Cycle #1 because cost allocation eligibility has not been met.
  2. For projects that were determined to not meet Expedited Process eligibility and are being reprioritized to Transition Cycle #1, not all reinforcements in excess of $5,000,000 may be shown in this report. This report may only display a subset of those reinforcements determined to be in excess of $5,000,000 which would classify the project as not meeting Expedited Process Eligibility. This is not a formal System Impact Study.
Summer Peak Analysis
Area Facility Description Contingency Name Contingency Type DC|AC Initial Loading Final Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Details
PJM STAR592-KEYSTONE 1.0/500.0 kV Ckt 4 transformer
999401 to 200011 ckt 4
PJM500_PN_P4-500-001A
CONTINGENCY 'PJM500_PN_P4-500-001A'
 DISCONNECT BRANCH FROM BUS 200011 TO BUS 200810 CKT 3   /*KEYSTONE     500.0 - 26KEYSTONE   230.0
 DISCONNECT BUS 200033                                   /*KEYS G2       20.0
 REMOVE MACHINE H FROM BUS 200033                        /*KEYS G2       20.0
 REMOVE MACHINE L FROM BUS 200033                        /*KEYS G2       20.0
END
Breaker AC 109.84 % 110.92 % 639.0 B 708.78 7.91
PJM STAR592-KEYSTONE 1.0/500.0 kV Ckt 4 transformer
999401 to 200011 ckt 4
PJM500_PN_P4-500-001D
CONTINGENCY 'PJM500_PN_P4-500-001D'
 DISCONNECT BRANCH FROM BUS 200011 TO BUS 200810 CKT 3   /*KEYSTONE     500.0 - 26KEYSTONE   230.0
 DISCONNECT BUS 200032                                   /*KEYS G1       20.0
 REMOVE MACHINE H FROM BUS 200032                        /*KEYS G1       20.0
 REMOVE MACHINE L FROM BUS 200032                        /*KEYS G1       20.0
END
Breaker AC 109.77 % 110.84 % 639.0 B 708.27 7.91
PJM/PL LACK-LACKAW 230.0/500.0 kV Ckt 3 transformer
208009 to 200074 ckt 3
PL_P42_001057
CONTINGENCY 'PL_P42_001057'
 DISCONNECT BRANCH FROM BUS 208009 TO BUS 200074 CKT 4   /*LACK         230.0 - LACKAW       500.0
 DISCONNECT BRANCH FROM BUS 208009 TO BUS 208049 CKT 1   /*LACK         230.0 - PAUP         230.0
 DISCONNECT BRANCH FROM BUS 208009 TO BUS 211681 CKT 2   /*LACK         230.0 - LACK          69.0
END
Breaker AC 105.94 % 107.07 % 1167.0 B 1249.51 15.28
PJM/PL LACK-LACKAW 230.0/500.0 kV Ckt 3 transformer
208009 to 200074 ckt 3
PL_P42_101231
CONTINGENCY 'PL_P42_101231'
 DISCONNECT BRANCH FROM BUS 208009 TO BUS 200074 CKT 4   /*LACK         230.0 - LACKAW       500.0
 DISCONNECT BRANCH FROM BUS 208009 TO BUS 208049 CKT 1   /*LACK         230.0 - PAUP         230.0
 DISCONNECT BRANCH FROM BUS 208009 TO BUS 211681 CKT 2   /*LACK         230.0 - LACK          69.0
END
Breaker AC 105.94 % 107.07 % 1167.0 B 1249.51 15.28
PENELEC 26TOWANDA-26NO MESHO 115.0 kV Ckt 1 line
200674 to 200677 ckt 1
PN-P1-2-PN-230-013A
CONTINGENCY 'PN-P1-2-PN-230-013A'
 DISCONNECT BRANCH FROM BUS 200675 TO BUS 200924 CKT 1   /*26E.TWANDA   230.0 - 26CANYON     230.0
 DISCONNECT BRANCH FROM BUS 200924 TO BUS 200706 CKT 1   /*26CANYON     230.0 - 26N.MESHPN   230.0
END
Single AC 110.47 % 115.27 % 202.0 B 232.85 12.91
PENELEC 26HOMER CT-26SHELOCTA 230.0 kV Ckt 1 line
200767 to 200795 ckt 1
PN_P4-500-002F
CONTINGENCY 'PN_P4-500-002F'
 DISCONNECT BRANCH FROM BUS 200005 TO BUS 200912 CKT 3   /*CONEM-GH     500.0 - 26CONEMAGH   230.0
 DISCONNECT BUS 200030                                   /*CONE G1       22.0
END
Breaker AC 137.35 % 138.54 % 917.0 B 1270.41 13.35
PENELEC 26HOMER CT-26SHELOCTA 230.0 kV Ckt 1 line
200767 to 200795 ckt 1
PN_P4-500-002A
CONTINGENCY 'PN_P4-500-002A'
 DISCONNECT BRANCH FROM BUS 200005 TO BUS 200912 CKT 3   /*CONEM-GH     500.0 - 26CONEMAGH   230.0
 DISCONNECT BUS 200031                                   /*CONE G2       22.0
END
Breaker AC 137.34 % 138.54 % 917.0 B 1270.41 13.35
NYISO/PENELEC 26E.SAYRE-N.WAV115 115.0 kV Ckt 1 line
200676 to 130836 ckt 1
PN-P1-2-PN-230-101T
CONTINGENCY 'PN-P1-2-PN-230-101T'
 DISCONNECT BRANCH FROM BUS 200675 TO BUS 130763 CKT 1   /*26E.TWANDA   230.0 - HILSD230     230.0
END
Single AC 92.14 % 126.08 % 128.0 B 161.38 42.78
NYISO/PENELEC 26E.SAYRE-N.WAV115 115.0 kV Ckt 1 line
200676 to 130836 ckt 1
PJM500_PL_P12_000082
CONTINGENCY 'PJM500_PL_P12_000082'
 DISCONNECT BRANCH FROM BUS 200074 TO BUS 200098 CKT 1   /*LACKAW       500.0 - LACHOP_T     500.0
 DISCONNECT BRANCH FROM BUS 200091 TO BUS 200098 CKT 1   /*HOPATCONG    500.0 - LACHOP_T     500.0
END
Single AC 75.57 % 110.56 % 128.0 B 141.52 44.76
NYISO/PENELEC 26E.SAYRE-N.WAV115 115.0 kV Ckt 1 line
200676 to 130836 ckt 1
PN-P1-3-PN-230-029
CONTINGENCY 'PN-P1-3-PN-230-029'
 DISCONNECT BUS 200908   /*26CHAPMAN+   230.0
 DISCONNECT BUS 200909   /*26LOBO+      230.0
END
Single AC 69.93 % 105.48 % 128.0 B 135.01 45.5
NYISO/PENELEC 26E.SAYRE-N.WAV115 115.0 kV Ckt 1 line
200676 to 130836 ckt 1
AP_P1-2_WP-230-324T_SRT-A
CONTINGENCY 'AP_P1-2_WP-230-324T_SRT-A'
 DISCONNECT BRANCH FROM BUS 200857 TO BUS 200909 CKT 1    /*26MARSHALL   230.0 - 26LOBO+      230.0
 DISCONNECT BRANCH FROM BUS 200908 TO BUS 200909 CKT 1    /*26CHAPMAN+   230.0 - 26LOBO+      230.0
 DISCONNECT BRANCH FROM BUS 235220 TO BUS 200908 CKT 1    /*01MOSHAN     230.0 - 26CHAPMAN+   230.0
 DISCONNECT BRANCH FROM BUS 236829 TO BUS 200909 CKT 81   /*01LOBO 46     46.0 - 26LOBO+      230.0
 REMOVE LOAD 1 FROM BUS 236829                            /*01LOBO 46     46.0
END
Single AC 69.93 % 105.48 % 128.0 B 135.01 45.5
NYISO/PENELEC 26E.SAYRE-N.WAV115 115.0 kV Ckt 1 line
200676 to 130836 ckt 1
Base Case Single AC 64.18 % 105.43 % 108.0 A 113.86 44.63
PENELEC 26SHELOCTA-26KEYSTONE 230.0 kV Ckt 1 line
200795 to 200810 ckt 1
PN_P4-500-002F
CONTINGENCY 'PN_P4-500-002F'
 DISCONNECT BRANCH FROM BUS 200005 TO BUS 200912 CKT 3   /*CONEM-GH     500.0 - 26CONEMAGH   230.0
 DISCONNECT BUS 200030                                   /*CONE G1       22.0
END
Breaker AC 134.76 % 136.03 % 917.0 B 1247.4 13.42
PENELEC 26SHELOCTA-26KEYSTONE 230.0 kV Ckt 1 line
200795 to 200810 ckt 1
PN_P4-500-002A
CONTINGENCY 'PN_P4-500-002A'
 DISCONNECT BRANCH FROM BUS 200005 TO BUS 200912 CKT 3   /*CONEM-GH     500.0 - 26CONEMAGH   230.0
 DISCONNECT BUS 200031                                   /*CONE G2       22.0
END
Breaker AC 134.76 % 136.03 % 917.0 B 1247.4 13.42
PENELEC 26HOMER CY-STAR599 345.0/1.0 kV Ckt N transformer
200769 to 999394 ckt N
PN-P2-3-PN-230-9E
CONTINGENCY 'PN-P2-3-PN-230-9E'
 DISCONNECT BRANCH FROM BUS 200767 TO BUS 200769 TO BUS 202641 CKT S /*26HOMER CT   230.0 - 26HOMER CY   345.0 - 26HOMERCITYS  23.0
 DISCONNECT BRANCH FROM BUS 200767 TO BUS 200837 CKT 1          /*26HOMER CT   230.0 - 26HOMER C1    20.0
 REMOVE MACHINE 1 FROM BUS 200837                               /*26HOMER C1    20.0
END
Breaker AC 117.08 % 118.8 % 807.0 B 958.72 16.63
PENELEC STAR599-26HOMER CT 1.0/230.0 kV Ckt N transformer
999394 to 200767 ckt N
PN-P2-3-PN-230-9E
CONTINGENCY 'PN-P2-3-PN-230-9E'
 DISCONNECT BRANCH FROM BUS 200767 TO BUS 200769 TO BUS 202641 CKT S /*26HOMER CT   230.0 - 26HOMER CY   345.0 - 26HOMERCITYS  23.0
 DISCONNECT BRANCH FROM BUS 200767 TO BUS 200837 CKT 1          /*26HOMER CT   230.0 - 26HOMER C1    20.0
 REMOVE MACHINE 1 FROM BUS 200837                               /*26HOMER C1    20.0
END
Breaker AC 117.0 % 118.72 % 807.0 B 958.07 16.63
PENELEC 26FOURMILE-26ERIE SE 115.0 kV Ckt 1 line
200927 to 200820 ckt 1
PN-P2-3-PN-230-6G
CONTINGENCY 'PN-P2-3-PN-230-6G'
 OPEN BUS 200819   /*26ERIE SE    230.0
 OPEN BUS 200918   /*26ERIE S TIE 230.0
END
Breaker AC 112.44 % 113.98 % 245.0 B 279.25 4.37
PENELEC 26KEYSTONE-STAR592 230.0/1.0 kV Ckt 4 transformer
200810 to 999401 ckt 4
PJM500_PN_P4-500-001A
CONTINGENCY 'PJM500_PN_P4-500-001A'
 DISCONNECT BRANCH FROM BUS 200011 TO BUS 200810 CKT 3   /*KEYSTONE     500.0 - 26KEYSTONE   230.0
 DISCONNECT BUS 200033                                   /*KEYS G2       20.0
 REMOVE MACHINE H FROM BUS 200033                        /*KEYS G2       20.0
 REMOVE MACHINE L FROM BUS 200033                        /*KEYS G2       20.0
END
Breaker AC 109.91 % 110.99 % 639.0 B 709.23 7.91
PENELEC 26KEYSTONE-STAR592 230.0/1.0 kV Ckt 4 transformer
200810 to 999401 ckt 4
PJM500_PN_P4-500-001D
CONTINGENCY 'PJM500_PN_P4-500-001D'
 DISCONNECT BRANCH FROM BUS 200011 TO BUS 200810 CKT 3   /*KEYSTONE     500.0 - 26KEYSTONE   230.0
 DISCONNECT BUS 200032                                   /*KEYS G1       20.0
 REMOVE MACHINE H FROM BUS 200032                        /*KEYS G1       20.0
 REMOVE MACHINE L FROM BUS 200032                        /*KEYS G1       20.0
END
Breaker AC 109.87 % 110.94 % 639.0 B 708.91 7.91
PENELEC STAR600-26HOMER CT 1.0/230.0 kV Ckt S transformer
999393 to 200767 ckt S
PN-P2-2-PN-230-001T
CONTINGENCY 'PN-P2-2-PN-230-001T'
 DISCONNECT BRANCH FROM BUS 200767 TO BUS 200807 CKT 1          /*26HOMER CT   230.0 - 26PIERC230   230.0
 DISCONNECT BRANCH FROM BUS 200769 TO BUS 200767 TO BUS 202640 CKT N /*26HOMER CY   345.0 - 26HOMER CT   230.0 - 26HOMERCITYN  23.0
 DISCONNECT BUS 200807                                          /*26PIERC230   230.0
 DISCONNECT BUS 200808                                          /*26PIERC138   138.0
 DISCONNECT BUS 200809                                          /*26SITHE      138.0
 REMOVE MACHINE 1 FROM BUS 200809                               /*26SITHE      138.0
END
Bus AC 98.82 % 100.5 % 824.0 B 828.12 16.6
PENELEC STAR600-26HOMER CT 1.0/230.0 kV Ckt S transformer
999393 to 200767 ckt S
PN-P2-3-PN-230-9I
CONTINGENCY 'PN-P2-3-PN-230-9I'
 DISCONNECT BRANCH FROM BUS 200767 TO BUS 200769 TO BUS 202640 CKT N /*26HOMER CT   230.0 - 26HOMER CY   345.0 - 26HOMERCITYN  23.0
 DISCONNECT BRANCH FROM BUS 200767 TO BUS 200807 CKT 1          /*26HOMER CT   230.0 - 26PIERC230   230.0
 DISCONNECT BRANCH FROM BUS 200807 TO BUS 200808 CKT 1          /*26PIERC230   230.0 - 26PIERC138   138.0
 DISCONNECT BRANCH FROM BUS 200808 TO BUS 200809 CKT 1          /*26PIERC138   138.0 - 26SITHE      138.0
 REMOVE MACHINE 1 FROM BUS 200809                               /*26SITHE      138.0
END
Breaker AC 98.82 % 100.5 % 824.0 B 828.12 16.6
PENELEC 26HOMER CY-STAR600 345.0/1.0 kV Ckt S transformer
200769 to 999393 ckt S
PN-P2-2-PN-230-001T
CONTINGENCY 'PN-P2-2-PN-230-001T'
 DISCONNECT BRANCH FROM BUS 200767 TO BUS 200807 CKT 1          /*26HOMER CT   230.0 - 26PIERC230   230.0
 DISCONNECT BRANCH FROM BUS 200769 TO BUS 200767 TO BUS 202640 CKT N /*26HOMER CY   345.0 - 26HOMER CT   230.0 - 26HOMERCITYN  23.0
 DISCONNECT BUS 200807                                          /*26PIERC230   230.0
 DISCONNECT BUS 200808                                          /*26PIERC138   138.0
 DISCONNECT BUS 200809                                          /*26SITHE      138.0
 REMOVE MACHINE 1 FROM BUS 200809                               /*26SITHE      138.0
END
Bus AC 98.74 % 100.42 % 824.0 B 827.46 16.6
PENELEC 26HOMER CY-STAR600 345.0/1.0 kV Ckt S transformer
200769 to 999393 ckt S
PN-P2-3-PN-230-9I
CONTINGENCY 'PN-P2-3-PN-230-9I'
 DISCONNECT BRANCH FROM BUS 200767 TO BUS 200769 TO BUS 202640 CKT N /*26HOMER CT   230.0 - 26HOMER CY   345.0 - 26HOMERCITYN  23.0
 DISCONNECT BRANCH FROM BUS 200767 TO BUS 200807 CKT 1          /*26HOMER CT   230.0 - 26PIERC230   230.0
 DISCONNECT BRANCH FROM BUS 200807 TO BUS 200808 CKT 1          /*26PIERC230   230.0 - 26PIERC138   138.0
 DISCONNECT BRANCH FROM BUS 200808 TO BUS 200809 CKT 1          /*26PIERC138   138.0 - 26SITHE      138.0
 REMOVE MACHINE 1 FROM BUS 200809                               /*26SITHE      138.0
END
Breaker AC 98.74 % 100.42 % 824.0 B 827.46 16.6

Light Load Analysis

The Queue Project was evaluated as a 75.0 MW (Capacity 75.0 MW) injection in the PENELEC area. Project was evaluated for compliance with applicable reliability planning criteria (PJM, NERC, NERC Regional Reliability Councils, and Transmission Owners). Potential light load period network impacts are listed below:

Important to Note:

Note for Uprate Projects: Per Tariff Part VII, Subpart B, section 304 (B), if a project is an uprate (project relies on the Interconnection Facilities of a prior project) whose base project does not qualify for the expedited process, the uprate also will not qualify for the expedited process, regardless of analysis results.

Notes regarding Results displayed:

  1. Some flowgate overloads that a New Service Request contributes to, but does not contribute enough to meet cost allocation eligibility (per Manual 14A, Attachment B.3), may be reported in this Transition Sort report. These types of flowgates do not affect the classification of the New Service Request as either Expedited Process or Transition Cycle #1 because cost allocation eligibility has not been met.
  2. For projects that were determined to not meet Expedited Process eligibility and are being reprioritized to Transition Cycle #1, not all reinforcements in excess of $5,000,000 may be shown in this report. This report may only display a subset of those reinforcements determined to be in excess of $5,000,000 which would classify the project as not meeting Expedited Process Eligibility. This is not a formal System Impact Study.
Light Load Analysis
Area Facility Description Contingency Name Contingency Type DC|AC Initial Loading Final Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Details
NYISO/PENELEC 26E.SAYRE-N.WAV115 115.0 kV Ckt 1 line
200676 to 130836 ckt 1
PN-P1-2-PN-230-101T
CONTINGENCY 'PN-P1-2-PN-230-101T'
 DISCONNECT BRANCH FROM BUS 200675 TO BUS 130763 CKT 1   /*26E.TWANDA   230.0 - HILSD230     230.0
END
Single AC 147.47 % 182.75 % 128.0 B 233.92 42.74
NYISO/PENELEC 26E.SAYRE-N.WAV115 115.0 kV Ckt 1 line
200676 to 130836 ckt 1
PN-P1-2-PN-345-104T
CONTINGENCY 'PN-P1-2-PN-345-104T'
 DISCONNECT BRANCH FROM BUS 200930 TO BUS 130757 CKT 1   /*26MAINESBURG 345.0 - WATRC345     345.0
END
Single AC 119.21 % 154.28 % 128.0 B 197.48 43.18
NYISO/PENELEC N.WAV115-26E.SAYRE 115.0 kV Ckt 1 line
130836 to 200676 ckt 1
PN-P1-3-PN-115-104
CONTINGENCY 'PN-P1-3-PN-115-104'
 DISCONNECT BRANCH FROM BUS 200676 TO BUS 200674 CKT 1   /*26E.SAYRE    115.0 - 26TOWANDA    115.0
 DISCONNECT BRANCH FROM BUS 200676 TO BUS 200882 CKT 1   /*26E.SAYRE    115.0 - 26E SAYRE2    34.5
END
Single AC 43.63 % 106.74 % 128.0 B 136.63 75.0
NYISO/PENELEC N.WAV115-26E.SAYRE 115.0 kV Ckt 1 line
130836 to 200676 ckt 1
PN-P1-2-PN-115-038
CONTINGENCY 'PN-P1-2-PN-115-038'
 DISCONNECT BRANCH FROM BUS 200674 TO BUS 200676 CKT 1   /*26TOWANDA    115.0 - 26E.SAYRE    115.0
END
Single AC 40.87 % 103.81 % 128.0 B 132.88 75.0

System Reinforcements

The table below lists all network upgrades which resolve the identified overloaded facilities in this report.

Important to Note:

Note for Uprate Projects: Per Tariff Part VII, Subpart B, section 304 (B), if a project is an uprate (project relies on the Interconnection Facilities of a prior project) whose base project does not qualify for the expedited process, the uprate also will not qualify for the expedited process, regardless of analysis results.

Notes regarding Results displayed:

  1. Some flowgate overloads that a New Service Request contributes to, but does not contribute enough to meet cost allocation eligibility (per Manual 14A, Attachment B.3), may be reported in this Transition Sort report. These types of flowgates do not affect the classification of the New Service Request as either Expedited Process or Transition Cycle #1 because cost allocation eligibility has not been met.
  2. For projects that were determined to not meet Expedited Process eligibility and are being reprioritized to Transition Cycle #1, not all reinforcements in excess of $5,000,000 may be shown in this report. This report may only display a subset of those reinforcements determined to be in excess of $5,000,000 which would classify the project as not meeting Expedited Process Eligibility. This is not a formal System Impact Study.
  3. Reinforcements previously identified by Transmission Owners for violations on lower voltage facilities are included in this report. Transmission Owner analysis will be updated as part of the Expedited Process and Transition Cycle 1 retools.
System Reinforcements
RTEP ID Title Total Cost
n6506.1 Reconductor 4.62 miles of transmission line. Replace line drops at Four Mile and Erie South substations $14,150,000
n6506.2 Replace the substation conductor at Four Mile $200,000
s2053 Replace the Homer City North 345/230-23 kV transformer with three (3) single phase units (Projected ISD 12/15/2023) $17,700,000
n8280 Replace the Homer City South 345/230 kV transformer with a larger unit $37,700,000
s2279.3 Replace line trap at Homer City on the Homer City - Shelocta 230 kV Line. $200,000
n8112 Reconductor/rebuild the Homer City - Shelocta 230 kV (~11 miles) $50,929,813
n8112.1 Adjust/replace relays at Homer City and Shelocta substations. $2,668,506
n8112.2 Replace disconnect switches and substation conductor at Homer City Substation. $3,333,312
n8112.3 Replace disconnect switches and leads at Shelocta Substation $1,744,708
s2279.2 Replace line trap at Keystone on the Keystone – Shelocta 230 kV Line. $200,000
n8192 Reconductor/rebuild the Shelocta - Keystone 230 kV line (~2.5 miles) $13,311,228
n8192.1 Adjust/replace relaying at Keystone and Shelocta substations. $2,668,506
n8192.2 Replace substation conductor at Keystone substation $1,142,812
n8192.3 Replace line drops at Keystone Substation $430,625
n8192.4 Replace bus conductor at Keystone Substation $1,142,812
n8192.5 Replace disconnect switches at Keystone Substation $2,629,706
n8192.6 Replace breaker leads at Keystone Substation $430,625
n8192.7 Replace disconnect switches and leads at Shelocta Substation $1,744,708
b3137 Rebuild 20 miles of the East Towanda - North Meshoppen 115kV line. $58,600,000
n8281 Replace the Keystone #4 500/230 kV transformer with a larger unit and install a high side breaker $41,580,000
(TBD) East Sayre-North Waverly 115kV line upgrade - NYSEG (NYISO CY17 driven upgrade) $0
n8471 East Sayre-North Waverly 115kV line upgrade - FE (NYISO CY17 driven upgrade) $0
(TBD) NYSEG would need to replace their section of the limiting conductor/equipment and provide estimates for their replacement. $0
n6815 Replace line relaying at East Sayre. $800,000
n7037 Adjust CT ratios at East Sayre $900,000
b3730 Reterminate the Lackawanna T3 and T4 500 / 230 kV transformers on the 230 kV side $10,700,000

Attachments

Conclusion

The Transition Sort load flow retool results indicate that AF2-406 is not eligible for the Expedited Process per PJM Tariff Part VII, Subpart B, section 304 (A) will be reprioritized to Transition Cycle #1. See next steps for your project in the "Introduction" section above.