AF1-116 Transition Sort Retool Results -- Qualifies for Expedited Process

v1.00 released 2023-12-14 11:12

Marion County 161 kV

72.0 MW Capacity / 120.0 MW Energy

Introduction

In accordance with Tariff Part VII, Subpart B, section 304, PJM performed load flow analysis (Transition Sort Retool) on all AE1 through AG1 projects that have met eligibility requirements according to Tariff, Part VII, Subpart B, section 303. The purpose of this study is to determine whether a project would be classified as eligible for the Expedited Process (Fast Lane) or if it would be reprioritized to be studied as part of Transition Cycle #1 (TC1) using the criteria from the Expedited Process Eligibility section of Tariff Part VII, section 304. This is not a System Impact Study report.

Below are the results of the study, how the study was performed, criterion used in the evaluation of the Expedited Process vs. TC1 determination, and next steps in the interconnection process for your project.

Eligible for Expedited Process:

The AF1-116 project has been determined to meet the initial screen to be eligible for the Expedited Process according to the Expedited Process Eligibility requirements in Tariff Part VII, Subpart B, section 304. Though your project initially screens as eligible for the Expedited Process, there are several conditions identified under Tariff Part VII, Subpart B, section 304 (B) that could shift your project from the Expedited Process into TC1. Please see "Expedited Process Rules" below.

Transition Sort Retool Study Process and Criteria:

In order to determine Expedited Process vs. Transition Cycle #1 classification, projects which met the Transition Eligibility requirements from Tariff Part VII, Subpart B, section 303 were studied on the base case model that was used for the original System Impact Study analysis. Both a summer peak and light load load flow analysis were performed. Projects that have cost allocation eligibility or are identified as the first to cause a system violation which requires the need for a Network Upgrade with a total estimated cost greater than $5 million will be reprioritized to Transition Cycle #1. All other projects will be eligible for the expedited procedures set forth in Tariff Part VII, Subpart B, section 304 (B).

Expedited Process Eligibility: OATT Tariff Part VII, section 304:

A project is not eligible for the expedited process if it has cost allocation eligibility or is identified as the first to cause, as determined according to Tariff, Part VI, section 217.3, for a Network Upgrade which has a total estimated cost of greater than $5,000,000. Such cost estimate will be based on Transmission Provider's most recently available data.

Not considered in the Transition Sorting: The cost of the Interconnection Facilities is not considered when determining a project's eligibility for the expedited process. Affected Systems upgrade costs are also not considered in the evaluation.

Transition Sort Retool Results Provided:

This report includes a list of:

  1. the overloaded flowgates (overloaded facilities + contingency pair) that the project contributes towards
  2. other interconnection projects that may also contribute to the overloaded facility, and
  3. the total estimated cost for any required Network Upgrades.

Important to Note: Some flowgate overloads that a New Service Request contributes to, but does not contribute enough to meet cost allocation eligibility (per Manual 14A, Attachment B.3), may be reported in this Transition Sort report. These types of flowgates do not affect the classification of the New Service Request as either Expedited Process or Transition Cycle #1 because cost allocation eligibility has not been met.

Next Steps for your project:

Refreshed Retool for Projects in Expedited Process:

After the initial sorting retool, PJM will conduct a refreshed analysis of the projects in the Expedited Process with the Transition Cycle #1 projects lifted from the study case model. After this refreshed analysis (including load flow, short circuit and stability analysis), retooled System Impact Study reports can be delivered to the Project Developers. Once the project's Facilities Study report is completed (and no conditions exist that would require the project to shift to TC1, see "Expedited Process Rules" below), the final GIA will be tendered along with the Facilities Study report.

Expedited Process Rules:

Though your project initially screens to be eligible for the Expedited Process, there are several conditions identified under Tariff Part VII, Subpart B, section 304 (B) that could shift your project into TC1 until the final GIA is tendered.

  • If stability analysis or a sag study is completed during the expedited process, and it is determined that a project has an estimated Network Upgrade cost greater than $5,000,000, the project will be removed from the expedited process and shifted to Transition Cycle #1.
  • If it is determined during the Facilities Study that the cost of a Network Upgrade is now estimated to be greater than $5,000,000, the project will be removed from the expedited process and shifted to Transition Cycle #1.
  • If a project is an uprate (project relies on the Interconnection Facilities of a prior project) whose base project does not qualify for the expedited process, the uprate also will not qualify for the expedited process, regardless of analysis results.
  • If the interconnected Transmission Owner identifies the need for a Network Upgrade due to a violation of their criteria that is in excess of $5M, the project will be removed from the expedited process and shifted to Transition Cycle #1.

General

The Interconnection Customer (IC), has proposed a Solar generating facility located in the EKPC zone — Washington County, Kentucky. The installed facilities will have a total capability of 120.0 MW with 72.0 MW of this output being recognized by PJM as Capacity.

Project Information
Queue Number AF1-116
Project Name Marion County 161 kV
Developer Name Logan Branch Solar, LLC
State Kentucky
County Washington
Transmission Owner EKPC
MFO 120.0 MW
MWE 120.0 MW
MWC 72.0 MW
Fuel Type Solar
Basecase Study Year 2023

Point of Interconnection

AF1-116 will interconnect on the EKPC transmission system at the Marion 161 kV substation.

Summer Peak Analysis

The Queue Project was evaluated as a 120.0 MW (Capacity 72.0 MW) injection in the EKPC area. Project was evaluated for compliance with applicable reliability planning criteria (PJM, NERC, NERC Regional Reliability Councils, and Transmission Owners). Potential Summer peak period network impacts are listed below:

Important to Note: Some flowgate overloads that a New Service Request contributes to, but does not contribute enough to meet cost allocation eligibility (per Manual 14A, Attachment B.3), may be reported in this Transition Sort report. These types of flowgates do not affect the classification of the New Service Request as either Expedited Process or Transition Cycle #1 because cost allocation eligibility has not been met.

Summer Peak Analysis
Area Facility Description Contingency Name Contingency Type DC|AC Initial Loading Final Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Details
EKPC 5MARION CO-5MARION IP T 161.0 kV Ckt 1 line
342769 to 342775 ckt 1
EKPC_P2-3_MAR W38-1014
CONTINGENCY 'EKPC_P2-3_MAR W38-1014'
 OPEN BRANCH FROM BUS 324280 TO BUS 342769 CKT 1   /*4MARION CO   138.0 - 5MARION CO   161.0
 OPEN BRANCH FROM BUS 341269 TO BUS 342703 CKT 1   /*2CASEY CO     69.0 - 5CASEY CO    161.0
 OPEN BRANCH FROM BUS 342703 TO BUS 342760 CKT 1   /*5CASEY CO    161.0 - 5LIBERTY J   161.0
 OPEN BRANCH FROM BUS 342703 TO BUS 342769 CKT 1   /*5CASEY CO    161.0 - 5MARION CO   161.0
END
Bus AC 75.16 % 162.98 % 131.0 B 213.5 120.0
EKPC 5MARION CO-5CASEY CO 161.0 kV Ckt 1 line
342769 to 342703 ckt 1
EKPC_P2-3_MAR W38-1004
CONTINGENCY 'EKPC_P2-3_MAR W38-1004'
 OPEN BRANCH FROM BUS 324280 TO BUS 342769 CKT 1   /*4MARION CO   138.0 - 5MARION CO   161.0
 OPEN BRANCH FROM BUS 342733 TO BUS 342817 CKT 1   /*5GREEN CO    161.0 - 5TAYLOR CO J 161.0
 OPEN BRANCH FROM BUS 342769 TO BUS 342775 CKT 1   /*5MARION CO   161.0 - 5MARION IP T 161.0
 OPEN BRANCH FROM BUS 342772 TO BUS 342775 CKT 1   /*5MARION IP   161.0 - 5MARION IP T 161.0
 OPEN BRANCH FROM BUS 342775 TO BUS 342805 CKT 1   /*5MARION IP T 161.0 - 5SALOMA  T   161.0
 OPEN BRANCH FROM BUS 342802 TO BUS 342805 CKT 1   /*5SALOMA      161.0 - 5SALOMA  T   161.0
 OPEN BRANCH FROM BUS 342805 TO BUS 944150 CKT 1   /*5SALOMA  T   161.0 - AF1-083 TAP  161.0
 OPEN BRANCH FROM BUS 342817 TO BUS 342818 CKT 1   /*5TAYLOR CO J 161.0 - 5TAYLRCO     161.0
END
Bus AC 64.72 % 139.34 % 153.0 B 213.19 120.0
EKPC 5MARION CO-5CASEY CO 161.0 kV Ckt 1 line
342769 to 342703 ckt 1
EKPC_P2-3_MAR W38-1004-B
CONTINGENCY 'EKPC_P2-3_MAR W38-1004-B'
 OPEN BRANCH FROM BUS 324280 TO BUS 342769 CKT 1   /*4MARION CO   138.0 - 5MARION CO   161.0
 OPEN BRANCH FROM BUS 342733 TO BUS 342817 CKT 1   /*5GREEN CO    161.0 - 5TAYLOR CO J 161.0
 OPEN BRANCH FROM BUS 342805 TO BUS 944150 CKT 1   /*5SALOMA  T   161.0 - AF1-083 TAP  161.0
 OPEN BRANCH FROM BUS 342817 TO BUS 342818 CKT 1   /*5TAYLOR CO J 161.0 - 5TAYLRCO     161.0
END
Bus AC 60.56 % 135.2 % 153.0 B 206.86 120.0
EKPC/LGEE 5COOPER2-5ELIHU 161.0 kV Ckt 1 line
342718 to 324141 ckt 1
EKPC_P2-2_LAUREL CO 161
CONTINGENCY 'EKPC_P2-2_LAUREL CO 161'
 OPEN BUS 342754   /*5LAUREL CO   161.0
END
Bus AC 109.24 % 116.25 % 277.0 B 322.01 18.88
EKPC 5CASEY CO-5LIBERTY J 161.0 kV Ckt 1 line
342703 to 342760 ckt 1
EKPC_P2-3_MAR W38-1004
CONTINGENCY 'EKPC_P2-3_MAR W38-1004'
 OPEN BRANCH FROM BUS 324280 TO BUS 342769 CKT 1   /*4MARION CO   138.0 - 5MARION CO   161.0
 OPEN BRANCH FROM BUS 342733 TO BUS 342817 CKT 1   /*5GREEN CO    161.0 - 5TAYLOR CO J 161.0
 OPEN BRANCH FROM BUS 342769 TO BUS 342775 CKT 1   /*5MARION CO   161.0 - 5MARION IP T 161.0
 OPEN BRANCH FROM BUS 342772 TO BUS 342775 CKT 1   /*5MARION IP   161.0 - 5MARION IP T 161.0
 OPEN BRANCH FROM BUS 342775 TO BUS 342805 CKT 1   /*5MARION IP T 161.0 - 5SALOMA  T   161.0
 OPEN BRANCH FROM BUS 342802 TO BUS 342805 CKT 1   /*5SALOMA      161.0 - 5SALOMA  T   161.0
 OPEN BRANCH FROM BUS 342805 TO BUS 944150 CKT 1   /*5SALOMA  T   161.0 - AF1-083 TAP  161.0
 OPEN BRANCH FROM BUS 342817 TO BUS 342818 CKT 1   /*5TAYLOR CO J 161.0 - 5TAYLRCO     161.0
END
Bus AC 49.82 % 116.9 % 153.0 B 178.86 106.11
EKPC 5CASEY CO-5LIBERTY J 161.0 kV Ckt 1 line
342703 to 342760 ckt 1
EKPC_P2-3_MAR W38-1004-B
CONTINGENCY 'EKPC_P2-3_MAR W38-1004-B'
 OPEN BRANCH FROM BUS 324280 TO BUS 342769 CKT 1   /*4MARION CO   138.0 - 5MARION CO   161.0
 OPEN BRANCH FROM BUS 342733 TO BUS 342817 CKT 1   /*5GREEN CO    161.0 - 5TAYLOR CO J 161.0
 OPEN BRANCH FROM BUS 342805 TO BUS 944150 CKT 1   /*5SALOMA  T   161.0 - AF1-083 TAP  161.0
 OPEN BRANCH FROM BUS 342817 TO BUS 342818 CKT 1   /*5TAYLOR CO J 161.0 - 5TAYLRCO     161.0
END
Bus AC 46.09 % 113.17 % 153.0 B 173.15 106.11
EKPC AE2-254 TAP-2GARRARD CO 69.0 kV Ckt 1 line
942410 to 341515 ckt 1
EKPC_P2-3_MAR W38-1004
CONTINGENCY 'EKPC_P2-3_MAR W38-1004'
 OPEN BRANCH FROM BUS 324280 TO BUS 342769 CKT 1   /*4MARION CO   138.0 - 5MARION CO   161.0
 OPEN BRANCH FROM BUS 342733 TO BUS 342817 CKT 1   /*5GREEN CO    161.0 - 5TAYLOR CO J 161.0
 OPEN BRANCH FROM BUS 342769 TO BUS 342775 CKT 1   /*5MARION CO   161.0 - 5MARION IP T 161.0
 OPEN BRANCH FROM BUS 342772 TO BUS 342775 CKT 1   /*5MARION IP   161.0 - 5MARION IP T 161.0
 OPEN BRANCH FROM BUS 342775 TO BUS 342805 CKT 1   /*5MARION IP T 161.0 - 5SALOMA  T   161.0
 OPEN BRANCH FROM BUS 342802 TO BUS 342805 CKT 1   /*5SALOMA      161.0 - 5SALOMA  T   161.0
 OPEN BRANCH FROM BUS 342805 TO BUS 944150 CKT 1   /*5SALOMA  T   161.0 - AF1-083 TAP  161.0
 OPEN BRANCH FROM BUS 342817 TO BUS 342818 CKT 1   /*5TAYLOR CO J 161.0 - 5TAYLRCO     161.0
END
Bus AC 97.03 % 114.45 % 63.0 B 72.1 13.95
EKPC AE2-254 TAP-2GARRARD CO 69.0 kV Ckt 1 line
942410 to 341515 ckt 1
EKPC_P2-3_MAR W38-1004-B
CONTINGENCY 'EKPC_P2-3_MAR W38-1004-B'
 OPEN BRANCH FROM BUS 324280 TO BUS 342769 CKT 1   /*4MARION CO   138.0 - 5MARION CO   161.0
 OPEN BRANCH FROM BUS 342733 TO BUS 342817 CKT 1   /*5GREEN CO    161.0 - 5TAYLOR CO J 161.0
 OPEN BRANCH FROM BUS 342805 TO BUS 944150 CKT 1   /*5SALOMA  T   161.0 - AF1-083 TAP  161.0
 OPEN BRANCH FROM BUS 342817 TO BUS 342818 CKT 1   /*5TAYLOR CO J 161.0 - 5TAYLRCO     161.0
END
Bus AC 96.12 % 113.66 % 63.0 B 71.61 13.95
EKPC 5GREEN CO-2GREEN CO 161.0/69.0 kV Ckt 1 transformer
342733 to 341563 ckt 1
EKPC_P2-3_MAR W38-1014
CONTINGENCY 'EKPC_P2-3_MAR W38-1014'
 OPEN BRANCH FROM BUS 324280 TO BUS 342769 CKT 1   /*4MARION CO   138.0 - 5MARION CO   161.0
 OPEN BRANCH FROM BUS 341269 TO BUS 342703 CKT 1   /*2CASEY CO     69.0 - 5CASEY CO    161.0
 OPEN BRANCH FROM BUS 342703 TO BUS 342760 CKT 1   /*5CASEY CO    161.0 - 5LIBERTY J   161.0
 OPEN BRANCH FROM BUS 342703 TO BUS 342769 CKT 1   /*5CASEY CO    161.0 - 5MARION CO   161.0
END
Bus AC 92.82 % 111.75 % 84.0 B 93.87 16.68
EKPC/LGEE 5TAYLOR CO J-5TAYLRCO 161.0 kV Ckt 1 line
342817 to 342818 ckt 1
EKPC_P2-3_MAR W38-1014
CONTINGENCY 'EKPC_P2-3_MAR W38-1014'
 OPEN BRANCH FROM BUS 324280 TO BUS 342769 CKT 1   /*4MARION CO   138.0 - 5MARION CO   161.0
 OPEN BRANCH FROM BUS 341269 TO BUS 342703 CKT 1   /*2CASEY CO     69.0 - 5CASEY CO    161.0
 OPEN BRANCH FROM BUS 342703 TO BUS 342760 CKT 1   /*5CASEY CO    161.0 - 5LIBERTY J   161.0
 OPEN BRANCH FROM BUS 342703 TO BUS 342769 CKT 1   /*5CASEY CO    161.0 - 5MARION CO   161.0
END
Bus AC 85.8 % 109.93 % 105.0 B 115.43 27.73
EKPC 2GREEN CO-2SUMMERSVIL 69.0 kV Ckt 1 line
341563 to 342325 ckt 1
EKPC_P2-3_MAR W38-1014
CONTINGENCY 'EKPC_P2-3_MAR W38-1014'
 OPEN BRANCH FROM BUS 324280 TO BUS 342769 CKT 1   /*4MARION CO   138.0 - 5MARION CO   161.0
 OPEN BRANCH FROM BUS 341269 TO BUS 342703 CKT 1   /*2CASEY CO     69.0 - 5CASEY CO    161.0
 OPEN BRANCH FROM BUS 342703 TO BUS 342760 CKT 1   /*5CASEY CO    161.0 - 5LIBERTY J   161.0
 OPEN BRANCH FROM BUS 342703 TO BUS 342769 CKT 1   /*5CASEY CO    161.0 - 5MARION CO   161.0
END
Bus AC 75.21 % 103.01 % 39.0 B 40.17 12.76
EKPC 5MARION CO-5MARION IP T 161.0 kV Ckt 1 line
342769 to 342775 ckt 1
EKPC_P4-2_MAR W38-1014
CONTINGENCY 'EKPC_P4-2_MAR W38-1014'
 OPEN BRANCH FROM BUS 324280 TO BUS 342769 CKT 1   /*4MARION CO   138.0 - 5MARION CO   161.0
 OPEN BRANCH FROM BUS 341269 TO BUS 342703 CKT 1   /*2CASEY CO     69.0 - 5CASEY CO    161.0
 OPEN BRANCH FROM BUS 342703 TO BUS 342760 CKT 1   /*5CASEY CO    161.0 - 5LIBERTY J   161.0
 OPEN BRANCH FROM BUS 342703 TO BUS 342769 CKT 1   /*5CASEY CO    161.0 - 5MARION CO   161.0
END
Breaker AC 75.16 % 162.98 % 131.0 B 213.5 120.0
EKPC 5MARION CO-5CASEY CO 161.0 kV Ckt 1 line
342769 to 342703 ckt 1
EKPC_P4-2_MAR W38-1004
CONTINGENCY 'EKPC_P4-2_MAR W38-1004'
 OPEN BRANCH FROM BUS 324280 TO BUS 342769 CKT 1   /*4MARION CO   138.0 - 5MARION CO   161.0
 OPEN BRANCH FROM BUS 342769 TO BUS 342775 CKT 1   /*5MARION CO   161.0 - 5MARION IP T 161.0
 OPEN BRANCH FROM BUS 342772 TO BUS 342775 CKT 1   /*5MARION IP   161.0 - 5MARION IP T 161.0
 OPEN BRANCH FROM BUS 342775 TO BUS 342805 CKT 1   /*5MARION IP T 161.0 - 5SALOMA  T   161.0
 OPEN BRANCH FROM BUS 342802 TO BUS 342805 CKT 1   /*5SALOMA      161.0 - 5SALOMA  T   161.0
 OPEN BRANCH FROM BUS 342805 TO BUS 944150 CKT 1   /*5SALOMA  T   161.0 - AF1-083 TAP  161.0
END
Breaker AC 64.73 % 139.34 % 153.0 B 213.19 120.0
EKPC/LGEE 5COOPER2-5ELIHU 161.0 kV Ckt 1 line
342718 to 324141 ckt 1
EKPC_P4-5_LAURL S50-1024
CONTINGENCY 'EKPC_P4-5_LAURL S50-1024'
 OPEN BRANCH FROM BUS 324688 TO BUS 342781 CKT 1   /*2PITTSBRG KU  69.0 - 5PITTSBURG   161.0
 OPEN BRANCH FROM BUS 342781 TO BUS 342820 CKT 1   /*5PITTSBURG   161.0 - 5TYNER       161.0
 OPEN BUS 342754                                   /*5LAUREL CO   161.0
END
Breaker AC 109.53 % 116.52 % 277.0 B 322.76 18.86
EKPC/LGEE 5COOPER2-5ELIHU 161.0 kV Ckt 1 line
342718 to 324141 ckt 1
EKPC_P4-5_LAURL S50-1014
CONTINGENCY 'EKPC_P4-5_LAURL S50-1014'
 OPEN BUS 342754   /*5LAUREL CO   161.0
END
Breaker AC 109.24 % 116.25 % 277.0 B 322.01 18.88
EKPC 5CASEY CO-5LIBERTY J 161.0 kV Ckt 1 line
342703 to 342760 ckt 1
EKPC_P4-2_MAR W38-1004
CONTINGENCY 'EKPC_P4-2_MAR W38-1004'
 OPEN BRANCH FROM BUS 324280 TO BUS 342769 CKT 1   /*4MARION CO   138.0 - 5MARION CO   161.0
 OPEN BRANCH FROM BUS 342769 TO BUS 342775 CKT 1   /*5MARION CO   161.0 - 5MARION IP T 161.0
 OPEN BRANCH FROM BUS 342772 TO BUS 342775 CKT 1   /*5MARION IP   161.0 - 5MARION IP T 161.0
 OPEN BRANCH FROM BUS 342775 TO BUS 342805 CKT 1   /*5MARION IP T 161.0 - 5SALOMA  T   161.0
 OPEN BRANCH FROM BUS 342802 TO BUS 342805 CKT 1   /*5SALOMA      161.0 - 5SALOMA  T   161.0
 OPEN BRANCH FROM BUS 342805 TO BUS 944150 CKT 1   /*5SALOMA  T   161.0 - AF1-083 TAP  161.0
END
Breaker AC 49.85 % 116.92 % 153.0 B 178.89 106.11
EKPC AE2-254 TAP-2GARRARD CO 69.0 kV Ckt 1 line
942410 to 341515 ckt 1
EKPC_P4-2_MAR W38-1004
CONTINGENCY 'EKPC_P4-2_MAR W38-1004'
 OPEN BRANCH FROM BUS 324280 TO BUS 342769 CKT 1   /*4MARION CO   138.0 - 5MARION CO   161.0
 OPEN BRANCH FROM BUS 342769 TO BUS 342775 CKT 1   /*5MARION CO   161.0 - 5MARION IP T 161.0
 OPEN BRANCH FROM BUS 342772 TO BUS 342775 CKT 1   /*5MARION IP   161.0 - 5MARION IP T 161.0
 OPEN BRANCH FROM BUS 342775 TO BUS 342805 CKT 1   /*5MARION IP T 161.0 - 5SALOMA  T   161.0
 OPEN BRANCH FROM BUS 342802 TO BUS 342805 CKT 1   /*5SALOMA      161.0 - 5SALOMA  T   161.0
 OPEN BRANCH FROM BUS 342805 TO BUS 944150 CKT 1   /*5SALOMA  T   161.0 - AF1-083 TAP  161.0
END
Breaker AC 96.41 % 113.99 % 63.0 B 71.81 13.95
EKPC 5GREEN CO-2GREEN CO 161.0/69.0 kV Ckt 1 transformer
342733 to 341563 ckt 1
EKPC_P4-2_MAR W38-1014
CONTINGENCY 'EKPC_P4-2_MAR W38-1014'
 OPEN BRANCH FROM BUS 324280 TO BUS 342769 CKT 1   /*4MARION CO   138.0 - 5MARION CO   161.0
 OPEN BRANCH FROM BUS 341269 TO BUS 342703 CKT 1   /*2CASEY CO     69.0 - 5CASEY CO    161.0
 OPEN BRANCH FROM BUS 342703 TO BUS 342760 CKT 1   /*5CASEY CO    161.0 - 5LIBERTY J   161.0
 OPEN BRANCH FROM BUS 342703 TO BUS 342769 CKT 1   /*5CASEY CO    161.0 - 5MARION CO   161.0
END
Breaker AC 92.82 % 111.75 % 84.0 B 93.87 16.68
EKPC/LGEE 5TAYLOR CO J-5TAYLRCO 161.0 kV Ckt 1 line
342817 to 342818 ckt 1
EKPC_P4-2_MAR W38-1014
CONTINGENCY 'EKPC_P4-2_MAR W38-1014'
 OPEN BRANCH FROM BUS 324280 TO BUS 342769 CKT 1   /*4MARION CO   138.0 - 5MARION CO   161.0
 OPEN BRANCH FROM BUS 341269 TO BUS 342703 CKT 1   /*2CASEY CO     69.0 - 5CASEY CO    161.0
 OPEN BRANCH FROM BUS 342703 TO BUS 342760 CKT 1   /*5CASEY CO    161.0 - 5LIBERTY J   161.0
 OPEN BRANCH FROM BUS 342703 TO BUS 342769 CKT 1   /*5CASEY CO    161.0 - 5MARION CO   161.0
END
Breaker AC 85.8 % 109.93 % 105.0 B 115.43 27.73
EKPC 2GREEN CO-2SUMMERSVIL 69.0 kV Ckt 1 line
341563 to 342325 ckt 1
EKPC_P4-2_MAR W38-1014
CONTINGENCY 'EKPC_P4-2_MAR W38-1014'
 OPEN BRANCH FROM BUS 324280 TO BUS 342769 CKT 1   /*4MARION CO   138.0 - 5MARION CO   161.0
 OPEN BRANCH FROM BUS 341269 TO BUS 342703 CKT 1   /*2CASEY CO     69.0 - 5CASEY CO    161.0
 OPEN BRANCH FROM BUS 342703 TO BUS 342760 CKT 1   /*5CASEY CO    161.0 - 5LIBERTY J   161.0
 OPEN BRANCH FROM BUS 342703 TO BUS 342769 CKT 1   /*5CASEY CO    161.0 - 5MARION CO   161.0
END
Breaker AC 75.21 % 103.01 % 39.0 B 40.17 12.76
EKPC/LGEE 5COOPER2-5ELIHU 161.0 kV Ckt 1 line
342718 to 324141 ckt 1
EKPC_P1-2_LAUR-L DAM161
CONTINGENCY 'EKPC_P1-2_LAUR-L DAM161'
 OPEN BRANCH FROM BUS 342754 TO BUS 342757 CKT 1   /*5LAUREL CO   161.0 - 5LAUREL DAM  161.0
END
Single AC 101.54 % 105.76 % 277.0 B 292.96 11.34
EKPC 5LAUREL DAM-5LAUREL CO 161.0 kV Ckt 1 line
342757 to 342754 ckt 1
EKPC_P1-2_COOP-ELIHU161
CONTINGENCY 'EKPC_P1-2_COOP-ELIHU161'
 OPEN BRANCH FROM BUS 324141 TO BUS 342718 CKT 1   /*5ELIHU       161.0 - 5COOPER2     161.0
END
Single AC 98.83 % 101.24 % 200.0 B 202.48 4.62
EKPC/LGEE 2SOMERSET KU-2FERGUSON SO 69.0 kV Ckt 1 line
342287 to 324531 ckt 1
EKPC_P7-1_COOP 161 DBL 2
CONTINGENCY 'EKPC_P7-1_COOP 161 DBL 2'
 OPEN BRANCH FROM BUS 324141 TO BUS 342718 CKT 1   /*5ELIHU       161.0 - 5COOPER2     161.0
 OPEN BRANCH FROM BUS 342718 TO BUS 342757 CKT 1   /*5COOPER2     161.0 - 5LAUREL DAM  161.0
END
Tower AC 118.5 % 130.26 % 105.0 B 136.77 12.1
EKPC/LGEE 5COOPER2-5ELIHU 161.0 kV Ckt 1 line
342718 to 324141 ckt 1
EKPC_P7-1_LAURL 161 DBL
CONTINGENCY 'EKPC_P7-1_LAURL 161 DBL'
 OPEN BRANCH FROM BUS 342754 TO BUS 342757 CKT 1   /*5LAUREL CO   161.0 - 5LAUREL DAM  161.0
 OPEN BRANCH FROM BUS 342754 TO BUS 342781 CKT 1   /*5LAUREL CO   161.0 - 5PITTSBURG   161.0
 OPEN BRANCH FROM BUS 342781 TO BUS 342820 CKT 1   /*5PITTSBURG   161.0 - 5TYNER       161.0
END
Tower AC 109.53 % 116.52 % 277.0 B 322.76 18.86
EKPC 2SOMERSET-2SOMERSET KU 69.0 kV Ckt 1 line
342286 to 342287 ckt 1
EKPC_P7-1_COOP 161 DBL 2
CONTINGENCY 'EKPC_P7-1_COOP 161 DBL 2'
 OPEN BRANCH FROM BUS 324141 TO BUS 342718 CKT 1   /*5ELIHU       161.0 - 5COOPER2     161.0
 OPEN BRANCH FROM BUS 342718 TO BUS 342757 CKT 1   /*5COOPER2     161.0 - 5LAUREL DAM  161.0
END
Tower AC 107.0 % 115.93 % 115.0 B 133.32 11.74
EKPC 5COOPER1-2COOPER 161.0/69.0 kV Ckt 1 transformer
342715 to 341344 ckt 1
EKPC_P7-1_COOP 161 DBL 2
CONTINGENCY 'EKPC_P7-1_COOP 161 DBL 2'
 OPEN BRANCH FROM BUS 324141 TO BUS 342718 CKT 1   /*5ELIHU       161.0 - 5COOPER2     161.0
 OPEN BRANCH FROM BUS 342718 TO BUS 342757 CKT 1   /*5COOPER2     161.0 - 5LAUREL DAM  161.0
END
Tower AC 98.67 % 103.57 % 152.0 B 157.43 7.38

Light Load Analysis

At this time light load analysis not required for this project.

System Reinforcements

The table below lists all network upgrades which resolve the identified overloaded facilities in this report.

Important to Note: Some flowgate overloads that a New Service Request contributes to, but does not contribute enough to meet cost allocation eligibility (per Manual 14A, Attachment B.3), may be reported in this Transition Sort report. These types of flowgates do not affect the classification of the New Service Request as either Expedited Process or Transition Cycle #1 because cost allocation eligibility has not been met.

Reinforcements previously identified by Transmission Owners for violations on lower voltage facilities are included in this report. Transmission Owner analysis will be updated as part of the Expedited Process and Transition Cycle 1 retools.

System Reinforcements
RTEP ID Title Total Cost
n8371 Change the setting of the 69 kV current transformer associated with the Cooper 161/69 kV transformer to at least 800 amps $10,000
(TBD) EKPC emergency rating is 152 MVA. $0
n6830 Increase the maximum operating temperature of the 266 MCM ACSR conductor in the Garrard County-Ae2-254 Tap 69 kV line section to 266 degrees F (0.25 miles) $20,000
n6834 Increase the maximum operating temperature of the 4/0 ACSR conductor in the Green County-Summersville 69 kV line section to 212 degrees F (4.2 miles) $280,000
b3047 Upgrade the existing 4/0 CU line jumpers with double 500 MCM CU associated [...] ect switches with 1200 A associated with the Green Co 161/69 KV transformer $250,000
n6232 Replace the 500 MCM copper jumpers at the Somerset substation using 750 MCM copper or equivalent $250,000
n6833 Change the Zone 3 relay setting at Casey County associated with the line protection to at least 182 MVA LTE rating. $0
n6832.1 Change the Zone 3 relay setting at Casey County associated with the line protection to at least 256 MVA LTE rating. $0
n6832.2 Increase the maximum operating temperature of the 636 MCM ACSR conductor in the Marion County-Casey County 161 kV line section to 212 degrees F (17.2 miles) $1,680,000
(TBD) EKPC emergency rating 298 MVA. $0
n8368.1 Increase the maximum operating temperature of the 795 MCM ACSR conductor in the Cooper-Elihu 161 kV line section to 275 degrees F (6.7 miles) $680,000
n7771.1 Increase the maximum operating temperature of the Laurel County-Laurel Dam 161 kV line section 795 MCM conductor to 167 degrees F (~0.2 miles) $35,000
n6831 Increase the maximum operating temperature of the Marion County-Marion County Industrial 161 kV line section 795 MCM conductor to 176 degrees F (4.0 miles) $390,000
(TBD) LGEE violation (non PJM area). EKPC emergency rating is 381 MVA. The extern [...] Owner, LGEE, will not evaluate this violation until the impact study phase. $0

Attachments

Conclusion

The Transition Sort load flow retool results indicate that AF1-116 is eligible for the Expedited Process per PJM Tariff Part VII, Subpart B, section 304 (A). See next steps for your project in the "Introduction" section above.